Volume 2-05, Chapter 3 - City of Wichita
Volume 2-05, Chapter 3 - City of Wichita Volume 2-05, Chapter 3 - City of Wichita
Section 3.2.10 - Stormwater Wetland planting sites and backfill these with uncompacted topsoil. However, these features must not be located within the tree exclusion area, and must not violate the groundwater clearance requirements. J. ADDITIONAL SITE-SPECIFIC DESIGN CRITERIA AND ISSUES Physiographic Factors - Local terrain design constraints Low Relief: Providing wetland drain can be problematic. High Relief: Embankment heights restricted Karst: Requires poly or clay liner to sustain a permanent pool of water and protect aquifers; limits on ponding depth; geotechnical tests may be required. Soils • Hydrologic group ‘A’ soils and some group ‘B’ soils may require liner. Special Downstream Watershed Considerations Aquifer Protection: Inflow of untreated hotspot runoff not permitted. May require liner for type “A” and some “B” soils. Five foot minimum clearance above historical high groundwater for unlined wetlands, 2 feet for lined. 3.2.10.6 Design Procedures Step 1 Step 2 Step 3 Step 4 Compute runoff control volumes from the integrated design approach. Calculate the WQ v . See Chapter 1 and Chapter 4. Confirm local design criteria and applicability. Consider any special site-specific design conditions/criteria. Check with local officials and other agencies to determine if there are any additional restrictions and/or surface water or watershed requirements that may apply. Determine pretreatment volume A sediment forebay is provided at each inlet, unless the inlet provides less than 10% of the total design storm inflow to the pond. The forebay should be sized to contain 0.1 acre-inch per impervious acre of contributing drainage and should be 4 to 6 feet deep. The forebay storage volume counts toward the total WQ v requirement and may be subtracted from the WQ v for subsequent calculations. Allocate the WQv volume among marsh, micropool, and extended detention volumes. Page 3 - 138 Volume 2, Technical Guidance
Section 3.2.10 - Stormwater Wetland Use recommended criteria from Table 3-8. Step 5 Step 6 Step 7 Step 8 Step 9 Determine wetland location and preliminary geometry, including distribution of wetland depth zones. This step involves initially laying out the wetland design and determining the distribution of wetland surface area among the various depth zones (high marsh, low marsh, and deepwater). Set WQ v permanent pool elevation (and WQ v -ED elevation for extended detention shallow wetland) based on volumes calculated earlier. Compute extended detention orifice release rate(s) and size(s), and establish CP v elevation. Shallow Wetland: The CP v elevation is determined from the stage-storage relationship and the orifice is then sized to release the channel protection storage volume over a 24 hour period. The channel protection orifice shall be adequately protected from clogging by an acceptable treatment as shown in Chapter 5, or a similar treatment at the discretion of the site engineer. A reverse slope pipe attached to the riser, with its inlet submerged 1 foot below the elevation of the permanent pool is a recommended design. ED Shallow Wetland: Based on the elevations established in Step 5 for the extended detention portion of the WQ V , the water quality orifice is sized to release this extended detention volume in 24 hours. The water quality orifice shall be adequately protected from clogging by an acceptable treatment as shown in Chapter 5, or a similar treatment at the discretion of the site engineer. A reverse slope pipe attached to the riser, with its inlet submerged one foot below the elevation of the permanent pool, is a recommended design. The CP v elevation is then determined from the stage-storage relationship. The invert of the channel protection orifice is located at the water quality extended detention elevation, and the orifice is sized to release the channel protection storage volume over a 24 hour period. Calculate the flood control release rates and water surface elevations. Set up a stage-storage-discharge relationship for the control structure for the extended detention orifice(s) and the flood control storms. Route floods through facility and adjust accordingly to achieve peak flow control. Design embankment(s) and spillway(s). Size the emergency spillway by routing 100-year flood through the spillway in accordance with the previously discussed criteria. Set the top of dam elevation based on a minimum of 1 foot of freeboard. At final design, provide safe passage for the 100-year event. Investigate potential pond/wetland hazard classification. Volume 2, Technical Guidance Page 3 - 139
- Page 93 and 94: Section 3.2.6 - Infiltration Trench
- Page 95 and 96: Section 3.2.6 - Infiltration Trench
- Page 97 and 98: Section 3.2.6 - Infiltration Trench
- Page 99 and 100: Section 3.2.7 - Soakage Trench 3.2.
- Page 101 and 102: Section 3.2.7 - Soakage Trench •
- Page 103 and 104: Section 3.2.8 - Surface Sand Filter
- Page 105 and 106: Section 3.2.8 - Surface Sand Filter
- Page 107 and 108: Section 3.2.8 - Surface Sand Filter
- Page 109 and 110: Section 3.2.8 - Surface Sand Filter
- Page 111 and 112: Section 3.2.8 - Surface Sand Filter
- Page 113 and 114: Section 3.2.8 - Surface Sand Filter
- Page 115 and 116: Section 3.2.8 - Surface Sand Filter
- Page 117 and 118: Section 3.2.9 - Bioretention Areas
- Page 119 and 120: Section 3.2.9 - Bioretention Areas
- Page 121 and 122: Section 3.2.9 - Bioretention Areas
- Page 123 and 124: Section 3.2.9 - Bioretention Areas
- Page 125 and 126: Section 3.2.9 - Bioretention Areas
- Page 127 and 128: Section 3.2.9 - Bioretention Areas
- Page 129 and 130: Section 3.2.9 - Bioretention Areas
- Page 131 and 132: Section 3.2.9 - Bioretention Areas
- Page 133 and 134: Section 3.2.10 - Stormwater Wetland
- Page 135 and 136: Section 3.2.10 - Stormwater Wetland
- Page 137 and 138: Section 3.2.10 - Stormwater Wetland
- Page 139 and 140: Section 3.2.10 - Stormwater Wetland
- Page 141 and 142: Section 3.2.10 - Stormwater Wetland
- Page 143: Section 3.2.10 - Stormwater Wetland
- Page 147 and 148: Section 3.2.10 - Stormwater Wetland
- Page 149 and 150: Section 3.2.10 - Stormwater Wetland
- Page 151 and 152: Section 3.3 - Secondary TSS Treatme
- Page 153 and 154: Section 3.3.1 - Proprietary Treatme
- Page 155 and 156: Section 3.3.1 - Proprietary Treatme
- Page 157 and 158: Section 3.3.2 - Gravity (Oil-Water)
- Page 159 and 160: Section 3.3.2 - Gravity (Oil-Water)
- Page 161 and 162: Section 3.3.2 - Gravity (Oil-Water)
- Page 163 and 164: Section 3.3.3 - Alum Treatment 3.3.
- Page 165 and 166: Section 3.3.3 - Alum Treatment •
- Page 167 and 168: Section 3.3.4 - Underground Sand Fi
- Page 169 and 170: Section 3.3.4 - Underground Sand Fi
- Page 171 and 172: Section 3.3.4 - Underground Sand Fi
- Page 173 and 174: Section 3.3.4 - Underground Sand Fi
- Page 175 and 176: Section 3.3.4 - Underground Sand Fi
- Page 177 and 178: Section 3.3.4 - Underground Sand Fi
- Page 179 and 180: Section 3.3.4 - Underground Sand Fi
- Page 181 and 182: Section 3.3.5 - Organic Filter 3.3.
- Page 183 and 184: Section 3.3.5 - Organic Filter •
- Page 185 and 186: Section 3.4 - Other Stormwater Mana
- Page 187 and 188: Section 3.4.1 - Conventional Dry De
- Page 189 and 190: Section 3.4.1 - Conventional Dry De
- Page 191 and 192: Section 3.4.1 - Conventional Dry De
- Page 193 and 194: Section 3.4.2 - Underground Dry Det
Section 3.2.10 - Stormwater Wetland<br />
Use recommended criteria from Table 3-8.<br />
Step 5<br />
Step 6<br />
Step 7<br />
Step 8<br />
Step 9<br />
Determine wetland location and preliminary geometry, including distribution <strong>of</strong><br />
wetland depth zones.<br />
This step involves initially laying out the wetland design and determining the<br />
distribution <strong>of</strong> wetland surface area among the various depth zones (high marsh, low<br />
marsh, and deepwater). Set WQ v permanent pool elevation (and WQ v -ED elevation<br />
for extended detention shallow wetland) based on volumes calculated earlier.<br />
Compute extended detention orifice release rate(s) and size(s), and establish CP v<br />
elevation.<br />
Shallow Wetland: The CP v elevation is determined from the stage-storage<br />
relationship and the orifice is then sized to release the channel protection storage<br />
volume over a 24 hour period. The channel protection orifice shall be adequately<br />
protected from clogging by an acceptable treatment as shown in <strong>Chapter</strong> 5, or a<br />
similar treatment at the discretion <strong>of</strong> the site engineer. A reverse slope pipe attached<br />
to the riser, with its inlet submerged 1 foot below the elevation <strong>of</strong> the permanent pool<br />
is a recommended design.<br />
ED Shallow Wetland: Based on the elevations established in Step 5 for the<br />
extended detention portion <strong>of</strong> the WQ V , the water quality orifice is sized to release<br />
this extended detention volume in 24 hours. The water quality orifice shall be<br />
adequately protected from clogging by an acceptable treatment as shown in <strong>Chapter</strong><br />
5, or a similar treatment at the discretion <strong>of</strong> the site engineer. A reverse slope pipe<br />
attached to the riser, with its inlet submerged one foot below the elevation <strong>of</strong> the<br />
permanent pool, is a recommended design. The CP v elevation is then determined<br />
from the stage-storage relationship. The invert <strong>of</strong> the channel protection orifice is<br />
located at the water quality extended detention elevation, and the orifice is sized to<br />
release the channel protection storage volume over a 24 hour period.<br />
Calculate the flood control release rates and water surface elevations.<br />
Set up a stage-storage-discharge relationship for the control structure for the<br />
extended detention orifice(s) and the flood control storms. Route floods through<br />
facility and adjust accordingly to achieve peak flow control.<br />
Design embankment(s) and spillway(s).<br />
Size the emergency spillway by routing 100-year flood through the spillway in<br />
accordance with the previously discussed criteria. Set the top <strong>of</strong> dam elevation<br />
based on a minimum <strong>of</strong> 1 foot <strong>of</strong> freeboard.<br />
At final design, provide safe passage for the 100-year event.<br />
Investigate potential pond/wetland hazard classification.<br />
<strong>Volume</strong> 2, Technical Guidance Page 3 - 139