CORRIGENDUM No. 2 - Yap State Government
CORRIGENDUM No. 2 - Yap State Government
CORRIGENDUM No. 2 - Yap State Government
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
(ii). Clarification Request #35:<br />
Since the panels will be installed outside and the controller inside, do we have to provide disconnect<br />
switches at the Array and also before the Charge Controller Entry. This means 2 disconnection points<br />
between the PV Array and Charge Controller. Please confirm.<br />
Response:<br />
Refer to the tender specifications for your systems designs for installation. These systems are to be<br />
packaged component stand-alone outside compact systems which are to be installed as complete units<br />
externally from the location being served by each system. All NEC guidelines must be followed as needed<br />
for design. Follow the instructions and you can include changes and/or additions in your design for<br />
evaluation.<br />
(jj). Clarification Request #36:<br />
As per the NEC guidelines, we can isolate one conductor and ground the other conductor or isolate both<br />
current carrying conductors by using appropriate circuit breakers. Please confirm if we can to supply these<br />
isolators / disconnection devices with this tender<br />
Response:<br />
All NEC and SEIAPI technical guidelines must be followed for design of stand-alone system. The guidelines<br />
are available online and have been attached with this email. The tenderer must design the system<br />
following these guidelines.<br />
(kk). Clarification Request #37:<br />
We have a question regarding the mounting structures for the modules.<br />
Will they be rammed into the ground or will there be a concrete foundation<br />
Response:<br />
The systems will be installed on concrete poles. The poles will be prepared by YSPSC but the tenderer<br />
proposal must provide the technical drawings for the poles along with the mounting requirements for the<br />
system/s that they are proposing.<br />
(ll). Clarification Request #38:<br />
Since SCS will be installed outside (compact installation)<br />
please confirm if both the controllers, inverters and all other accessories to be installed outside<br />
Response:<br />
SCS to be outside and please refer to the complete tender dossier and especially the documents of<br />
“Instruction for Tenderers” long with “Annex II” for definition of “PV solar packages” and “complete”<br />
system for both the SCS/SHS. All system components to be included with such.<br />
(mm). Clarification Request #39:<br />
Is SHS also a compact system with controllers and inverters mounted outdoors<br />
Response:<br />
Correct and again please refer to tender document Annex II item “h).” which provides guide to the region<br />
and conditions of the where these systems will be installed. Reference to “<strong>Yap</strong>, Federated <strong>State</strong>s of<br />
Micronesia” is made and which also encompasses the outer islands of the state of <strong>Yap</strong>, FSM. Research and<br />
becoming familiar with this region and the conditions that can be encountered is strongly encouraged.<br />
(nn). Clarification Request #40:<br />
Confirmation on Tender Guarantee<br />
If TG is submitted in another form, say Bank Guarantee or Bank Draft, will the company be disqualified<br />
from the tendering process