Response:<br />
The CD has to contain all submitted documents from the tenderer.<br />
(e). Clarification Request #5:<br />
It is nothing mentioned about the size of the containers to deliver the goods. Are there any requirements<br />
It is also not clear about the containers whether they are only used for delivering and going back to the<br />
tenderer or if you are going to keep them<br />
Response:<br />
Only 20’ containers can be accepted in <strong>Yap</strong> harbor. The containers can go back to the tenderer.<br />
(f). Clarification Request #6:<br />
PV Module Mounting Structure<br />
Can you please clarify if we also have to supply the post/poles for the array mounting structure<br />
Response:<br />
<strong>No</strong>, the modules will be ground-mounted on a concrete structure prepared by YSPSC. It is however<br />
important to include the technical drawings of the proposed mounting structure.<br />
(g). Clarification Request #7:<br />
Charge Controllers<br />
For a SCS the charge controller is specified to be 70A at 48V. Our question is can we offer a lesser amps<br />
controller than 70A if our array voltage will be configured at higher voltage to charge the 48V battery bank<br />
via MPPT technology.<br />
Response:<br />
You can offer an alternative design that we can look into however the official proposal needs to comply<br />
with the requested specs. <strong>No</strong>te that the specifications ask for a 48 V system and 3,360 Wp. It is however,<br />
possible to parallel 2 or 3 charge controllers, if this is recommended by the manufacturer. Please refer to<br />
point e.8 of Annex II.<br />
(h). Clarification Request #8:<br />
Wires, connectors and fuses<br />
Could please specify the cable run between the PV Module to Charge controller and the cable run<br />
between charge controller and battery for the SCS<br />
Response:<br />
The tender documents ask the tenderer under point g.2 to specify the wire sizes for the SCS with the note<br />
that “All wiring must be sized to keep line voltage losses to less than two percent (2%) in each sub-circuit<br />
and to allow the circuit to operate at a maximum of 60deg Celsius within the ampacity rating of the cable.”<br />
Voltage drop calculations need to be included in the proposal.<br />
(i). Clarification Request #9:<br />
Will 12V batteries be considered as well (e.g. 12V 190Ah for SHS)<br />
Response:<br />
<strong>No</strong>, the specs need to comply with the technical tender document. We have left a window open to send<br />
besides the offer that follows the set specification to propose and alternative design. For now only 6V and<br />
2V batteries will be accepted.<br />
(j). Clarification Request #10:<br />
Typically larger charge controllers (45A and above), function only as a charge controller or a load