RFP for Resurvey project - ANAND & other SEVEN Districts <strong>of</strong> Gujarat State<br />

5 Third Set <strong>of</strong> Taluka Actual Bill – (1/3rd <strong>of</strong> Sum<br />

<strong>of</strong> (1) + (2)<br />

6 Fourth Set <strong>of</strong> Taluka Actual Bill – 10% <strong>of</strong><br />

Estimated contract value l<br />

Above payments shall be made after deduction <strong>of</strong> tax at source, whichever may be applicable, by the Acts<br />

prevailing at the time <strong>of</strong> making payment. Payment <strong>of</strong> all other tax and levies would be the responsibility <strong>of</strong><br />

the Survey Agency. All payments to the agencies would be made in Indian Rupees only.<br />

The payment shall be made after the successful completion <strong>of</strong> the activity and successful submission <strong>of</strong> the<br />

deliverables & its acceptance by SC & DLR.<br />

c. The minimum gap between two successive invoices will be 1 month.<br />

PENALTY CLAUSE<br />

Vendor should submit his own detailed time schedule with measurable milestones and such schedules<br />

should be practicable, reasonable and balanced. At the time <strong>of</strong> presentation, SC&DLR and the vendor would<br />

come to a mutually agreeable time schedule, which will be the finalized schedule to form part <strong>of</strong> the<br />

agreement.<br />

Any delay in implementation at any milestone mentioned in the plan, will attract a penalty <strong>of</strong> 0.5% <strong>of</strong> the<br />

contract value for every 7 days, subject to a maximum <strong>of</strong> 4%. Maximum delay permitted will be 60 days<br />

beyond which the agreement is liable to be terminated and vendor performance guarantee will be forfeited.<br />

In such case, SC&DLR reserves the right to make necessary alternate arrangements to complete the project.<br />

Further any delays must be made up by the vendor by the time <strong>of</strong> the payment milestone for the completion<br />

<strong>of</strong> 75% i.e. project implementation needs to be as per schedule at this point.<br />

The purpose <strong>of</strong> this is to ensure all necessary formalities for project completion and closure are completed as<br />

planned and vendor will not deliver/ complete a large part <strong>of</strong> the work only at the end stage, as this would<br />

hinder smooth project completion and sign-<strong>of</strong>f. Penalties if deducted earlier will be refunded at this stage.<br />