RFP for ANAND & other Seven DISTRICTS Resurvey project<br />
d. Detailed schedule <strong>of</strong> the visit <strong>of</strong> survey team to each village shall be handed over to all<br />
the heads <strong>of</strong> land owning departments - so that the <strong>of</strong>ficials from the departments help<br />
the agency in the identification <strong>of</strong> boundaries <strong>of</strong> the lands owned by the department.<br />
e. At the taluka level, revenue village should be taken as a unit. The village level plan<br />
showing details <strong>of</strong> day wise program <strong>of</strong> survey shall be published in the concerned<br />
taluka, village, at least 10 days before commencement <strong>of</strong> field survey.<br />
f. There should be adequate number <strong>of</strong> survey teams and adequate number <strong>of</strong> adjudicating<br />
personnel to complete the work as per the schedule.<br />
g. Every survey team should have at least one member familiar with the local language<br />
and the field workers and supervisory staff should be conversant with the local<br />
language.<br />
h. Survey adjudicator will be appointed by the government. However he/she shall be<br />
assisted by one surveyor along with ETS machine from Agency.<br />
i. From the agency side, each survey team shall have at least one machine operator and 2<br />
support staff .<br />
j. The Taluka/District level team along with the members from survey agency should<br />
conduct a gram sabha in the village before the commencement <strong>of</strong> survey work and the<br />
entire process should be explained. The day wise survey schedule should also be<br />
discussed and farmers concerned should be mobilized.<br />
k. Agency shall establish a village survey center in the appropriate place in the villages<br />
with adequate number <strong>of</strong> laptops, printers and consumables. Basic infrastructure<br />
including uninterrupted power supply for establishing a Survey Center is readily<br />
available in all the village. In case these facilities are not available in any particular<br />
village, the survey agency could have its base in the nearest village during the survey<br />
execution.<br />
l. Agency has to bear the expenses <strong>of</strong> establishing the village survey centers in case the<br />
government buildings are not available. The cost <strong>of</strong> electricity and other expenditure<br />
has to be borne by the Agency. In case these facilities are not available in any particular<br />
village, the survey agency could have its base in the nearest village during the survey<br />
execution.<br />
m. The field work shall commence as per the schedule published in the village. Note the<br />
boundary marking using ETS as shown by the concerned owners or enjoyers in the<br />
31<br />