“The Saving Costs During an Economic Downturn challenge”:<br />

This next objective in managing the Productronica exhibit production was met in several<br />

ways. The first one as mentioned earlier was by cuts made from an initial booth plan of<br />

192 sqm for €125,000 to arrive at a 150 sqm stand with an estimated cost of €84,500.<br />

This one-third reduction was achieved mainly by reducing floor space, removing three<br />

meeting rooms and replacing with open meeting areas.<br />

Another way to save costs involved changes to the booth construction for 2009 from the<br />

previous tradeshow in 2007. By removing structures and some costly graphics, and<br />

making some changes to materials used in fabrication, the savings were about 33.5%<br />

(from €55,526 to €36,926), or over $27K to be allocated amongst the companies.<br />

Having a third company to share costs instead of just two like in 2007 provided<br />

extraordinary savings, specifically for Nordson ASYMTEK, as shown in the table below:<br />

Allocations by % to: 2007 Euros split 2009 Euros split<br />

Nordson ASYMTEK 74% 70,056 40% 29,002<br />

Nordson EFD 26% 24,614 26% 18,852<br />

Nordson YESTECH 34% 24,652<br />

Booth Build 55,526 36,926<br />

Stand Raw Space 39,144 35,580<br />

TOTAL 100% 94,670 100% 72,506<br />

In addition to the above, each company was responsible for their own costs of travel,<br />

promotions, specific utilities and graphics, and individual freight. As advised in Session<br />

72001/72101: “Global Exhibiting: An Introductory Overview”, I also needed to consider a<br />

contingency fund for unforeseen costs such as the increasing currency exchange rate<br />

and changes in inflation.<br />

According to the detailed expense analysis that I had prepared for Nordson ASYMTEK<br />

(*Productronica Detail Reporting of Costs can be found in the Appendix, page 46),<br />

some other significant cost savings from the 2007 show included 26% less in travel<br />

(sent less people), 61% in hospitality and catering (reduced the cocktail party and<br />

skipped the all-day sales training meeting), and 75% saved in international and local<br />

freight (by not sending machinery from USA and shipping half the machines as in 2007).<br />

In conclusion, Nordson ASYMTEK reduced the cost of exhibiting at Productronica 2009<br />

by 47.5% or $76,942 in total (from $162K to $85K) compared to Productronica 2007.<br />

CTSM Portfolio – <strong>Tracey</strong> <strong>Schropp</strong> Page 18