4<br />

Cut the GTEC Dryliner Channel RD1 5mm<br />

shorter than the length of the ceiling required<br />

and locate the GTEC Dryliner Channel RD1 into<br />

the GTEC Dryliner Track.<br />

Where required insert mineral wool batts<br />

above the framing ensuring that the mineral<br />

wool forms one continuous lining.<br />

5<br />

Fix plasterboards with the long edges at right<br />

angles to the GTEC Dryliner Channels. Screw-fix<br />

the boards to the GTEC Dryliner Channels<br />

at 230mm maximum centres and 150mm<br />

maximum centres at perimeters and the cut<br />

ends of board.<br />

With two layers of plasterboard, stagger all the<br />

joints between the layers. For the typical single<br />

layer and two-layer plasterboard layouts, see<br />

diagrams overleaf.<br />

Table 1: Maximum framing centres<br />

Board thickness Board length GTEC Dryliner<br />

(mm) (mm) Channel centres (mm)<br />

12.5 2400 400<br />

1800, 2700 450<br />

3600 450<br />

15 and 19 2700 450<br />

other lengths 600<br />

Table 2: Centres for GTEC Joist Connectors and<br />

GTEC SR Brackets<br />

Board thickness<br />

9.5mm plasterboard single layer 600<br />

12.5mm plasterboard single layer 600<br />

15.0mm plasterboard single layer 600<br />

All double layer boarding 600<br />

Maximum (mm)<br />

THE INSTALLATION HANDBOOK 2008<br />

59