INSTALLATION<br />

1 Set out the Lafarge GTEC Independent Wall<br />

Lining System inside the external wall; allow<br />

a minimum cavity width of 30mm between<br />

external wall and the back of the metal framing,<br />

or to the insulation if thickness of insulation<br />

is greater than width of framing.<br />

Fix GTEC U Track to timber or concrete floor<br />

at 600mm centres using suitable fixings.<br />

Note: If applying GTEC U Track directly to new<br />

concrete, the concrete must be dry and a dampproofing<br />

membrane must be used. On uneven<br />

floors a timber sole plate may be required. Where<br />

sound insulation is critical, apply a bead of GTEC<br />

Intumescent Acoustic Sealant under the sole plate.<br />

2<br />

Install a GTEC C Stud using a spirit level<br />

to plumb upright on end wall, and fix at<br />

600mm centres using suitable fixings.<br />

3<br />

Install ceiling GTEC U Track onto the end wall<br />

GTEC C Stud, using a GTEC I Stud (as a temporary<br />

prop) and spirit level. Plumb the opposite end of<br />

the ceiling GTEC U Track to align with floor GTEC<br />

U Track. Screw-fix the ceiling GTEC U Track into<br />

position at 600mm centres or less.<br />

Now fix the opposite end wall GTEC C Stud<br />

Note: If sound insulation is required, apply a 6mm<br />

bead of GTEC Intumescent Acoustic Sealant around the<br />

perimeter of the framing before applying<br />

the boards.<br />

16 THE INSTALLATION HANDBOOK 2008