shall be performed by Subcontractor as part of the WORK. Drawings and specifications are to be<br />

construed as supplementing each other.<br />

d. In executing this Agreement, except as expressly noted and provided for in Exhibit “B”, the<br />

Subcontractor represents that he has visited, investigated, examined, inspected, and thoroughly<br />

familiarized itself with the Contract Documents, the Project site and adjoining premises, and the<br />

local conditions, in connection with which the WORK covered by this Agreement is to be<br />

performed, that it has thoroughly informed itself as to any difficulties in connection therewith, that<br />

the Design/Builder has made no representation of any kind or nature with references thereto<br />

except as may be expressly set forth in writing in this Agreement and Subcontractor has correlated<br />

its observations with the requirements of the Contract Documents and further represents that based<br />

on that review, Subcontractor finds the Contract Documents are sufficient for the WORK to be<br />

performed. Commencement of this WORK or any portion thereof by the Subcontractor shall be<br />

conclusive evidence that the Project site, or that part thereof at which the WORK is being<br />

installed, is in proper condition for the reception and installation of the WORK.<br />

e. Design/Builder may provide some or all of the Contract Documents, whether draft or final<br />

versions, in electronic media for Subcontractor’s use as reference documents. Due to the potential<br />

that the information set forth in such electronic media can be corrupted or modified in<br />

transmission or by the Subcontractor or others, unintentionally or otherwise, or that design<br />

changes may be made after the data is transferred, Subcontractor recognizes and agrees that all use<br />

of such electronic media will be at Subcontractor’s sole risk and without any liability, risk or legal<br />

exposure to the Design/Builder, its employees, officers, subcontractors or consultants.<br />

f. Subcontractor agrees to indemnify, defend and hold harmless Design/Builder with respect to any<br />

loss or damage incurred by Design/Builder due to Subcontractor's use of the electronic Contract<br />

Documents.<br />

4. SUBMITTALS<br />

a. Time is of the essence of this Agreement. Subcontractor shall prepare and submit to<br />

Design/Builder a submittal log and schedule which, shall be updated weekly, showing the status of<br />

all required shop drawings, samples and other required submittals. Subcontractor shall prepare all<br />

shop drawings and other required data and furnish same for review and approval by the<br />

Design/Builder in strict accordance with this Agreement and Design/Builder’s schedule<br />

requirements (as said schedule requirements maybe adjusted by Design/Builder from time to time<br />

in response to the current needs of the Project), so as not to delay the progress of either the<br />

Subcontractor's WORK, the total WORK required of the Design/Builder pursuant to the Prime<br />

Contract or the work of Owner or any other person or entity with respect to the Project. Adequate<br />

copies of such data shall be submitted by Subcontractor to Design/Builder, plus the number of<br />

returned copies desired by the Subcontractor for his use. In the instance of specifically prepared<br />

fabrication drawings, submittal shall consist of one reproducible drawing and two prints.<br />

Subcontractor agrees to keep Design/Builder fully informed regarding his delivery schedule and<br />

will immediately advise the Design/Builder in writing should any delay be anticipated. A<br />

complete, up-to-date procurement schedule will be submitted on forms acceptable to the<br />

Design/Builder, upon request. Procurement schedule and Project Schedule to be compatible.<br />

b. In reviewing Subcontractor’s shop drawings, samples and other submittals, Design/Builder is not<br />

responsible for verifying dimensions or field conditions. Review or approval of any such<br />

materials shall not relieve the Subcontractor from his responsibility for the proper matching and<br />

fitting of the WORK with all contiguous work and the coordination of the WORK with other work<br />

being performed on the Project site, or of any duty and responsibility to perform the WORK in<br />

accordance with the Contract Documents.<br />

c. As-built documents and data shall be maintained and recorded on a continuous basis by the<br />

Subcontractor as applicable to his WORK and shall be reviewed periodically by Design/Builder.<br />

Should Design/Builder determine that such as-built documents are not being properly maintained,<br />

Design/Builder shall have the right to withhold payment under the terms of this Agreement until<br />

such time as, in Design/Builder’s determination, the as-built documents have been properly<br />

recorded.<br />

4