Deepwater Horizon Oil Spill Response<br />

Chapter 4 - Mobilization<br />

SUPSALV initially directed deployment from <strong>ESSM</strong> Cheatham, VA and <strong>ESSM</strong> Port Hueneme,<br />

CA. Trucks began rolling on 27 April and without specific guidance, the intended destination was<br />

Houma, LA, the site of the UAC. En route, SUPSALV was told their destination was Gulfport,<br />

MS but not specifically where. The SUPSALV advance team made arrangements with the Naval<br />

Construction Battalion Center, Gulfport to take delivery but by the time the first trucks were<br />

arriving, the Coast Guard had negotiated for space at the State Pier in Gulfport to which the<br />

remainder of the trucks were diverted.<br />

4-1 Initial Mobilization<br />

SUPSALV initially responded with the deployment of 66,000 feet of oil containment boom, 2<br />

salvage skimmer vans, 9 boom handling / tow boats, 1 High Speed Skimmer System (VOSS<br />

Current Buster) and 7 modular MARCO MK V skimmers. Other equipment included 4 shop and<br />

rigging vans, 2 command vans, 4 bunk vans, 4 work boats and 45 boom mooring systems. This<br />

represented a total of 57 truckloads from Port Hueneme and Cheatham <strong>ESSM</strong> bases. The trip<br />

from Cheatham generally took 2 days and from the west coast, 3 days. On 30 April, the order<br />

was placed for 9 wide-body skimmers, 5 from Cheatham and 4 from Port Hueneme. These wide<br />

loads were delayed while permits were arranged for interstate travel. The 30 April order<br />

represented an additional 18 truck loads.<br />

By default, the equipment destination was State Pier, Gulfport but in some instances, where<br />

allocation assignments had already been made, trucks were diverted to Venice, Louisiana, ICP<br />

Houma’s staging area. <strong>ESSM</strong>’s transport was effective and by 4 May, 79 of 85 truckloads had<br />

arrived in-theater and by 6 May all of the originally shipped equipment has been received and<br />

staged at the designated locations throughout the Gulf Coast per USCG direction.<br />

Figure 4-1. <strong>ESSM</strong> equipment sitting on trailers recently arrived at State Pier, Gulfport,<br />

MS on 2 May waiting to be unloaded.<br />

Additional equipment was ordered as SUPSALV identified the need to bring the gear into the<br />

Gulf. On 1 May, additional mooring systems were ordered. By 10 May, the number of MARCO<br />

4-1