Final Report, SONS Deepwater Horizon Oil Spill, Gulf of Mexico, 27 April — 24 September 2010<br />

The total SUPSALV Oil Containment Boom in GOMEX was 98,000′ with 38,000′ of boom<br />

deployed. Eighteen Class V Vessel Skimmers with crews were positioned at the USCG<br />

designated locations.<br />

Five Class V Skimmers, positioned on board four spud/jack-up barges off Mobile, did not get<br />

underway again due to the weather. Two Class V Skimmers from Port Fourchon were loaded on<br />

the Pecos barge to conduct skimming operations in Mobile Bay. Three bladder offloading<br />

systems and trainers were sent to Bayou La Batre to be taken offshore to support bladder<br />

offloading operations of task forces 1, 2, and 3 on barges in Mobile.<br />

OSV Wes Bordelon was underway with 4400′ of USS-42″ Oil Containment Boom at East Bay<br />

but could not deploy boom due to the weather.<br />

SUPSALV personnel onshore in Grand Isle continued to support near-shore recovery operations.<br />

Two Class V Skimmers, both in “free skimming mode”, were on standby near the shore. Two<br />

Class V Skimmers and the shore based operations encountered oil. See Figure 16.<br />

Figure 16. Crude Oil Rolling off Skimmer Belt<br />

OSV MV John Coghill, with two Current Buster VOSS, was at the oil site conducting skimming<br />

operations, but rough weather was encountered. OSV AHTS Vanguard was inbound to Gulfport<br />

to have knuckle cranes installed to lift Weir Skimmers from High Speed Current Buster pockets<br />

as had been accomplished on the OSV MV John Coghill. This had greatly accelerated debris<br />

clearance and maintenance.<br />

OSV MV Renee was pierside in Gulfport with the Class XI Skimmer System installation<br />

completed. Testing and training were conducted. OSV MV Renee was to get underway midday<br />

Saturday to refuel in Theodore then proceed to sea.<br />