North American Special - Trenchless International
North American Special - Trenchless International
North American Special - Trenchless International
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Undersea HDD rescue<br />
in Saudi Arabia<br />
About ISTT/Membership<br />
The ISTT is the umbrella organisation for trenchless technologists in over 40<br />
countries of the world. In 22 countries groups of trenchless technologists have<br />
their own national groups which are affiliated while the remainder are registered<br />
directly with the ISTT.<br />
In 2007-08 a pioneering HDD project was started using <strong>Trenchless</strong><br />
Technology on the Berri Causeway and Abu Ali Island on the<br />
Persian Gulf coast of Saudi Arabia. Two parallel 3,050 metre long<br />
steel pipelines were to be installed under the bay.<br />
<strong>Trenchless</strong> technology covers the repair, maintenance, upgrade and new<br />
installation of underground utility services using equipment and techniques<br />
which avoid or considerably reduce the need for excavation. The ISTT promotes<br />
research, training and the more extensive use of trenchless technology<br />
through publications, co-operation with other NGOs, an annual international<br />
conference and an interactive website.<br />
oil and gas<br />
April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />
The smaller 24 inch pipe was to be<br />
used as an oil trunk line and the larger<br />
30 inch, with a total steel pipe weight<br />
of more than 1,500 tonnes, to serve as<br />
a water injection line. The project was<br />
reported to be the world’s longest undersea<br />
HDD crossing.<br />
In November 2008, Middle East specialist<br />
HDD contractor Digital Connection Co<br />
Ltd of Al-Khobar, Kingdom of Saudi Arabia<br />
sought technical advice and assistance<br />
in the recovery of a 42 inch hole-opener<br />
that had become stuck along with the<br />
3 km drill string beneath the seabed during<br />
a pre-ream pass on the second of two<br />
subsea pipeline crossings.<br />
The Berri Causeway pipeline project in<br />
the Middle East was always seen as a big<br />
challenge. Both the length of the crossings<br />
and the dimensions of the pipeline,<br />
which would weigh more than 1,525<br />
tonnes, were testing the boundaries.<br />
While the first 24 inch oil pipeline had<br />
previously been successfully installed,<br />
unforeseen delays between the drilling<br />
process over a twelve week, non-working<br />
period had caused the drill string and<br />
the 42 inch hole-opener to become stuck<br />
on the second, 30 inch pipeline crossing<br />
and installation.<br />
They had little time to provide a solution<br />
to releasing the 3 km stuck drill string<br />
and 42 inch hole-opener.<br />
However, emergency discussions<br />
between TT-UK, the main contractor, and<br />
the local drilling contractor quickly led to<br />
a response. The company recommended<br />
using the Grundoram Taurus impacting<br />
hammer combined with steel pipe adaptations.<br />
The adaptations were designed<br />
and formulated to transfer dynamic<br />
impact performance energies through<br />
special steel fabrications adapted to the<br />
drill string via the Grundoram dynamic<br />
impacting hammer.<br />
Sharing the project information with<br />
other TT Group offices in the USA and<br />
For further information please contact TT UK LTD (+44) 1234 342566<br />
fax: (+44) 1234 352184 email: info@tt-uk.com website: www.tt-uk.com<br />
Germany, TT-UK drew up a strategic<br />
plan together with a technical proposal<br />
on how they believed the drill string could<br />
be freed up using dynamic impact vibration<br />
energy.<br />
While similar successful undertakings<br />
had previously been carried out<br />
worldwide, few have been attempted for<br />
releasing stuck drill rods over such an<br />
exceptionally long distance, with each<br />
drill rod weighing 480 kg. Dynamic<br />
impact vibration energies have normally<br />
been placed on the end of product pipes<br />
for assistance in completing HDD (ram<br />
assist), or using HDD techniques for<br />
product pipe retrieval where the product<br />
pipe has become stuck. Few undertakings<br />
had previously attempted with stuck<br />
drill rods due to the enormous impact<br />
power that has to be contained onto a<br />
relatively small size drill rod (6/58th) from<br />
a large impacting hammer in a usable<br />
and controllable process.<br />
The Project owner is Saudi Aramco.<br />
The main pipeline contractor is Al Robaya<br />
and the HDD subcontractors are DCL<br />
and TATCO. The combined efforts from<br />
all companies and the personal attendance<br />
on site of Roger Atherton of TT-UK<br />
proved invaluable to the success and<br />
final retrieval of this problematic drill<br />
bore taking TT’s Grundoram and pipe<br />
ramming technologies to a new level of<br />
HDD ram assist, pipe/drill stem rescue<br />
method. Following bore-hole salvage the<br />
3 km, 30 inch water injection pipe-line<br />
was finally and successfully installed on<br />
13 January 2009.<br />
This rescue prevented significant<br />
financial implications such as the total<br />
cost of a lost drilled bore, any contractual<br />
penalties and ongoing cost delays<br />
in commissioning the final pipelines.<br />
Associated costs involved in planning a<br />
new bore and the actual costs of duplicating<br />
all the undertakings of a new bore/<br />
installation.<br />
ISTT Membership/Directory<br />
Please complete the following form.<br />
Please note: Entry in the ISTT Directory is free to Corporate<br />
Members<br />
but only if the Industry Sector is completed.<br />
Alternatively, you can fill in this form online at www.istt.com.<br />
MEMBERSHIP TYPE<br />
Corporate Membership<br />
COMPANY DETAILS<br />
Company/Organisation Name:<br />
Name of Affiliate:<br />
Please write ISTT if there is not an ISTT Affiliate in your country.<br />
CONTACT DETAILS<br />
Title:<br />
First Name:<br />
Position:<br />
Department:<br />
Address:<br />
City:<br />
State/County:<br />
Zip/Postal Code:<br />
Country:<br />
Telephone:<br />
Email:<br />
Website:<br />
<strong>Trenchless</strong> technology is recognised as an Environmentally Sustainable<br />
Technology and is particularly suited to use in densely populated urban<br />
areas by reducing disruption to peoples daily lives, social costs (traffic congestion,<br />
damage to road surfaces and buildings, air quality), noise and dust.<br />
<strong>Trenchless</strong> technologies also have a considerably reduced carbon footprint<br />
compared to trenching in most situations.<br />
Ordinary Membership<br />
Last Name:<br />
Fax:<br />
INDUSTRY SECTOR<br />
Please select the industry sector that<br />
best describes your company, multiple<br />
selections can be made. Please check all<br />
relevant boxes.<br />
Agent<br />
Consultant<br />
Contractor<br />
Site Survey / Inspection /<br />
Leakage Detection<br />
Off Line Installation / Replacement<br />
Moling / Ramming<br />
Boring / Directional Drilling<br />
Pipe jacking / Microtunnelling<br />
On Line Replacement -<br />
Pipe Bursting / Splitting / Eating<br />
Repairs<br />
Internal Sleeves / Seals<br />
Resin Injection<br />
Robotic Repairs<br />
Renovation<br />
Cured in Place<br />
Sliplining (incl. spiral wound)<br />
Close Fit Lining<br />
Spray Lining<br />
Large diameter Systems<br />
(incl. segment lining, in situ lining<br />
and manholes)<br />
Equipment / Materials Supplier /<br />
Manufacturer<br />
Equipment Rental<br />
Public Sector / Utility<br />
Water / Sewerage<br />
Gas<br />
Electricity<br />
Telecoms<br />
Other<br />
Education / Research /<br />
Test Laboratory<br />
the international society for trenchless technology<br />
April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />
68<br />
69