05.01.2015 Views

North American Special - Trenchless International

North American Special - Trenchless International

North American Special - Trenchless International

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

• Geophysical surveys of 29 km of tunnel<br />

• Probe and core drilling<br />

• Fibre optic scope inspection<br />

• Test grouting program<br />

• Epoxy mortar lining – test section<br />

• High quality video recording<br />

• Walk-through inspections in 5.3 km<br />

length of pressurised section of NCA.<br />

In general the design phase focused on<br />

restoration of the brick lining rather than<br />

its replacement with concrete or shotcrete.<br />

Where significant defects had been<br />

observed in previous inspections and were<br />

determined to require larger-scale repairs,<br />

in situ concrete was used. (Figure 2). The<br />

design phase also considered temporary<br />

structures, such as the design of standby<br />

bulkheads to fit inside the shafts in the<br />

pressurised section of the NCA. These<br />

temporary bulkheads would serve as a<br />

means of restoring the service of the NCA<br />

should it be required to provide water<br />

to the city in the event of an emergency<br />

situation elsewhere in the water supply<br />

system. In addition, the design phase<br />

included mechanical engineering for the<br />

inspection and replacement of ageing<br />

infrastructure such as pipes, gates and<br />

valves.<br />

Diagram showing the horseshoe-shaped<br />

brick liner of the New Croton Aqueduct in<br />

the gravity flow portions of the alignment.<br />

The profile on the left shows a typical cutand-cover<br />

section: the profile on the right is<br />

typical of the mined sections. Source: The<br />

City of New York Aqueduct Commission,<br />

1895.<br />

Part 2: inspection<br />

Objective<br />

The objective of the shaft and tunnel<br />

inspections was to locate and document<br />

defects. Information gathered during the<br />

visual inspection was used to establish<br />

focal areas for both future repair contracts<br />

and further field investigation, which<br />

included coring, probe drilling, fibre optic<br />

scope inspection and test grouting.<br />

Inspection of the tunnel and shafts<br />

The scope of the inspection work<br />

under the construction contract included<br />

assessing the condition of the 9.6 km long<br />

pressurised section of NCA and inspection<br />

of shafts, headhouses and blow-off structures<br />

in both the pressurised and gravity<br />

sections.<br />

Tunnel inspection was performed<br />

between stations. Brick-lined portions of<br />

the tunnel and shafts were sounded, and<br />

the entire tunnel alignment was visually<br />

inspected. Potential voided areas were<br />

recorded in the field log and marked on the<br />

wall for possible future probe hole drilling.<br />

The lowest part of the invert was typically<br />

covered with water 100 to 200 mm deep,<br />

preventing inspection; but defects were<br />

noted when observed.<br />

The siphon under the Harlem River<br />

extends to a depth of 122 m. The purpose<br />

of performing an ROV inspection instead<br />

of dewatering the siphon and performing<br />

a walk-through inspection, was to minimise<br />

the risk of the lining buckling due<br />

to external water pressure acting on an<br />

empty lining. The siphon has never needed<br />

dewatering since it was brought into operation<br />

in 1891. The ROV was equipped with<br />

high resolution video and dual imaging<br />

sonar instruments. The objective was to<br />

verify shaft and siphon lining materials and<br />

construction features, to assess sediment<br />

levels and debris accumulations, to locate<br />

defects and to obtain video and sonic<br />

records of the structures.<br />

Testing<br />

the ground<br />

Non-destructive geophysical testing was<br />

performed within Gould’s Swamp and a<br />

fibre optic testing program was conducted<br />

at locations that appeared from the visual<br />

and geophysical investigations to merit<br />

Test grouting operations in the Bronx pressurised<br />

aqueduct.<br />

further investigation.<br />

Continuous diamond core drilling was<br />

performed on selected areas of the aqueduct<br />

to obtain samples of the tunnel lining,<br />

mortared and grouted rubble, and foundation<br />

bedrock for material identification and<br />

laboratory testing to determine engineering<br />

properties. Test grouting was performed in<br />

both the Bronx and Manhattan pressurised<br />

tunnels and at two shaft locations.<br />

The comprehensive field investigation<br />

program was used to assess the current<br />

condition of the NCA and to design a<br />

rehabilitation program. Overall, the tunnel<br />

and shafts are in very good condition,<br />

with reparable leaks or defects at some<br />

locations. The visual inspection identified<br />

tunnel defects and the geophysical inspection<br />

determined the condition of the brick<br />

liner and the grouted and mortared rubble<br />

backing. Visual and geophysical inspection<br />

findings frequently complement the laboratory<br />

test results. The test grouting program<br />

successfully stopped or decreased<br />

inflows into the test areas. The locations<br />

of abandoned shafts were verified using<br />

geophysical methods. Investigations of the<br />

‘soft rock zone’ determined that the area is<br />

geologically stable.<br />

There are a total of 49 shafts along the<br />

aqueduct alignment, ranging from large<br />

chambers in cut-and-cover sections, to<br />

small diameter shafts up to 113 m deep.<br />

Seventeen of these shafts were filled at<br />

the end of construction and are difficult<br />

to detect from the ground surface or from<br />

within the tunnel. Eight shafts were lined<br />

with a combination of brick and Cast Iron.<br />

Most were rimmed with granite collars, typically<br />

350 mm thick, at the surface. Collars<br />

at the tunnel intersection are up to 600 mm<br />

thick. Most shafts had steel ladders from<br />

the ground surface to the tunnel crown<br />

which often exhibited oxidation, tuberculation<br />

and/or section loss. The shafts were in<br />

very good to excellent condition, overall.<br />

The Harlem River siphon and associated<br />

structures were successfully inspected by<br />

a ROV and found to be aligned according<br />

to historic drawings and without evidence<br />

of major displacement or defects.<br />

Heavy groundwater inflow encountered<br />

after drilling into a water-filled void. Inflow<br />

rates subsided over the following 48 hours<br />

and were significantly reduced after grouting.<br />

Part 3: rehabilitation<br />

The goal of the project was to restore<br />

the gravity flow section of the aqueduct<br />

to optimal operating condition, thus<br />

extending the lifespan of this significant<br />

water supply for the New York City<br />

metropolitan area. A large-scale contact<br />

grouting program was performed in the<br />

horseshoe-shaped gravity flow sections<br />

of the aqueduct, with the objective of<br />

filling identified voids behind the liner,<br />

filling fractures in broken mortared and<br />

grouted rubble and foundation bedrock<br />

materials, and reducing water infiltration<br />

into the tunnel.<br />

Cover depths of the aqueduct vary considerably,<br />

ranging from a few to hundreds<br />

of metres, typically consisting of hard<br />

rock. Primarily mined using conventional<br />

methods of the late 1800s, construction<br />

of the NCA also employed cut-and-cover<br />

methods in several low-lying sections of<br />

the alignment, totalling approximately 1.6<br />

km. The NCA passes through numerous<br />

lithologic changes, fault/shear zones and<br />

under several significant water bodies,<br />

including the Pocantico and Saw Mill<br />

Rivers and the Tarrytown Reservoir. It<br />

also passes under the Harlem River as a<br />

siphon at a depth of approximately 122<br />

metres below grade.<br />

Soon after construction, reports on the<br />

NCA from The Aqueduct Commission<br />

documented prominent defects in the tunnel,<br />

such as large voids behind the lining.<br />

More recently, large-scale inspections<br />

of the gravity flow section, performed<br />

during the 1990s, and a 2004 inspection<br />

of portions of the pressurised sections,<br />

have revealed additional defects, such<br />

as open and/or deteriorated masonry<br />

joints/cracks, leaks ranging from trickles<br />

to several gallons per minute into and out<br />

of the aqueduct, missing bricks, formed<br />

openings, and in one place, a rupture<br />

through the liner with discernible offset.<br />

Despite these defects, the generally<br />

good condition of the NCA is remarkable.<br />

It is not uncommon to traverse several<br />

miles through the aqueduct without noting<br />

any significant defects.<br />

Major liner repair<br />

Major liner repair work consisted of<br />

cast-in-place reinforced concrete for filling<br />

of existing formed openings located at<br />

or near the crown of the tunnel and areas<br />

of brick heave located within the tunnel<br />

invert. Areas requiring brick replacement<br />

were minimal, totalling only 14.8 square<br />

metres.<br />

The successful rehabilitation of the<br />

38 km long gravity flow section of the<br />

New Croton Aqueduct resulted from<br />

good management and positive working<br />

relationships among the owner,<br />

the engineering consultants and the<br />

contractor. The rehabilitation was completed<br />

on schedule within approximately<br />

17 months, with crews working a typical<br />

eight-hour work shift five days a week.<br />

This is an edited version of a paper by A. Noble,<br />

D. Roberts and A. Fareth. Please refer to the paper<br />

for more detailed information, acknowledgements<br />

and references.<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

58<br />

59

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!