05.01.2015 Views

North American Special - Trenchless International

North American Special - Trenchless International

North American Special - Trenchless International

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

north america<br />

is a biaxial stress, which is a combination<br />

of hoop stress due to internal pressure<br />

and longitudinal stress due to bending<br />

of the pipe to achieve the curved shape<br />

of the HDD path added to the stress<br />

imposed on the pipeline due to thermal<br />

differential. A large positive thermal differential,<br />

together with internal pressure<br />

is typically the worst case.<br />

Shortly after deciding to complete<br />

the 36 inch ream the project team recognised<br />

it may not be reasonable to<br />

expect the 36 inch ream, to improve the<br />

current minimum pilot hole radius from<br />

270 metres to the minimum calculated<br />

radius of 425 metres as calculated in<br />

the Tresca analysis. This led to another<br />

refinement of the combined stress calculation.<br />

A more realistic approach is to<br />

compute combined stress as per the Von<br />

Mises formula, which uses similar inputs<br />

as Tresca with modest time and effort<br />

required. The Von Mises calculation<br />

method is also known to be more realistic<br />

for ductile steel such as employed in<br />

modern oil and gas pipeline systems.<br />

For the Pine Creek crossing the soil<br />

within the drill path was assumed to<br />

be a ‘soft formation’ based on feedback<br />

from the drilling contractor, the<br />

difficulty experienced with down hole<br />

steering and the results of the geotechnical<br />

investigation carried out by AMEC<br />

Earth and Environmental. This resulted<br />

in the use of soil category A.<br />

Analysis of the drill path was completed<br />

using the Von Mises method<br />

with the above parameters. The resultant<br />

minimum acceptable radius was<br />

determined to be 385 metres, a marginal<br />

improvement on the previous<br />

425 metres. The 385 metre radius would<br />

need to be compared to the calculated<br />

minimum radius in the drill path after<br />

completion of the 36 inch ream.<br />

The ream was completed two days<br />

later. Entec analysed the drill profile<br />

data and calculated a minimum dogleg<br />

radius of 284 metres, with a number<br />

of other radii less than 385 metres.<br />

The subsequent survey tool run was<br />

completed later in the same day. Entec<br />

analysed these results and calculated<br />

a minimum radius of 170 metres<br />

with a number of other radii less than<br />

385 metres. The ever decreasing calculated<br />

minimum radius confirms that the<br />

progression of the calculations is from<br />

conservative to more realistic.<br />

Pembina and its construction manager<br />

subsequently decided to pull the NPS24<br />

pipe, as seen on page 55, into the hole<br />

and the project team agreed to continue<br />

analysing the available information to<br />

determine if in fact the 36 inch reamed<br />

drill path was acceptable.<br />

First, the project team completed a<br />

sensitivity analysis to determine if reducing<br />

the MOP of the pipeline or increasing<br />

the pipe grade would be a viable alternative.<br />

After careful review, the required<br />

MOP reduction to 4,400 kPa or pipe<br />

grade increase to 545 MPa were still not<br />

sufficient to provide acceptability for the<br />

Pine Creek crossing.<br />

The next and only viable alternative<br />

for analysing the crossing was to determine<br />

the absolute stress level within<br />

the pipe at this location. The Tresca<br />

and Von Mises methods are both stress<br />

based, conservatively not accounting<br />

for the nonlinear steel properties. Due<br />

to tight bend radii determined in the<br />

field, the group agreed to undertake a<br />

third method of analysis; a nonlinear<br />

strain analysis, which is permitted by<br />

CSA-Z662 Annex C as a limit states<br />

design approach. This strain analysis is<br />

much more complex than either stress<br />

method, but it also is a more rational<br />

and usually less restrictive approach.<br />

Determination of the longitudinal strain<br />

with nonlinear steel properties and subject<br />

to biaxial stresses is performed with<br />

a finite-element computer program.<br />

Subsequent to the very detailed review<br />

of the stresses involved in this installation,<br />

the current drill alignment was<br />

supported by Worley Parsons Calgary,<br />

based on the maximum calculated strain<br />

being below the maximum allowable<br />

strain for the crossing using limit states<br />

analysis. Colt used the minimum drill<br />

path radius of 170 metres and compared<br />

the strain at this location to the maximum<br />

strain allowable for the NPS24 crossing<br />

pipe. The results were deemed acceptable<br />

as per the above discussion.<br />

In addition, Colt has recommended<br />

running a geo-pig through the crossing<br />

within two years of the start of pipeline<br />

operation. This can be used to verify the<br />

geometry of the pipe within the crossing<br />

and reconfirm the results of the limit<br />

states analysis. It is anticipated that the<br />

final geometry of the drill profile will be<br />

better than the lowest indicated radius<br />

of 172 metres.<br />

The purpose of this article is not to<br />

support less conservative analysis as<br />

a general rule for HDD installations but<br />

rather, given the difficult circumstances<br />

encountered at the site, to illustrate that<br />

this method of analysis is applicable and<br />

required in certain circumstances. HDD<br />

installations of pipelines beneath pipeline<br />

route obstructions are technically<br />

challenging, as are the determination of<br />

the construction stresses. These installations<br />

are such that future repair and<br />

cleanup if a problem develops, are<br />

not possible or are extremely difficult<br />

due to the location and depth of these<br />

installations. Therefore, a conservative<br />

approach to the design provides some<br />

assurance that problems should not<br />

occur at this type of crossing.<br />

This article is an edited version of a paper entitled<br />

Does the HDD reaming pass remove extreme<br />

alignment dog-legs: Case History by James P.<br />

Murphy, Glen Fyfe, Trevor Giesbrecht and Wes<br />

Dyck. The paper is to be presented at No-Dig<br />

2009 Toronto, Canada. Please refer to the paper<br />

for references and acknowledgements.<br />

Below: Crossing Alignment at Pine<br />

Creek- ROW sandwiched between<br />

adjacent ROWs.<br />

Rehabilitating New<br />

York City’s NCA<br />

By A Noble, D Roberts and A Fareth<br />

Constructed between 1885 and 1891, the New Croton Aqueduct<br />

(NCA) in New York State is a 50 km tunnel conveying water from<br />

the Croton watershed north of New York City to distribution<br />

systems in the Bronx and Manhattan. The NCA has benefited from<br />

an extensive design, inspection and rehabilitation program.<br />

The NCA rehabilitation program<br />

has been underway in phases since 1993,<br />

with inspections scheduled to minimise<br />

outages, allowing this strategic aqueduct<br />

to remain in service during critical seasonal<br />

periods. Between 1993 and 1997<br />

a series of in-tunnel investigations were<br />

performed in the open channel portion of<br />

the NCA, consisting of field inspection,<br />

non-destructive geophysical testing, and<br />

coring of the brick liner.<br />

Between November 2004 and<br />

September 2005, a major inspection<br />

program was conducted to assess the<br />

condition of the 11 km long pressurised<br />

section and all shafts, headhouses and<br />

blow-off structures along the entire 50 km<br />

alignment. Inspection methods included<br />

using an underwater remote operated<br />

vehicle (ROV) equipped with sonar and<br />

cameras to inspect the deep siphon, fibre<br />

optics examinations of probe holes drilled<br />

through and beyond the brick lining, and<br />

core holes and geophysical inspections to<br />

assess properties of the liner and behindthe-liner<br />

materials. A water pressure and<br />

test grouting program was conducted<br />

to assess methods and expected grout<br />

takes for the rehabilitation work in the<br />

pressurised sections. The rehabilitation<br />

program is anticipated to be completed<br />

in 2010.<br />

Part 1: planning and design<br />

The overall concept for rehabilitation<br />

of the NCA was developed in the early<br />

1990s, at which time a far-reaching program<br />

for achieving a logical and practical<br />

approach to the work was established.<br />

Since outages could only take place seasonally,<br />

contracts for any program had to<br />

be appropriately sized to coincide with<br />

the seasonal outages, while taking into<br />

account the operational needs of other<br />

water supply aqueducts owned and operated<br />

by NYCDEP.<br />

The design for the NCA rehabilitation<br />

was initially based on the results of previous<br />

investigations performed within the<br />

aqueduct’s gravity flow section in 1993<br />

and 1996. The field investigation program<br />

in 1993 included:<br />

• Visual inspection of 9.6 km of tunnel<br />

• Geophysical surveys of 9.6 km of tunnel<br />

• Remote operated vehicle (ROV) inspections<br />

• Gould’s Swamp siphon<br />

• Harlem River siphon<br />

• Probe and core drilling<br />

• Fibre optic scope inspection.<br />

The field investigation program in 1996<br />

included:<br />

• Visual inspection of the remaining 29<br />

km of gravity flow tunnel<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

The NCA is a 3.73 to 4.34 metre diameter, brick-lined circular, and horseshoe-shaped water tunnel.<br />

Except at two siphons, the aqueduct operates as an open channel conduit from the New Croton Reservoir<br />

downstream 39 km to the Jerome Park Reservoir in the Bronx. The remaining 11 km is operated as a<br />

pressurised conduit and includes a major siphon, of circular cross-section, under the Harlem River. A total of<br />

163 million bricks were used in the construction, enough to build a 48 km wall around Manhattan Island,<br />

3 metres thick and 15 metres high.<br />

The aqueduct has a flow capacity of approximately 1,100 million litres of water per and supplies on average<br />

ten per cent of New York City’s drinking water. The City’s water supply system is operated and maintained<br />

by the New York City Department of Environmental Protection (NYCDEP). Until a partial inspection in 1982,<br />

the NCA had flowed continuously since its completion nearly 100 years before. Flow tests have confirmed<br />

that the NCA can convey up to 290 million gallons per day.<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

56<br />

57

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!