05.01.2015 Views

North American Special - Trenchless International

North American Special - Trenchless International

North American Special - Trenchless International

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Rehabilitation of a return<br />

line for cooling water<br />

An innovative low pressure pipeline repair technique has been tested at a power plant in Berlin.<br />

Michael Roeling describes the procedure and successful outcome of the test.<br />

With a capacity of 600 MW, Reuter<br />

West is the most powerful heat and power<br />

plant in Berlin, Germany. It consists of<br />

two equal units, each with an output of<br />

300 MW (block D and E), which were put<br />

into operation in 1987 and 1989 respectively<br />

and located next to the existing old<br />

power plant, Reuter.<br />

During recent routine maintenance<br />

checks it was noticed that two of the four<br />

return pipes connecting the side coolers<br />

with the main cooling return line between<br />

the cooling tower and unit E were showing<br />

leakages caused by pitting corrosion. The<br />

leaking pipes are made of welded steel,<br />

with a nominal diameter of 600 mm and are<br />

operated with a maximum pressure of 29<br />

psi. The pipeline had been partly assembled<br />

by welding half pipes together on site,<br />

causing tolerances in diameter, an unusual<br />

trait for steel pipelines.<br />

The return lines, together with many other<br />

lines, are installed in a service duct below a<br />

pavement designed for heavy-duty trucks.<br />

The replacement of larger pipe sections<br />

would have required the opening of the<br />

pavement, digging a trench and removing<br />

the reinforced concrete floor. This method<br />

was rejected from the beginning; primarily<br />

due to the obstruction it would cause to<br />

internal plant traffic, but also for cost reasons.<br />

The replacement of small sections<br />

inside the closed service duct by hand was<br />

also discussed as a possible alternative.<br />

However, the cost would have been quite<br />

high. In either case, the replacement could<br />

never have been executed within the time<br />

frame.<br />

BKP Berolina Polyester GmbH & Co<br />

offered to install the new Berolina-LP-Liner,<br />

the first field test of the product. This<br />

renovation solution promised cost advantages<br />

for the power plant’s owner Vattenfall<br />

Europe. Plant management decided to<br />

renovate a test section using the liner and<br />

await a result before making a final decision<br />

about the method of renovation or<br />

replacement.<br />

Preparation<br />

As the condition of the leaking pipes —<br />

except the pitting holes — was generally<br />

still good, the final decision on method was<br />

postponed for several months. The leakages<br />

were closed by welding steel plates<br />

over the holes. A 40 metre test section was<br />

left for the liner renovation test. This section<br />

was limited by a 90 degree bend with a<br />

wall duct that followed on one side. On the<br />

other side of the section, and an additional<br />

90 degree bend led into an extension section.<br />

The distance between the upper pipe,<br />

which had to be renovated, and the ceiling<br />

measured only 3 to 5 cm. First the bends<br />

were removed because the liner installation,<br />

and subsequent curing by using<br />

UV-light, required reasonably straight sections.<br />

Afterwards the section was scheduled<br />

to be cleaned by high pressure jetting.<br />

Unfortunately this was not sufficient as the<br />

pipe was encrusted with a hardened buildup<br />

that could have damaged the liner.<br />

An intensive cleaning and levelling of the<br />

pipe’s inner surface was carried out using<br />

a special scraper known as a ‘go-devil’<br />

(pictured).<br />

The insertion of the light train.<br />

Installation of the liner<br />

The liners were fibre reinforced plastics<br />

(FRP), using several layers of glass-fibre<br />

mesh reinforcement together with polyester<br />

resin which is cured by using UVA-light.<br />

So far the Berolina-Liners have been used<br />

for renovation of storm water or sewer<br />

pipes. The water tightness test in those<br />

cases followed the procedures of EN 1610<br />

with a maximum test pressure of 7.25 psi<br />

when using water and 1.45-2.90 psi when<br />

using air as a pressure medium. Based on<br />

the existing liner products the company<br />

ventured into a new product line to enable<br />

the renovation of pressure pipes.<br />

In this project, the liner for low pressure<br />

pipes was chosen to complete the test.<br />

Following the pipe cleaning, a polyethylene<br />

gliding foil was pulled in the pipe to<br />

protect the liner from damage by welding<br />

burrs or any remaining hardened build-up<br />

when being pulled in.<br />

Then the liner was pulled into the pipe<br />

with a hydraulic winch and closed with<br />

end caps.<br />

The liner was then inflated by air pressure<br />

in order to insert the UVA-light source.<br />

The light source consisted of a light train<br />

with eight metal halide lamps. The light<br />

spectrum was synchronised to the photo<br />

catalysts in the polyester resin. A curing<br />

unit, type Compact and made by HC<br />

PipeTech, was used for curing the liner.<br />

Due to the very small external dimensions<br />

of this equipment, the installation crew<br />

was able to bring the unit into the service<br />

duct by hand and through a door only 90<br />

cm wide.<br />

After the insertion of the light train, the<br />

liner was expanded close fit to the inner<br />

wall of the host pipe. The special design<br />

of the liner allows it to dialate over a<br />

relatively wide range of diameters – from<br />

5 per cent under measurement up to 5<br />

per cent over measurement compared<br />

with the specified size of the host pipe.<br />

Therefore, the large tolerances in diameter<br />

of the host pipe were not an issue for<br />

the liner.<br />

After dilatation, the light source was<br />

ignited and pulled through the liner at a<br />

defined speed. The UVA-light enabled the<br />

polymerisation of the polyester resin.<br />

After the curing had been completed<br />

the liner ends were cut with precision and<br />

the installed liner could be examined. The<br />

smoothness of the inner liner surface was<br />

striking. In a public sewer system the job<br />

would have been completed by this stage.<br />

In this case, the connection to the existing<br />

pipeline had to be made. Flange collars,<br />

also made of FRP, were bonded to the<br />

protruding liner ends and the continuing<br />

pipeline components with flange joints<br />

attached. This design was necessary for<br />

two reasons. Firstly, the design allowed for<br />

the opening of the test section for future<br />

inspections without destroying any part of<br />

the pipeline. Secondly, a joint by laminating<br />

was not possible because of the very<br />

narrow distance between the pipeline<br />

and the reinforced concrete ceiling. Even<br />

for the flange type of connection used in<br />

this project, the concrete cover had to<br />

be removed at some locations to allow<br />

enough working space.<br />

Summary<br />

The project described above has been<br />

accomplished in an extremely short time<br />

frame, especially considering the very<br />

tight working space. The renovation of the<br />

straight section, including cleaning with<br />

the ‘go-devil’, pulling in of gliding foil and<br />

liner, curing and exact cutting was done<br />

in a single day. The replacement of the<br />

pipe section with half pipes would have<br />

taken three to four weeks. The time taken<br />

for connecting the liner with the rest of<br />

the pipeline, as well as for the preparing<br />

works for removing the old steel bends,<br />

was within the normal time frame for this<br />

kind work. The pipe section renovated by<br />

ID 150 mm (~ 6‘‘) up to<br />

ID 1000 mm (~ 40‘‘)<br />

Glass fibre and/or polyester<br />

webs impregnated with resin<br />

Brief installation time<br />

Bridging of profile<br />

differences and cross<br />

sections<br />

Chemical resistant<br />

Suitable for all profiles<br />

Seamless construction<br />

Smooth surface<br />

Ready for installation<br />

Berolina-Liner System<br />

®<br />

Lightspeed sewer rehabilitation in 5 continents<br />

CIPP with UV-light<br />

The renovated pipe section.<br />

using the Berolina-LP Liner has been in<br />

full and unrestricted operation for over six<br />

months at the time of writing. From testing<br />

so far the Berolina-LP-Liner can be<br />

rated as reliable for this kind of pipeline<br />

renovation in power plants and other low<br />

pressure pipes.<br />

BKP Berolina Polyester GmbH & Co. KG, Berlin, Germany. For more information visit www.bkp-berolina.de or<br />

contact +49-30-36471-400 email info@bkp-berolina.de<br />

BKP Berolina Polyester GmbH & Co. KG<br />

Am Zeppelinpark 22<br />

13591 Berlin, Germany<br />

®<br />

UV-light source<br />

Tel.: +49 (0) 30 / 36471-400<br />

Fax: +49 (0) 30 / 36471-410<br />

info@bkp-berolina.de<br />

UVA-light in action.<br />

Insertion of the Berolina-LP-Liner.<br />

Less space required<br />

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

30<br />

31

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!