05.01.2015 Views

North American Special - Trenchless International

North American Special - Trenchless International

North American Special - Trenchless International

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

SPR technology<br />

SPR utilises steel-reinforced interlocking PVC profile strips sealed<br />

in place by a high-pressure grout. The installation equipment can be<br />

utilised via standard manhole access points without site excavation.<br />

Sekisui’s CPT SPR technology can also be installed in vertical<br />

applications such as wet wells, access shafts and other large diameter<br />

structures.<br />

SPR is a spiral winding technique which is particularly well suited<br />

to the renewal of very large diameter pipelines – up to 5 metres. In<br />

addition to standard circular profiles, egg-shaped and horseshoe<br />

profiles, any custom shapes can also be provided. The winding<br />

machine is specially adapted to each project, enabling it to cover<br />

a very wide range of applications. SPR technology is already being<br />

successfully deployed in Asia and the USA to renew large diameter<br />

pipelines.<br />

The SPR process is unique as it can provide a customised structural<br />

solution to aging pipelines. It can be engineered to correct hydraulic<br />

anomalies as well as restore the slope of the original pipe. The<br />

interlocking edges of the profile create an impermeable mechanical<br />

lock that can withstand strong deformational forces.<br />

SPR liners have been tested in accordance with industry standards<br />

and meet or exceed the standards for spiral wound PVC Profile Wall<br />

Liners ASTM F – 1697-02 and F 1741-02a. Furthermore the SPR PVC<br />

profile has a Manning’s coefficient of n = .010.<br />

PROJECTS<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

All wound up in Poland<br />

Szczecin, Poland is the first city in Europe to benefit from a new Japanese renewal technology, spiral<br />

pipe renewal (SPR).<br />

When the tender for a renewal project<br />

in Szczecin, Poland was first issued at the<br />

beginning of 2008, GRP short-pipe lining<br />

was specified. However, after some extensive<br />

research by the customer it was found<br />

that it would be very difficult to maintain the<br />

required water flow rates using the chosen<br />

technique. Severe deformation of the old<br />

pipe, which was not identified during the<br />

planning stage, meant that if a GRP shortpipe<br />

lining was used, the diameter of the<br />

renewed pipe would be much smaller,<br />

and so reduce the capacity of the new<br />

pipeline.<br />

Another challenge was posed by the fact<br />

that the pipeline being renewed in Szczecin<br />

was a main collector in the city centre,<br />

where it would be impossible to construct a<br />

dewatering system. Even though a large pit<br />

for the GRP lining had already been dug,<br />

at the last minute the customer decided<br />

– based on the new demands faced – to<br />

opt for the first ever European use of SPR<br />

technology.<br />

The masonry-lined combination sewer<br />

was built over a century ago. The condition<br />

of the sewer had deteriorated severely<br />

in recent years. As a result of continuous<br />

traffic and other external loads, longitudinal<br />

cracks had formed along the crown of the<br />

pipe, leading to increased deformation.<br />

Renewal had become a matter of urgency.<br />

There were also a large number of deposits<br />

and other obstacles protruding as much as<br />

50 cm into the pipe. Consequently, it was<br />

clear that thorough cleaning and jet-grouting<br />

work would have to be carried out prior<br />

to the renewal process. The SPR installation<br />

process can be divided into three key<br />

stages: the winding of the PVC profile, the<br />

construction of the bracing system and the<br />

grouting of the annulus<br />

Winding process<br />

The winding was executed starting from<br />

the manhole access shaft downstream to<br />

the next shaft. Based on the local conditions<br />

and the existing 18 metre long pit, the<br />

stretch of pipeline scheduled for renewal<br />

was divided into four segments. The winding<br />

machine installed the profile in the existing<br />

pipeline guided the profile and formed it<br />

into the desired shape, with an inner<br />

diameter of 2,240 x 1,600 mm.<br />

The winding machine<br />

moved one<br />

The SPR winding machine pulls the SPR profile into place and<br />

engages the dual locking mechanism.<br />

profile width forward on each rotation of the<br />

profile, locking the profile edges to form a<br />

water-tight pipe in the process.<br />

As soon as the machine’s forward<br />

momentum had taken it to the next shaft,<br />

the winding process was stopped and<br />

the profile separated. The team from the<br />

Polish construction company, together with<br />

the Japanese engineers, laid the<br />

winding machine and<br />

the profile reel to the<br />

next shaft, which<br />

then served as the<br />

new starting<br />

Bracing the shaft.<br />

point for the next installation phase and as<br />

the conduit through which the profile was<br />

again guided by the winding machine, as<br />

in the first phase.<br />

Bracing system<br />

In the next step, when the winding process<br />

was complete, the expert team constructed<br />

the bracing system. The braces were introduced<br />

through the shaft into the spiral<br />

wound pipe and carefully installed. The<br />

constructed cross-section of the bracing<br />

system prevents lifting of the new spiral<br />

wound pipe during subsequent grouting<br />

and prevents deformation.<br />

Grouting<br />

The grouting process for each renewal<br />

segment comprised injection of the grout<br />

into the annulus between the old pipe and<br />

the spiral wound PVC profile and curing of<br />

the grout. The team executed the grouting<br />

work in three stages. Then the braces<br />

were dismantled and installed in the next<br />

renewal segment. The pit area was grouted<br />

to a statically determined height above the<br />

spiral wound PVC profile.<br />

SPR technology in Poland.<br />

Below: SPR PVC profile is unreeled and fed<br />

into the winding machine.<br />

For further information contact Christopher Moritz at KMG LinerTec GmbH:<br />

christopher.moritz@sekisuicpt.com<br />

Summary<br />

All work was carried out by the team<br />

comprising workers from the local Polish<br />

agent of Sekisui CPT and Japanese technical<br />

specialists. The renewed sewer<br />

is beneath one of the main streets in<br />

Szczecin, and collects the rainwater and<br />

sewage from all the smaller surrounding<br />

systems. Work was interrupted several<br />

times due to flooding and above average<br />

rainfall, and lost time had to be made up<br />

for at night. However, since SPR can also<br />

be applied with drainage, the installation<br />

could be resumed without problem following<br />

the enforced breaks.<br />

Headed by Christopher Moritz, an<br />

expert team provides technical know-how<br />

and support covering all aspects of the<br />

new technology. “One of the key benefits<br />

of the SPR PVC profile from Sekisui is its<br />

environmental sustainability – including 60<br />

per cent less fossil fuel consumption, 30<br />

per cent less energy use and four times<br />

lower CO2 emissions in production.<br />

“That is one of the factors that will<br />

enable us to achieve our goal of delivering<br />

premium renewal solutions and becoming<br />

the market leader in the renewal of<br />

large-diameter pipelines in Europe,” said<br />

Mr Moritz.<br />

Despite the very difficult weather conditions,<br />

the European premiere of SPR<br />

technology was successfully completed<br />

within approximately two months.<br />

PROJECTS<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

26<br />

27

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!