05.01.2015 Views

North American Special - Trenchless International

North American Special - Trenchless International

North American Special - Trenchless International

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Insertion of the liner takes about three hours.<br />

Cured liner in the accessible<br />

oval profile.<br />

shaft the liner was equipped with pressure<br />

locks so that it could then be expanded in<br />

the sewer using compressed air.<br />

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

liners of 32.5 metres and 173.6 metres in<br />

length had to be installed, including all<br />

preparatory and related work.<br />

Light-curing GFRP liner<br />

The related work included the opening<br />

of the connection lines that are covered<br />

up by the liner. This work played a decisive<br />

role in the selection of the process<br />

— due to the time factor. The planners<br />

at HanseWasser decided at the outset<br />

that only light-curing GFRP liner systems<br />

were to be considered. With this pipe lining<br />

variant there is no need to consider<br />

the reduction of stresses in the liner,<br />

which can take several days. The lack of<br />

shrinkage means that there are no axial<br />

movements and the connections can be<br />

milled out directly after the curing of the<br />

liner without the risk of changes in length.<br />

Considering the high density of connections<br />

in Ostertorsteinweg and the fact<br />

that behind almost every connection there<br />

is a multi-storey residential building with<br />

retail space at ground floor level, smooth<br />

maintenance of the drainage was especially<br />

important. In order to maintain the<br />

drainage during the rehabilitation, DN 400<br />

free-flow pipelines were installed above<br />

ground for temporary water drainage,<br />

including sufficiently powerful pumps.<br />

At exactly 9:00 pm, the last train had<br />

just disappeared around the corner and<br />

the preparatory cleaning work began in<br />

the collection drain so that at 11:00 pm<br />

the Brandenburger construction crew<br />

could begin with the insertion of the liner<br />

through the start shaft near Poststraße. The<br />

10.4 tonne glass fibre tube was let down<br />

into the opened shaft out of the transport<br />

packaging and, using an electrical<br />

conveyor belt, pulled with a steel cable<br />

connection to the target shaft at the<br />

Weberstraße. A foil that had been laid<br />

down protected it from damage. At 2:00 am<br />

on Saturday morning, the entire 173 metre<br />

length of liner lay in the Ostertorsteinweg<br />

collection drain. At the start and end of the<br />

Lamp train and curing<br />

A lamp train with nine UV modules,<br />

each 1,000 watt maximum power, was<br />

pulled through the form-fit calibrated liner<br />

with pre-calculated speed. The connection<br />

to the new UV technology with the<br />

special resin recipe made it possible to<br />

also achieve curing in a very short time.<br />

The light-curing process lasted a total of<br />

four and a half hours at a train speed of<br />

65 cm per minute and was recorded in<br />

all relevant parameters, including speed,<br />

exposure dose and liner temperature. The<br />

computer-aided documentation of this<br />

data allowed for any eventual deviations<br />

from target values of the technical parameters<br />

to be recognised immediately and<br />

allowed tracking of the curing procedure.<br />

Connection lines<br />

Directly after the curing of the liner,<br />

work began to open the connections. By<br />

midday Saturday, all 48 residential connections<br />

in the rehabilitated collection<br />

drain were milled open and at the start<br />

of the tram traffic on Monday morning at<br />

9:00 am they were all connected according<br />

to the specifications of the client. This<br />

was accomplished with the installation of<br />

glass fibre short liners up to 50 cm over<br />

the first pipe connection. The direct support<br />

area was filled with an epoxy resin<br />

system so that it was waterproof and<br />

had no cavities. The local residents were<br />

hardly affected by the project in terms<br />

of disruptive effects normally associated<br />

with construction projects.<br />

Further construction sections<br />

The combined second and third construction<br />

sections in Ostertorsteinweg<br />

were performed over ten days. As the<br />

tram traffic was already suspended, there<br />

was not the same degree of time pressure<br />

as in the first section. Two 115 and<br />

128 metre long liners were installed with<br />

all preparatory and related work. There<br />

was a work pause of almost four weeks<br />

after the first construction section due<br />

to a large number of residential connections,<br />

in the area of the collection drain<br />

yet to be rehabilitated, that were renewed<br />

in open cut. This entailed excavation<br />

work but also the renewed preparation<br />

of the surrounding drainage conduit. The<br />

independent laboratory inspection, as<br />

a major component of the quality management<br />

system, was performed in the<br />

Ostertorsteinweg project by engineering<br />

company Siebert in Oststeinbek. Their<br />

analysis of the liner samples taken from<br />

the construction site came to the positive<br />

result that all specified parameter nominal<br />

values of all liners were exceeded by<br />

at least ten per cent.<br />

Summary<br />

HanseWasser was pleased with the<br />

successful and on schedule completion<br />

of the rehabilitation project. The successful<br />

Ostertorsteinweg rehabilitation project<br />

accentuated not only the special advantages<br />

of the liner process that was used,<br />

but is also another example for the plus<br />

factors of the trenchless pipe lining technology<br />

as a whole.<br />

The rehabilitation using pipe lining with light-curing<br />

reaction resin systems<br />

The procedure has already proved itself in 26 countries, in which<br />

over 2,000 km of sewers have been installed in diameters from DN<br />

150 to DN 1000. In principle, the Brandenburger pipe liner procedure<br />

is based on the same basic idea as all other liner. A tube support<br />

saturated with reactive synthetic resin is brought into the sewer,<br />

where it is expanded with inside pressure to be form-fitting, i.e.<br />

with no ring gap, and then cured by a chemical reaction of the resin<br />

to a self-supporting inner lining. This technology is consequently<br />

trenchless, as no type of earthworks are necessary. The flexible<br />

liner tubes are typically applied using existing inspection shafts<br />

in the sewer. The special characteristics that differentiate the<br />

Brandenburger liner system from other pipe lining types are:<br />

• Use of seamlessly wound liners out of glass fibre laminate webs,<br />

• Unique saturation of the raw materials before the production of<br />

the pipe liner with UV-reactive UP resin (possibly with addition<br />

of peroxides for the variation “hybrid curing” for larger wall<br />

thicknesses over 10 millimetres)<br />

• Drawing in the liner on a protective foil and form-fitting expansion<br />

using compressed air<br />

• Curing of the liner using precisely dosed UV exposure<br />

(“BLUETEC® technology”).<br />

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

24<br />

25

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!