05.01.2015 Views

North American Special - Trenchless International

North American Special - Trenchless International

North American Special - Trenchless International

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

In this issue | Canada | USA | Japan | France | China | UK | Saudi Arabia | Germany | Australia<br />

Asset Management<br />

Robotics<br />

Oil & Gas<br />

<strong>North</strong><br />

<strong>American</strong><br />

<strong>Special</strong><br />

April 2009<br />

Issue 3<br />

The official magazine of the ISTT


herrenknecht AG | utility tunnellinG | t r A ffic tunnellinG<br />

u SA<br />

lOnG DiStAnce tunnellinG in the uSA<br />

SetS neW StAnDArDS.<br />

POrtlA n D | u SA<br />

PROJECT DATA<br />

M-1122M, AVND2000AB<br />

Diameter: 2,605mm<br />

Max. torque: 780kNm<br />

Tunnel length: 9 drives,<br />

totaling 2,393m<br />

Geology: sand, gravel, loam<br />

CONTRACTOR<br />

KBB JV<br />

(Bilfinger Berger AG,<br />

Kiewit Construction<br />

Co.)<br />

S-348, Mixshield KBB JV<br />

Diameter: 7,700mm (Bilfinger Berger AG,<br />

Driving power: 1,000kW Kiewit Construction<br />

Tunnel length:<br />

Co.)<br />

6,189m + 2,721m<br />

Geology: sand, silt, gravel<br />

with stones and stone blocks<br />

An impressive record result in long distance tunnelling: In scarcely 1.5 months, the Herrenknecht<br />

Micromachine AVND2000AB achieved a U.S. record in Portland (Oregon). For a large<br />

wastewater project, the “Combined Sewer Overflow System” on the Willamette River, the<br />

construction site team succeeded in precisely and rapidly producing a 938 meters long<br />

microtunnel without intermediate shaft which is the longest ever excavated by a machine.<br />

In times of heavy rainfall, the “Combined Sewer Overflow System” on the western and<br />

eastern banks of the river, will temporarily store the city’s mixed water and then channel it<br />

to a treatment plant in a controlled way. In order to connect the existing wastewater lines<br />

to the new storage tunnel, a Herrenknecht Micromachine is boring a total of nine partial<br />

sections with an overall length of 2,393 meters through sand, gravel and loam. Although iron<br />

rail spikes and timber dock piles in the underground made tunnelling more difficult, the<br />

machine achieved the new milestone on the “Outfall 46” section.<br />

Until completion in 2011, a total of four Herrenknecht tunnelling machines will have<br />

been in operation. Among them, the S-348 Mixshield (Ø 7.7m) which is excavating an almost<br />

nine kilometer long stretch of the new storage tunnel on the eastern river bank. Thanks to<br />

best weekly performances of up to 160 meters, 3,732 meters of tunnel could already be<br />

completed by January 2009.<br />

This means, that both machine and environmental protection are moving forward in<br />

Portland.<br />

Herrenknecht AG<br />

D-77963 Schwanau<br />

Phone + 49 7824 302-0<br />

Fax + 49 7824 3403<br />

marketing@herrenknecht.com<br />

Herrenknecht Corporation<br />

98390 Sumner, USA<br />

Phone +1 253 447 2335<br />

Fax +1 253 863-9397<br />

joconnell@herrenknecht-usa.com<br />

www.herrenknecht.com


Dec Downey<br />

Istt Chairman<br />

<strong>Trenchless</strong> Middle East, organised<br />

recently in Dubai by Westrade Group,<br />

was a great success attracting almost<br />

70 participating companies and a host<br />

of visitors from 32 countries. A large<br />

group of German companies, led by<br />

GSTT Chairman Prof Jens Hoelterhoff and<br />

Secretary Klaus Beyer, participated and<br />

we were once again generously entertained<br />

by the German Consul General<br />

at the residence. We enjoyed the participation<br />

of some 30 delegates in our<br />

<strong>Trenchless</strong> Masterclass and the lively<br />

discussions spilled over into the breaks,<br />

signalling that the event formula is working<br />

and, with experience, will improve<br />

even more. Westrade’s performance in<br />

Dubai hopefully gives us just a hint of<br />

what they will be able to achieve for ISTT<br />

in Singapore in 2010.<br />

This weekend I am travelling to Hong<br />

Kong to promote the objectives of ISTT by<br />

speaking at the <strong>International</strong> Conference<br />

on Utility Management and Safety, many<br />

thanks to our HKSTT colleagues for securing<br />

this invitation. In preparation I have<br />

spent some time thinking through ideas<br />

about the contribution our technologies<br />

make to 21st Century pipeline construction<br />

and rehabilitation. We often speak<br />

about the challenges of ageing underground<br />

infrastructure and the benefits<br />

of our technologies in addressing urban<br />

renewal with minimum disruption, but<br />

there is much more to say about the contribution<br />

of <strong>Trenchless</strong> Technology to the<br />

maintenance of existing networks and the<br />

construction of pipelines for the future.<br />

It seems to me that many of today’s<br />

problems can be attributed as much<br />

to the historic choices of materials and<br />

methodology available at the time of construction<br />

as to time-related deterioration<br />

and shortcomings in construction supervision.<br />

With the clarity of hindsight, we can<br />

identify some of our past mistakes and<br />

build on this hard-earned understanding<br />

to do better for our communities, and the<br />

trenchless option has so much to offer in<br />

these initiatives.<br />

<strong>Trenchless</strong> methods facilitate construction<br />

with less joints or better-made joints,<br />

with potentially more durable materials<br />

and with less reliance on hard-to-supervise<br />

skills in the darker corners of the<br />

underground. Today we have improved<br />

geotechnical exploration and utility location<br />

skills, though further development is<br />

required. The practices of microtunnelling,<br />

pipe ramming and horizontal directional<br />

drilling have improved substantially.<br />

Modern pipe materials properly installed<br />

by these methods must surely offer sustainable<br />

solutions to the challenge.<br />

We have an increasing tool box of technologies<br />

to address ageing pipelines and<br />

provide lasting solutions to these problems.<br />

While condition assessment and<br />

service connection reinstatement remain<br />

challenging, many of the rehabilitation<br />

techniques we use have been tried and<br />

tested over a considerable length of time<br />

and our retrospective evaluations can<br />

underpin service life predictions. New<br />

techniques continue to evolve, along with<br />

our understanding of the pipe-soil interface.<br />

We have high hopes for emerging<br />

structural spray and reinforced linings.<br />

Quality of construction work and safety<br />

of installation crews are very important<br />

facets of our business. In my Hong Kong<br />

presentation I hope to show that our<br />

industry has placed due emphasis on<br />

these aspects, which will extend the<br />

appeal of our skills to a larger audience<br />

of professionals in a marketplace where<br />

<strong>Trenchless</strong> Technology is an essential<br />

consideration.<br />

FROM the CHAIRMAN's desk<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

1


Issue 3 - April 2009<br />

Great Southern Press<br />

Pty Ltd<br />

For the Americas call +1 216220 5126<br />

For Europe call +453696 5124<br />

For the United Kingdom call +44 208133 5127<br />

For Australasia call +61 39248 5100<br />

For Asia call +85 28124 5122<br />

query@trenchlessinternational.com<br />

www.trenchlessinternational.com<br />

Editor: Chris Bland<br />

Associate Editor: Kate Pemberton<br />

Sales Manager: Tim Thompson<br />

Senior Account Manager: David Marsh<br />

Sales Representative: Brett Thompson<br />

Design Manager: Michelle Bottger<br />

Designers: Venysia Kurniawan,<br />

Stephanie Rose, Sandra Noke<br />

Proofing: Michelle Perl<br />

Event Co-ordinator: Stephanie Fielden<br />

GPO Box 4967<br />

Melbourne VIC 3001 Australia<br />

Fax: +61 3 9602 2708<br />

ISSN: 1836-3474<br />

In this issue | Canada | USA | Japan | France | China | UK | Saudi Arabia | Germany | Australia<br />

The official magazine of the ISTT<br />

Asset Management<br />

Robotics<br />

Oil & Gas<br />

<strong>North</strong><br />

<strong>American</strong><br />

<strong>Special</strong><br />

April 2009<br />

Issue 3<br />

Photo courtesy of <strong>American</strong> Augers.<br />

REGULARS<br />

From the Chairman’s Desk 1<br />

Executive Director’s Report 4<br />

Upcoming Events 16<br />

About ISTT/Membership 69<br />

ISTT Membership/Directory 69<br />

Contacts and Addresses of Affiliated Societies 70<br />

Advertisers’ Index 72<br />

Subscription and Information 72<br />

News<br />

World Wrap 6<br />

Pipes & People 8<br />

News in Brief 10<br />

istt news<br />

<strong>Trenchless</strong> in Toronto 12<br />

<strong>Trenchless</strong> City: preserving the environment 14<br />

PFTT celebrates ten years 16<br />

Remembering a trenchless Pioneer 17<br />

special feature<br />

Made in China 18<br />

Projects<br />

Reconstructing pipes in Wajima City 20<br />

UV light: curing pipe problems 23<br />

All wound up in Poland 26<br />

Alleviating flooding in Ashbourne 28<br />

Rehabilitation of a return line for cooling water 30<br />

Products and Services<br />

Locating laterals in Toronto 34<br />

A guide to manual coating application 35<br />

ASSET MANAGEMENT<br />

Managing assets in Las Vegas 36<br />

Risky business 37<br />

Covering your assets 40<br />

ENVIRONMENT<br />

Delivering desalinated water to Sydney 43<br />

Pipe and conduit<br />

Pipe and conduit<br />

Part one - a brief history and guide 46<br />

Record SWP down under 49<br />

north america<br />

<strong>Trenchless</strong> Technology - building the economy 51<br />

Testing the limits of HDD 53<br />

Rehabilitating New York City's NCA 57<br />

Auger boring through hard rock:<br />

overcoming the challenge 60<br />

HRX: heading across the harbour 62<br />

HDD is the key to the Keystone Pipeline 66<br />

Oil and gas<br />

Undersea HDD rescue in Saudi Arabia 68<br />

This magazine is an official publication of the<br />

<strong>International</strong> Society for <strong>Trenchless</strong> Technology<br />

(ISTT) and is distributed free to members and other<br />

interested parties worldwide. It is also available on<br />

subscription.<br />

The publishers welcome editorial contributions from<br />

interested parties. However, neither the publishers<br />

nor the ISTT accept responsibility for the content<br />

of these contributions and the views contained<br />

therein which will not necessarily be the views of the<br />

publishers or the ISTT. Neither the publishers nor the<br />

ISTT accept responsibility for any claims made by<br />

advertisers.<br />

All communications should be directed to the<br />

publishers.<br />

ROBOTICS<br />

The role of robotics in the trenchless industry 32<br />

2 3


EXECUTIVE DIRECTOR'S REPORT<br />

John Hemphill<br />

Istt Executive Director<br />

<strong>International</strong> Society for<br />

<strong>Trenchless</strong> Technology<br />

Chairman: Dr Dec Downey<br />

dec.downey@jasonconsult.com<br />

Vice-Chairman: Dr Samuel Ariaratnam<br />

ariaratnam@asu.edu<br />

Executive Director: John Hemphill<br />

hemphill@istt.com<br />

Membership Secretary: Kyoko Kondo<br />

kondo@istt.com<br />

Executive Sub Committee<br />

Derek Choi: China<br />

Karel Franczyk: Czech Republic<br />

Gerda Hald: Denmark<br />

Norman Howell: United Kingdom<br />

Olga Martynyk: Ukraine<br />

It is Wednesday, 18 February. I am on<br />

a Boeing 777 at 38,000 feet somewhere<br />

over the Atlantic Ocean on my way home<br />

from Dubai, UAE where I participated in<br />

teaching, along with Drs Dec Downey<br />

and Sam Ariaratnam, in a highly successful<br />

ISTT Masterclass. The class was a<br />

part of the 2009 <strong>Trenchless</strong> Middle East<br />

<strong>International</strong> Exhibition and Conference.<br />

The Masterclass was a first for ISTT. It<br />

featured technical presentations by the<br />

three of us on subjects ranging from new<br />

installation techniques, such as horizontal<br />

direction drilling and pipe bursting,<br />

to pipe rehabilitation, including pipe linings<br />

and pipeline condition assessment.<br />

These presentations were supplemented<br />

by presentations from trenchless manufacturing<br />

and contractors on real-world,<br />

case-studies of trenchless projects.<br />

The Dubai ISTT Masterclass had over<br />

40 participants from several Middle<br />

Eastern countries including the UAE,<br />

Saudi Arabia, and Oman, as well as<br />

attendees from Russia, Bulgaria and the<br />

United Kingdom.<br />

The Masterclass format seems ideal<br />

for getting the message on <strong>Trenchless</strong><br />

Technology to regions of the world where<br />

we have no affiliated societies and to<br />

affiliated societies that have a need for<br />

trenchless training but may not be in<br />

a position to host an ISTT No-Dig. The<br />

Masterclass format allows the training<br />

to be structured to meet local training<br />

needs. Masterclasses can be put together<br />

relatively quickly and, as the Dubai experience<br />

has shown us, it can be a very<br />

effective training tool.<br />

Our next big event in 2009 is the<br />

<strong>International</strong> No-Dig in Toronto. It is<br />

just around the corner – 29 March to 3<br />

April. By the time this issue of <strong>Trenchless</strong><br />

<strong>International</strong> is published, we will be<br />

co-hosting the No-Dig conference and<br />

exhibition with <strong>North</strong> <strong>American</strong> Society<br />

for <strong>Trenchless</strong> Technology. In addition to<br />

over 140 technical papers authored by<br />

representatives from 15 countries outside<br />

<strong>North</strong> America, the ISTT will recognise<br />

achievements in the trenchless industry<br />

including two product awards, and a<br />

project award. The Society will also make<br />

its fifth award of the ISTT Gold Medal at<br />

the 2009 No-Dig. The Gold Medal Award<br />

is the highest honour bestowed by the<br />

Society to an individual involved in promoting<br />

<strong>Trenchless</strong> Technology in-country<br />

and worldwide.<br />

ISTT’s 2009 educational activities do<br />

not end with the 2009 No-Dig. We will<br />

continue to pursue training opportunities<br />

with affiliates and in other regions of the<br />

world. We anticipate holding several more<br />

Masterclasses this year and in 2010.<br />

Before we know it, the 2010 No-Dig<br />

Conference and Exhibition will be upon<br />

us. The 2010 No-Dig is scheduled to<br />

be held the first week of November in<br />

Singapore.<br />

C<br />

M<br />

Y<br />

CM<br />

MY<br />

CY<br />

CMY<br />

K<br />

www.istt.com<br />

info@istt.com<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Executive Director, ISTT<br />

308 S. Lee Street<br />

Alexandria, VA 22314<br />

United States<br />

Tel: +1 (703) 299-8484<br />

Kyoko Kondo (Ms.)<br />

Membership Secretary ISTT<br />

3rd Nishimura Bldg.,<br />

2-11-18, Tomioka, Koto-ku,<br />

Tokyo 135-0047, Japan<br />

Tel:: +81 (3)5639 9970<br />

FAX: +81 (3)5639 9975<br />

Registered Address:<br />

15 Belgrave Square<br />

LONDON, SW1X 8PS<br />

UK<br />

4


World Wrap<br />

Contract continued in Canada<br />

Insituform Technologies, has been awarded an additional<br />

$US 6 million in sewer pipe rehabilitation work for the City<br />

of Hamilton, Ontario, Canada. Insituform expects to perform<br />

approximately 90,000 feet of small- and medium- diameter<br />

sanitary sewer lining under this contract award. Work on the<br />

project is currently underway and should be completed within<br />

twelve months.<br />

Terra Solutions expands tunnelling division<br />

Terra Solutions will invest in excess of £2.1 million to acquire and<br />

expand the drilling and tunnelling division of environmental services<br />

firm McAllister Brothers. Terra Solutions was established to specialise<br />

in tunnelling and pipe jacking for the laying of water, gas, sewerage,<br />

drainage and oil pipelines, as well as for laying telecommunications<br />

cables.<br />

Saving with HDD<br />

The Haarbach District Authority in Bavaria<br />

Germany is constructing a 7.2 km waste<br />

water disposal system using HDD. The<br />

trenchless solution is 30 per cent less<br />

expensive than the open cut alternative.<br />

Renewal in Mumbai<br />

The City of Mumbai, in an effort to develop the urban<br />

infrastructure and keep pace with rapid population<br />

growth, is working to improve the quality of the water<br />

supply and to upgrade the ageing and overloaded<br />

sewer networks. As part of the upgrade TT-UK and<br />

contracting partner KEPL of Bangalore are undertaking<br />

the replacement and renewal of 17 kms of existing<br />

clayware sewer pipes.<br />

NEWS<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

SSC credits construction<br />

professionals<br />

The <strong>Special</strong>ised Services Company<br />

(SSC) trenchless training program<br />

now offers continuing education<br />

credits to construction professionals.<br />

Each session in the 12 month<br />

series focuses on a different trenchless<br />

application. Participants are<br />

provided a case-based learning<br />

experience that explores topics<br />

such as horizontal auger boring,<br />

HDD, and pipe ramming/bursting.<br />

HDD record on VNG<br />

A HDD record has been set on the<br />

Virginia Natural Gas (VNG) project<br />

Elizabeth River crossing that will link<br />

Norfolk to Newport News under the<br />

Hampton Roads harbour in the United<br />

States. Contractors Mears Group,<br />

Weeks Marine and Bradford Brothers<br />

installed 2.2 km of 24 inch diameter<br />

steel pipeline under the Elizabeth<br />

River reaching a maximum depth of<br />

33 metres.<br />

Sales for Singapore<br />

The Urban Infrastructure & Environmental Products<br />

Company of Sekisui Chemical Corporation has established<br />

Sekisui CPT Asia, a sales company of pipeline<br />

rehabilitation business, in Singapore where demand is<br />

expected to increase in the future. The company will be<br />

engaged in sales of pipeline rehabilitation materials and<br />

machinery in the Asian region as well as supervision and<br />

technical support of construction partners.<br />

NEWS April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

6<br />

7


Pipes & People<br />

Prime Horizontal<br />

pipes & people<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

8<br />

Vale Gary Vermeer<br />

Founder and Chairman Emeritus of<br />

Vermeer Corporation Gary Vermeer passed<br />

away on 2 February 2009 at 90 years of<br />

age.<br />

Mr Vermeer and a cousin started the business<br />

in 1948, after inventing a wagon hoist<br />

five years earlier, which made it easier to<br />

unload corn. Demand for the labour-saving<br />

device from his neighbours prompted him<br />

to open Vermeer Manufacturing Company.<br />

From that small operation, the company<br />

has grown over the past 60 years to an<br />

international organisation that manufactures<br />

agricultural, construction, environmental,<br />

and industrial equipment. Today, Vermeer<br />

Corporation has industrial dealerships in<br />

over 60 countries and on every continent<br />

except Antarctica.<br />

Moles Awards Herrenknecht<br />

US heavy construction industry association<br />

The Moles has presented the Schwanau<br />

entrepreneur Martin Herrenknecht with the<br />

Moles Award 2009.<br />

Dr Herrenknecht is the first European<br />

and non-US citizen to be honoured with this<br />

prize. Dr Herrenknecht was presented with<br />

the Award in New York on 28 January, in the<br />

presence of some 2,000 decision-makers<br />

and representatives of the US heavy construction<br />

industry, as well as the Governor<br />

of New Jersey, Jon S Corzine.<br />

In addition, Dr. Herrenknecht was awarded<br />

honourary Moles membership. The former<br />

US President Herbert C Hoover is also<br />

among those who have been honoured with<br />

the Moles Award in the past.<br />

During the ceremony the presenter<br />

of the Moles Award Committee James<br />

M Marquardt said that the entrepreneur<br />

embodies precisely what <strong>American</strong>s highly<br />

respect, “a competitive spirit, willingness to<br />

tackle difficult projects and the perseverance<br />

to see them through to a successful<br />

conclusion”.<br />

Mr Marquardt went on to say that Dr<br />

Herrenknecht was receiving the award for<br />

his extraordinary service to the heavy construction<br />

industry, and in particular for his<br />

efforts in the development and innovation of<br />

<strong>Trenchless</strong> Technology and for the establishment<br />

and development of a world-renowned<br />

mechanical engineering enterprise.<br />

Paul Nicholas joins Akkerman Inc.<br />

Paul Nicholas will hold the position of <strong>International</strong> Marketing Manager for Akkerman<br />

Inc, increasing Akkerman sales overseas for all lines of equipment with a focus on microtunnelling<br />

systems.<br />

Mr Nicolas has a 22 year career in<br />

<strong>Trenchless</strong> Technology and international<br />

sales and marketing experience. Prior<br />

to joining Akkerman he held the position<br />

of General Manager of The Robbins<br />

Company SBU division.<br />

Akkerman Vice President of Sales and<br />

Marketing, Rob Tumbleson said “We are<br />

excited about the potential opportunities<br />

in store for Akkerman with Paul coming on<br />

board. Having an international presence<br />

has been a long-time goal for our team.”<br />

He is survived by his wife, Matilda, and<br />

three children and their spouses, Stanley and<br />

Alma Vermeer, Robert and Lois Vermeer,<br />

and Mary and Dale Andringa, eight grandchildren,<br />

and nine great grandchildren.<br />

Performing for Permaform<br />

APM Permaform President Bill Shook<br />

has announced the appointment of<br />

Steve Henning as Manager – Technical<br />

Development of its Eastern Region.<br />

APM is a provider of technology, equipment<br />

and material for trenchless repairing,<br />

rebuilding and replacing of underground<br />

sanitary and storm water structures. Mr<br />

Henning has been in the trenchless rehabilitation<br />

industry for over ten years, is a<br />

past director of NASSCO and has served<br />

on the board of directors of the Gulf Coast<br />

<strong>Trenchless</strong> Association.<br />

Mr Shook said “He brings experience,<br />

knowledge and energy to APM. He is a<br />

proven contributor to our industry and a<br />

tireless crusader for higher standards."<br />

Drain Doctor to treat Portugal<br />

Drain Doctor Plumbing, the UK’s largest<br />

plumbing and drain repair service,<br />

has appointed Francisco José Ferreira<br />

São Vicente as Operations Manager for<br />

Portugal to help build its first business<br />

venture in mainland Europe.<br />

Drain Doctor Director Jan Mitman said<br />

“Once the structure is in place Francisco<br />

will employ a group of technicians to<br />

cover all aspects of Drain Doctor’s service<br />

to deal with plumbing, drainage, relining<br />

and CCTV. He will initially cover the whole<br />

of the Algarve region. When the operation<br />

is as successful as we are sure it is going<br />

to be he will start franchising the system in<br />

the rest of Portugal.”<br />

Mr Vicente said “The plumbing and<br />

drainage systems in Portugal are very<br />

similar to those in the UK, but we do not<br />

have CCTV and no dig drainage technology<br />

in Portugal so this will give us a<br />

great competitive advantage. For example,<br />

drain lining will allow us to complete<br />

repairs without having to dig up our customers’<br />

drains.”<br />

Unexcelled Accuracy<br />

HDD Guidance services for<br />

Intersects and Drilled Crossings<br />

using ParaTrack<br />

Please see our paper #F-1-04<br />

ProData Rig Data Display & Transmission System<br />

1 April, 2009, in the HDD & Challenging Conditions Track.<br />

NAS T T<br />

2009 <strong>International</strong> No-Dig Show<br />

29 March - 3 April 2009<br />

Sheraton Centre, Toronto, Canada<br />

Prime Horizontal Companies<br />

In Holland: +31 (0)251 271 790<br />

In USA: 1-570-675-0901<br />

visit our website: www.primehorizontal.com


news<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

News in Brief<br />

English privates go public<br />

Approximately 200,000 km of privately<br />

owned sewers and lateral drains in<br />

England will be transferred to water and<br />

sewerage companies from 2011.<br />

Currently, if a private sewer or lateral<br />

drain needs repairing, the bill is picked<br />

up by householders, even if the problem<br />

is outside their property boundary.<br />

Most householders don’t even know the<br />

sewer or drain is their responsibility as it<br />

is not apparent when buying a property,<br />

and their insurance policies are unlikely<br />

to cover wear and tear.<br />

Environment Secretary Hilary Benn<br />

said “Millions of householders are unwittingly<br />

sitting on the ticking financial<br />

time bomb of private sewers and lateral<br />

drains. They may not realise it, but if<br />

something goes wrong they have to pick<br />

up the bill. The transfer to water and<br />

sewerage companies will create a fairer<br />

system for all and save many households<br />

the agony of finding thousands of<br />

pounds to pay for repairs.”<br />

It is estimated that well over half<br />

of all houses in England have a private<br />

sewer or lateral drain, the part of<br />

a drain that lies outside the property<br />

boundary. An extensive review of private<br />

sewers began in 2001, prompted<br />

by the concerns of householders and<br />

a consultation in 2003 revealed a high<br />

level of support for transfer. The costs<br />

of transfer will be met by an increase in<br />

the sewerage element of bills across the<br />

nine sewerage companies currently<br />

estimated to be around 7.5 pence to 23<br />

pence a week.<br />

Before the transfer can take place, the<br />

government has to introduce and consult<br />

on regulations and follow Parliamentary<br />

process. The water and sewage companies<br />

will then have to draw up schemes<br />

for the transfer of private sewers in their<br />

regions.<br />

Private sewers stem from an arrangement<br />

that dates from 1936, before that<br />

time the 1875 Public Health Act had<br />

made all sewers public. The 1936 Public<br />

Health Act meant sewers were only public<br />

if they were already in place, laid or<br />

adopted by a sewerage undertaker.<br />

B.C. – new life for old pipes<br />

The City of Victoria in British Columbia,<br />

Canada has begun rehabilitating an integral<br />

part of the city’s water transmission<br />

system, renewing 4,500 metres of highpressure<br />

steel pipes, ranging in diameter<br />

from 20 cm – 1 metre.<br />

The $US4.4 million pipe contract has<br />

been awarded to Insituform Technologies.<br />

The company will complete the work in 26<br />

installations, using a close-fit polyethylene<br />

solution for water pipe renewal. Work began<br />

in late November 2008 and is expected to<br />

be completed in August 2009.<br />

The City of Victoria has a history of promoting<br />

environmentally sound practices. In<br />

addition to Insituform’s minimally disruptive<br />

and environmentally friendly method of<br />

rehabilitating transmission mains, the city<br />

has also retained a professional arborist to<br />

help protect the trees on the job site.<br />

Robbins receives medal for TBM<br />

Development<br />

In April 2009, Richard J. Robbins,<br />

President and CEO of The Robbins<br />

Company from 1958 to 1993, will accept the<br />

Benjamin Franklin Medal for Engineering.<br />

Mr Robbins is being honoured for a lifetime<br />

of innovation underground — developing<br />

TBMs for some of the largest tunnelling<br />

projects in history.<br />

The Franklin Institute Awards have been<br />

ongoing for 185 years, and continue to<br />

recognise the greatest men and women in<br />

science, engineering and technology. Mr<br />

Robbins said “When I reflect on the process<br />

of the award, and the fact that only<br />

one engineer is picked per year, I am truly<br />

honoured and amazed.”<br />

Mr Robbins’ father developed the first<br />

rock tunnel boring machine in 1952 and<br />

founded The Robbins Company, which<br />

is now a worldwide business with representation<br />

in over 25 countries. Richard<br />

Robbins has been responsible for leading<br />

or creating the company’s subsequent<br />

innovations, from large diameter hard rock<br />

disc cutters to the first Double Shield TBM<br />

for Italy’s Orichella Project in 1972.<br />

“One of the most memorable projects<br />

I’ve worked on is the Channel Tunnel.<br />

We designed machines that successfully<br />

bored through water-bearing ground at 10<br />

bar pressure — a much higher pressure<br />

than had ever been done before,” said Mr<br />

Robbins. The 39 km (24 mi) long Channel<br />

Tunnel was completed in 1991, following<br />

the use of five Robbins shielded TBMs<br />

placing precast concrete segments.<br />

Another career highlight was a machine<br />

developed for the RER metro system<br />

in Paris, France in 1965. “We created<br />

the world’s first below water, pressure<br />

bulkhead shielded machine using air<br />

pressure.”<br />

Richard Robbins continues to work in<br />

the tunnelling industry as a member of<br />

the Board of Directors of The Robbins<br />

Company and as a collaborator in development<br />

projects. He sees much work to<br />

be done in the future.<br />

Communicating below the surface<br />

Telecommunications company, Eastern<br />

Communications will install a 240 km fibre<br />

network to service industrial parks and<br />

economic zones in the Philippines, using<br />

HDD to minimise traffic disruptions.<br />

Eastern Communications representative<br />

Edwin Domingo said “Eastern's backhaul<br />

expansion will provide us with three<br />

business opportunities. Primarily, we will<br />

provide connectivity to more than 600 ecozones<br />

and industrial parks along the route<br />

where the backhaul will run. Secondarily,<br />

it will allow the company to maximise the<br />

submarine cables because of the additional<br />

bandwidth, and thirdly, it will allow us<br />

to offer greater bandwidth to other carriers<br />

and telecommunications companies.”<br />

Multinational corporations and BPOs are<br />

relocating to various economic zones and<br />

industrial parks located in Tagaytay, Cavite,<br />

Laguna, and Batangas. The expansion will<br />

also reach Nasugbu, enabling the company<br />

to connect to its submarine cables.<br />

Surprises lead to delays, delays lead to cost<br />

overruns. So work with a team that keeps nasty<br />

surprises away from you, your schedule, and<br />

your budget. At Mears, our in-house planners<br />

and engineers look deeper, to plan farther<br />

ahead. And, our field operators have both<br />

<strong>Trenchless</strong> success in the Middle East<br />

<strong>Trenchless</strong> Middle East 2009, held<br />

in Dubai’s Jumeirah Beach Conference<br />

and Exhibition Centre, has been heralded<br />

as a success by the ISTT and<br />

conference delegates.<br />

<strong>Trenchless</strong> Middle East, the fifth event<br />

in this biennial series, was complemented<br />

by the ISTT Masterclass, which<br />

attracted 40 participants from several<br />

Middle Eastern countries including the<br />

UAE, Saudi Arabia, and Oman, as well<br />

as attendees from Russia, Bulgaria and<br />

the United Kingdom.<br />

ISTT Executive Secretary John<br />

Hemphill said “The Masterclass format<br />

seems ideal for getting the message on<br />

<strong>Trenchless</strong> Technology to regions of the<br />

world where we have no affiliated societies<br />

and to affiliated societies that have a<br />

need for trenchless training but may not<br />

be in a position to host an ISTT No-Dig.”<br />

The conference provided an opportunity<br />

for specialist companies from around<br />

the world to display their equipment<br />

and services for the installation, repair<br />

and refurbishments of utility companies,<br />

engineers, consultants, planners, and<br />

traffic authorities.<br />

GSTT Executive Director, Dr Klaus Beyer; John Hemphill, show-organiser<br />

Caroline Prescott of Westrade, GSTT Chairman Professor Jens Hölterhoff and<br />

Dr Dec Downey at the German Pavillion at <strong>Trenchless</strong> Middle East.<br />

Mears horizontal directional drilling. Because a lot can<br />

happen between Point A and Point B.<br />

the expertise and the equipment to implement<br />

any plan, in any place.<br />

We listen. We plan. We deliver. So the only<br />

thing that happens, is success. Give us a call<br />

at (800) 632-7727.<br />

DESIGN/BUILD • SOIL AND ROCK • SMALL TO LARGE CROSSINGS • SHORE APPROACHES<br />

Mears Group, Inc. • 411 <strong>North</strong> Sam Houston Parkway East, Suite 420 • Houston, TX 77060 USA • www.mears.net<br />

news<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

10<br />

11


<strong>Trenchless</strong> in Toronto<br />

The 2009 <strong>International</strong> No-Dig Conference and Exhibition is set<br />

to be the premier trenchless event of the year. The No-Dig Show,<br />

endorsed by the ISTT and the NASTT, is the largest <strong>Trenchless</strong><br />

Technology event in <strong>North</strong> America.<br />

Look out for the <strong>Trenchless</strong> <strong>International</strong><br />

magazine team at the No-Dig exhibition.<br />

Meet Sales Representative Brett<br />

Thompson, Associate Editor Kate<br />

Pemberton and Editor Chris Bland.<br />

istt news<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

The conference and exhibition will<br />

be held from 29 March to 3 April at the<br />

Sheraton Centre in Toronto, Canada. The<br />

event combines an extensive technical<br />

program, exhibition hall and networking<br />

and social activities for the nearly 2,000<br />

trenchless professionals expected to<br />

attend from around the world.<br />

The event attracts decision-makers from<br />

utilities, engineers, contractors, manufacturers<br />

and suppliers, who are there to do<br />

business in the one forum that is dedicated<br />

to exclusively promoting <strong>Trenchless</strong><br />

Technology.<br />

Program Chair Joe Loiacono said<br />

“Together we will explore the new methods<br />

and techniques available that will help you<br />

save money and improve infrastructure in<br />

your cities, towns and municipalities using<br />

trenchless methods.”<br />

Delegates will have the opportunity to<br />

choose between a five track technical<br />

component, which runs from Monday 30<br />

March to Wednesday 1 April. Over 140<br />

technical papers will be presented by<br />

trenchless experts from <strong>North</strong> America,<br />

Brazil, Denmark, China, France, Germany,<br />

Italy, Japan, the Netherlands, Poland,<br />

South Africa, the United Kingdom, India,<br />

Peru and Taiwan.<br />

The technical papers cover all aspects<br />

of the industry including machinery,<br />

rehabilitation, inspection, asset management,<br />

leak detection, the environment<br />

and sustainability. The conference will<br />

cover all utilities that benefit from trenchless<br />

solutions including electrical, gas,<br />

telecommunications, sewer/wastewater<br />

and water.<br />

The 50,000 square foot exhibit area<br />

will showcase a wide range of<br />

trenchless vendors – from<br />

manufacturers of microtunnelling<br />

and pipe bursting<br />

equipment to suppliers<br />

of coatings and linings<br />

materials.<br />

In addition to the informative presentations<br />

and exhibition hall, Mr Loiacono said<br />

that the Program Committee has worked<br />

diligently to offer an educational yet fun<br />

program with plenty of opportunities for<br />

networking, industry awards and recognition<br />

and entertaining events.<br />

Networking, industry awards and<br />

entertainment<br />

Both the ISTT and NASTT events are<br />

renowned for their strong social programs,<br />

and Toronto 2009 is no different.<br />

Arrive a day early to enjoy the majesty<br />

of Niagara Falls. Alternatively, delegates<br />

can attend an introduction to <strong>Trenchless</strong><br />

Technology short course covering new<br />

construction techniques and rehabilitation<br />

methods. There are also a range of<br />

post-conference seminars to improve your<br />

trenchless knowledge.<br />

The conference will kick off with<br />

the Monday morning breakfast featuring<br />

entertainment and delicious food.<br />

<strong>Special</strong> events will be the presentation of<br />

<strong>Trenchless</strong> Technology Person of the Year<br />

and the comedic stylings of Glen Foster.<br />

The NASTT 8th Annual Educational<br />

Fund Auction will be held in the evening,<br />

promising fundraising in a friendly environment.<br />

The Gala Awards Dinner will be held<br />

Tuesday evening. The dinner provides<br />

an opportunity to socialise with industry<br />

personnel in a relaxed atmosphere. The<br />

winners of the 2008 <strong>Trenchless</strong> Technology<br />

Projects of the Year in rehabilitation and<br />

new installations will be recognised in a<br />

special awards ceremony, as well as the<br />

ISTT Gold Medal. The ISTT Gold Medal<br />

is awarded to individuals for outstanding<br />

and exceptional contributions in the field<br />

of <strong>Trenchless</strong> Technology. The Society will<br />

recognise a truly deserving individual at<br />

the Gala Dinner. This is only the fifth time<br />

in the 23 year history of the Society that<br />

the ISTT has presented the Gold Medal.<br />

And the winner is…<br />

Project of the Year: new<br />

installation<br />

Portland Oregon, East Side<br />

CSO Project (featured in<br />

<strong>Trenchless</strong> <strong>International</strong><br />

October issue)<br />

This project involved the<br />

installation of approximately<br />

3,000 ft (910 metres) of 84-inch<br />

(2 metres) ID concrete pipe in a<br />

single drive under challenging<br />

conditions.<br />

ISTT Innovative<br />

Technology Award for<br />

new installation<br />

DCI DigiTrak F2 Locating<br />

System<br />

The DigiTrak F2 is a novel<br />

three dimensional field-view<br />

directional drilling locating<br />

system with a single button<br />

user interface and graphically<br />

driven menu.<br />

ISTT Innovative<br />

Technology Award for<br />

pipe rehabilitation<br />

Aqualiner is launching a<br />

revolutionary patented<br />

thermoplastic in-situ lining<br />

system for both potable<br />

water and sewer applications.<br />

Aqualiner’s process involves<br />

forming a thin walled, high<br />

strength, standalone liner<br />

in glass fibre reinforced<br />

polypropylene, which is an inert<br />

material, easy to install with a<br />

long shelf life and avoids the<br />

need to use chemical based<br />

resins.<br />

TT Technologies to exhibit at Toronto No-Dig – Booth 705<br />

<strong>Trenchless</strong> equipment manufacturer, TT Technologies, will display the<br />

Grundotugger lateral pipe bursting system and Grundodrill 4X compact<br />

directional drill rig at the No-Dig show.<br />

The trenchless equipment is also marketed in Europe by Tracto-Technik<br />

GmbH, Germany; part of the TT Worldwide Group.<br />

The Grundotugger bursts and replaces sewer laterals of up to 45.7 metres quickly and easily, without costly restoration<br />

or disruption. The lightweight Grundotugger includes everything needed for bursting 10.16 to 15.24 cm laterals, upsize or<br />

size for size including bursting heads, winch cable unit and a power pack, and pipe fusion equipment.<br />

The compact Grundodrill 4X is ideal for the installation of conduit for power and FTTP applications. The Grundodrill<br />

4X offers 4,445 kg of thrust and pullback. Using the compact drill is less intrusive and ideal for areas where larger<br />

units are not an option. The drill features a dual hydrostatic pump system and a four-auger stake down system that<br />

provides greater stability.<br />

Innovators in <strong>Trenchless</strong> since 1962<br />

Most Accurate Piercing Tools · Most Powerful Rams · Hardest Burst · Best Equipment<br />

The RIgHT Technical Support Keeps<br />

The WROng Things From Happening<br />

TRACTO-TECHNIK GmbH & Co. KG · P.O. Box 4020 · D 57356 Lennestadt<br />

Phone: +49 2723 808110 · Email: export@tracto-technik.de · www.tracto-technik.com<br />

45 Years of<br />

Experience<br />

ISTT news<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

12<br />

13


<strong>Trenchless</strong> City: preserving<br />

the environment<br />

Hosted by the FSTT, the seventh Ville Sans Tranchée (VST) 2009 will take place from 16-18 June in<br />

Rosny-sous-Bois in Paris. Following on from the international No-Dig 2009 in Toronto, VST looks set<br />

to be a comprehensive, informative and dynamic event.<br />

The VST event, <strong>Trenchless</strong> City, has<br />

grown steadily over time, and this year will<br />

see approximately 100 exhibitors – compared<br />

with 60 in 2005 and 80 in 2007 – from<br />

France and around the world, including<br />

project owners and managers, businesses,<br />

suppliers, and equipment companies.<br />

VST is the foremost French National<br />

exhibition devoted purely to trenchless<br />

works and technology. The event provides<br />

answers for those seeking information<br />

regarding methods of pipeline installation,<br />

repair and replacement that are less invasive<br />

then open cut methods. <strong>Trenchless</strong><br />

Technology is less disruptive to residents<br />

and business. Furthermore, the projects<br />

are carried out more quickly and more<br />

safely.<br />

One of the unique characteristics of VST<br />

is that it combines booths under a huge<br />

marquee structure, and equipment demonstrations<br />

outside on the Rosny-sous-Bois<br />

stage. Technical managers of local groups<br />

and communities, as well as elected representatives,<br />

will appreciate being able to<br />

see microtunnellers and pipe-bursters in<br />

action.<br />

<strong>Trenchless</strong> trophies<br />

For the third time at the VST, the FSTT<br />

will award the ‘trenchless trophies’,<br />

recognising the top innovative achievements<br />

and initiatives in trenchless works<br />

and projects. Open to businesses, local<br />

bodies, and students/researchers, the<br />

competition will reward the best projects<br />

from these categories, and will also recognise<br />

the trenchless Person of the Year.<br />

This last award honours an individual who<br />

has had a marked impact on the French<br />

trenchless industry.<br />

Founded in 1990, the FSTT is a professional<br />

association, of both a scientific<br />

and technical nature, that primarily seeks<br />

to promote awareness and disseminate<br />

practical knowledge about trenchless<br />

techniques, as well as advancing research<br />

and training in the area.<br />

Promoting a trenchless environment<br />

In gearing up for the VST, the FSTT<br />

recently exhibited at a massive international<br />

environmental expo to raise<br />

awareness of the importance and various<br />

benefits of <strong>Trenchless</strong> Technology. The<br />

FSTT said that the great success of the<br />

recent Pollutec Horizons event, held in<br />

Lyon, was great news and bodes well for<br />

the VST. Pollutec Horizons is an annual<br />

international exhibition of equipment, technology<br />

and environmental services.<br />

Over the four-day exhibition, many people<br />

visited the FSTT booth, allowing the<br />

Society to communicate to people, who<br />

were either completely uninformed or<br />

knew very little about the sector, just how<br />

and why trenchless solutions are beneficial<br />

to the planet. The trenchless industry<br />

was well represented at the event, with a<br />

number of FSTT members in attendance,<br />

such as Sade, Tracto Technic, CMR-MSR,<br />

Hydrovideo, SET, and Serpolet among<br />

others.<br />

Afterwards, organisers said that the<br />

event had received 73,668 visitors, the first<br />

time that attendees had exceeded 70,000.<br />

<strong>International</strong> visitors comprised 11.4 per<br />

cent of the total attendance, with 8,422<br />

professionals of 110 different nationalities.<br />

The next Pollutec Horizons event will be<br />

held in Paris from 1-4 December 2009,<br />

focusing on the environment and sustainable<br />

development.<br />

Population boom good sign for<br />

trenchless<br />

A recent French survey – and perhaps<br />

reflective of other parts of the world –<br />

conducted by the French Institution for<br />

Statistics and Economic Studies showed<br />

that approximately 60 per cent of the population<br />

is centralised around urban hubs;<br />

27.7 per cent living in the city centres, and<br />

32.5 per cent in the surrounding suburbs.<br />

Population inevitably equals a growing<br />

need for more installation, repair/<br />

rehabilitation and maintenance of underground<br />

pipeline networks. This increasing<br />

demand, together with the necessity for<br />

durable developments, requires works<br />

that reduce:<br />

• Pollution<br />

• Noise<br />

• Carbon emissions<br />

• and, environmental disruption.<br />

All of this provides the ideal context<br />

for the increasing use and popularity of<br />

<strong>Trenchless</strong> Technology, which meets all<br />

of the above needs and more.<br />

Translated by Michelle Perl.<br />

IDS_high_res_HPH.pdf 25/2/09 9:48:58 AM<br />

1.4<br />

1.2<br />

1.0<br />

0.8<br />

0.6<br />

0.4<br />

0.2<br />

0.0<br />

0.0<br />

Rural<br />

1999-2006<br />

1982-1999<br />

0.7<br />

0.3<br />

Urban<br />

0.5<br />

1.2<br />

1.3<br />

Suburban<br />

After decreasing, and then remaining constant, the rural population has<br />

been steadily increasing at a rate of 0.7 per cent annually.<br />

1999-2<br />

1982-1<br />

istt news<br />

C<br />

M<br />

istt news<br />

Y<br />

CM<br />

MY<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

CY<br />

CMY<br />

K<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

14<br />

15


Events<br />

ISTT <strong>International</strong> No Dig 2009<br />

Toronto, Canada<br />

29 March – 3 April 2009<br />

www.nodigshow.com<br />

Wasser Berlin 2009<br />

Berlin, Germany<br />

30 March – 3 April 2009<br />

www.wasser-berlin.de<br />

PFTT celebrates<br />

ten years<br />

The Polish Foundation for <strong>Trenchless</strong> Technology (PFTT) has<br />

recently celebrated its ten year anniversary.<br />

Remembering a<br />

trenchless Pioneer<br />

The life and contribution of Dr Satoru Tohyama, a <strong>Trenchless</strong><br />

Technology pioneer in Japan and the ISTT, is remembered by<br />

friend and colleague Ted Flaxman.<br />

istt news<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

UKSTT Awards Dinner<br />

Birmingham, UK<br />

24 April 2009<br />

www.ukstt.org.uk<br />

CityPipe 2009<br />

Moscow, Russia<br />

26 – 29 May 2009<br />

www.citypipe.ru<br />

Ville Sans Tranchée (VST ) /<br />

<strong>Trenchless</strong> City<br />

Paris, France<br />

16 – 18 June 2009<br />

www.fstt.org<br />

SWE Japan<br />

Tokyo, Japan<br />

June 2009<br />

www.jswa.jp/<br />

Modern <strong>Trenchless</strong> Technologies<br />

Ukraine<br />

June 2009<br />

www.no-dig.odessa.ua<br />

Engineering 2009<br />

Tomaszowice, Poland<br />

16 - 18 June 2009<br />

www.i-b.pl/conference/<br />

DT Exhibition 2009<br />

Cheltenham, UK<br />

16 – 17 September 2009<br />

www.dtexhibition.com<br />

<strong>Trenchless</strong> Australasia 2009<br />

Melbourne Park, Melbourne,<br />

Australia<br />

20 - 22 September 2009<br />

www.trenchless2009.com<br />

ICUEE 2009<br />

Louisville, USA<br />

6 – 8 October 2009<br />

www.icuee.com<br />

<strong>International</strong> Pipelines and<br />

<strong>Trenchless</strong> Technology<br />

Conference<br />

Shanghai, China<br />

18 – 21 October 2009<br />

www.icptt.org<br />

over the last decade, the PFTT has<br />

succeeded in achieving its central purpose<br />

of promoting the use of <strong>Trenchless</strong><br />

Technology in Poland. The PFTT is very<br />

active at both a national and international<br />

level. The foundation is one of the<br />

co-organisers of the Polish No-Dig conference;<br />

an international event held every<br />

second year in Kielce. The next conference,<br />

themed <strong>Trenchless</strong> Technologies<br />

in Environmental Engineering No-Dig<br />

Poland 2010, will be held in April 2010.<br />

The founder of the PFTT was Per<br />

Aarsleff Polska Director Arkadiusz<br />

Bachan. The foundation’s first Chairman<br />

was Jerzy Adamski, also a Chairman<br />

of Kielce Waterworks. Following Mr<br />

Adamski, Marek Banasik led the PFTT.<br />

For the last three years its Chairman has<br />

been Andrzej Kuliczkowski (pictured).<br />

The PFTT was awarded the 2008<br />

No-Dig Award in the Academic Category<br />

for organising a twelve month course<br />

in <strong>Trenchless</strong> Technology. This year, in<br />

conjunction with the Kielce University<br />

of Technology, the PFTT will offer an<br />

international post graduate course from<br />

the 2 to the 22 September (See Issue 2<br />

<strong>Trenchless</strong> <strong>International</strong>).<br />

To encourage the study of trenchless<br />

solutions, the foundation grants an<br />

annual award for the best master thesis<br />

involving <strong>Trenchless</strong> Technology. The<br />

PFTT also supports various initiatives<br />

including two polish magazines, trade<br />

fairs and conferences through the generous<br />

support of council and supporting<br />

members.<br />

The ten year anniversary was commemorated<br />

with the presentation of<br />

PFTT Chairman Andrzej Kuliczkowski.<br />

From left Dec Downey, Jerzy Adamski,<br />

Arkadiusz Bachan and Andrzej<br />

Kuliczkowski.<br />

Jubilee Expert statuettes. The statuettes<br />

were awarded to Arkadiusz Bachan<br />

and Jerzy Adamski for their personal<br />

contribution to the foundation and development<br />

of the PFTT. The Jubilee Expert<br />

was also granted to ISTT Chairman Dec<br />

Downey for his outstanding activity in<br />

promoting <strong>Trenchless</strong> Technology at an<br />

international level.<br />

Polish Foundation for <strong>Trenchless</strong> Technology<br />

akulicz@tu.kielce.pl www.pftt.pl<br />

Although it was more than 20 years<br />

ago, I well remember my first meeting<br />

with Dr Tohyama. It took place in London<br />

on 15 April 1985, on a River Thames<br />

boat where we had arranged a dinner for<br />

Chairmen and Authors of papers on the<br />

evening before the opening of No-Dig<br />

85. I was immediately impressed by two<br />

things about him. First, his friendliness<br />

and easy approachability and secondly,<br />

the great respect in which he was<br />

obviously held by the other Japanese<br />

delegates present, who clearly knew<br />

him well.<br />

That was an important meeting for me.<br />

It led to a long and very fruitful friendship<br />

which, sadly, came to an end recently<br />

with Dr Tohyama’s death. The news of<br />

his death must have saddened a great<br />

many people, both in Japan and various<br />

other countries round the world, who<br />

had come to know him during his long<br />

and distinguished career. I am grateful<br />

for this opportunity to put on record my<br />

appreciation of his major contribution to<br />

the trenchless initiative worldwide.<br />

Even before we met, he had shown<br />

his keen interest and strong support for<br />

the first No-Dig event. He had submitted<br />

a paper on Microtunnelling in Japan,<br />

which we felt to be so important that he<br />

was asked to present it during the opening<br />

session of the Conference. Also, he<br />

had brought to England a party of 30<br />

from Japan – the largest overseas delegation<br />

at the Conference. During the<br />

closing session of the Conference, the<br />

formation of an international society was<br />

proposed. The support of the Japanese<br />

delegates and of Dr Tohyama in particular,<br />

was a great encouragement.<br />

We kept in touch and in October 1986<br />

I had an opportunity to visit Tokyo. It<br />

was typical of Dr Tohyama that although<br />

my plane arrived in Tokyo more than<br />

12 hours late – due to a mishap before<br />

leaving Heathrow – he nevertheless met<br />

me at the airport in the evening and conveyed<br />

me to my hotel. The following day<br />

we had very useful discussions about<br />

the newly formed ISTT and about the<br />

next event planned for London, No-Dig<br />

Dr Satoru Tohyama.<br />

87. He also arranged for me to pay visits<br />

to the Iseki Poly factory and, when<br />

I moved on to Singapore, to several<br />

microtunnelling construction sites.<br />

In 1987, Dr Tohyama again led a<br />

major delegation to the No-Dig event in<br />

London, and it was in that year that the<br />

ISTT really began to develop as an international<br />

organisation. Plans were agreed<br />

for holding No-Dig 88 in Washington DC,<br />

in collaboration with the <strong>American</strong> Water<br />

Pollution Control Federation. Dr Tohyama<br />

accepted an invitation to become Vice-<br />

President of the ISTT in recognition of<br />

the key role that he was already playing<br />

in the Society’s development worldwide.<br />

He again led a substantial Japanese<br />

delegation to the Washington DC event<br />

and it was there that the first tentative<br />

discussions took place about the formation<br />

of National Societies that would be<br />

affiliated to the ISTT. The Netherlands<br />

Society was created first and Japan<br />

soon followed with the JSTT, which was<br />

formed with a splendid initial membership<br />

of more than 150 in April 1989, with<br />

Dr Tohyama as its Chairman.<br />

This led to proposals for an<br />

<strong>International</strong> No-Dig event to be held in<br />

Osaka in 1990, organised jointly by the<br />

JSTT and ISTT. The Executive Secretary<br />

of the ISTT Col Jon Sutro and I visited<br />

Japan in February 1990 and were much<br />

impressed by the arrangements proposed<br />

by Dr Tohyama and his team.<br />

When the event took place in October<br />

of that year, it attracted the largest<br />

number of attendees for any No-Dig<br />

to date – just over 1,000 – and also<br />

included the presentation of the largest<br />

number of papers to date.<br />

When it was over we had a special<br />

‘round-up’ meeting of those who had<br />

been involved in organising this highly<br />

successful event, followed by a dinner.<br />

It was not a large gathering and it was<br />

very informal, but I remember it well. At<br />

the conclusion of the meal Dr Tohyama<br />

invited me to say a few words and in my<br />

response I emphasised how pleasing<br />

it was that two teams of people from<br />

very different cultural and historic backgrounds<br />

had collaborated so easily,<br />

that our common interest in promoting<br />

<strong>Trenchless</strong> Technology had enabled us<br />

to work so well together. As we parted,<br />

he shook me repeatedly by the hand<br />

with a warmth that I am sure echoed<br />

his own pride that the first <strong>International</strong><br />

No-Dig in Asia had been such a fine<br />

achievement.<br />

We met repeatedly after that, in many<br />

different parts of the world. He attended<br />

every <strong>International</strong> No-Dig in places as<br />

diverse as Paris, Hamburg, New Orleans,<br />

Copenhagen, Dresden, Taipei, Prague,<br />

Birmingham, Genoa, Perth and Budapest,<br />

always leading a substantial Japanese<br />

delegation and always ensuring that<br />

papers were presented illustrating the<br />

steady progress of the technology in<br />

Japan. We also met on other occasions,<br />

such as Lord Nugent’s lunches in London,<br />

and even — by chance — occasionally in<br />

airport lounges. When an <strong>International</strong><br />

Committee was set up in the early days,<br />

Dr Tohyama was one of the founding<br />

members and when the <strong>International</strong><br />

Board was established a few years later<br />

he became one of the small team, which<br />

during his lifetime grew to a board of<br />

more than 20 directors. His contribution<br />

to the ISTT was so outstanding that it<br />

was recognised first with a Gold Medal in<br />

1995 and then in 1998 when he accepted<br />

an invitation to become the ISTT’s first<br />

and only President.<br />

Drafting this note about Dr Tohyama<br />

has brought back a flood of memories.<br />

His dedication to golf; the friendly presence<br />

of his wife during many of the early<br />

No-Digs; his chairmanship of Working<br />

Group No 3 on microtunnelling, which<br />

produced several excellent reports; and<br />

the quiet way in which he would interject<br />

sound ideas into the Board’s discussions.<br />

He was a wonderful man and a<br />

great civil engineer. It was a pleasure<br />

and a privilege to have known him.<br />

istt news<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

16<br />

17


SPECIAL FEATURE<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Made in China<br />

by Kate Pemberton<br />

The global HDD market is a dynamic and expanding area. A new innovative market emerging from<br />

the east is set to challenge the dominance of the traditional manufacturers.<br />

The prolonged and extensive<br />

period of construction growth in China<br />

has enabled the country’s huge cities to<br />

modernise utilities such as water, wastewater,<br />

and telecommunications. Above<br />

ground construction has been achieved<br />

so rapidly that in many of China’s populous<br />

cities no-dig construction is the only<br />

practical method to install and repair the<br />

necessary supporting infrastructure.<br />

The use of HDD has been a factor in<br />

the development of a growing export<br />

market. Despite the slow down in China’s<br />

growth rates, the trenchless industry continues<br />

to gain momentum domestically.<br />

Chinese companies are finding success<br />

exporting machinery such as HDD rigs to<br />

the rest of the world.<br />

The HDD market<br />

In the past Chinese ‘knock-offs’ have<br />

been dismissed as unreliable, based on<br />

quality concerns. However, international<br />

partnerships, increased technological<br />

capability and lower costs are combining<br />

to create a market for the Chinese<br />

product.<br />

HDD Broker General Manager Bob<br />

Martin spoke to <strong>Trenchless</strong> <strong>International</strong><br />

regarding the international HDD market.<br />

Mr Martin said that historically the<br />

<strong>North</strong> <strong>American</strong> market has been unwilling<br />

to accept Chinese manufactured<br />

equipment. Mr Martin said “Even the<br />

Chinese do not readily accept their own<br />

equipment, acknowledging the quality<br />

shortcomings and instead opt for the<br />

much more expensive US-manufactured<br />

drills.”<br />

However, this situation is changing.<br />

The impact of the global financial crisis<br />

is reverberating around the world.<br />

Project managers are looking for ways to<br />

cut costs while still maintaining the high<br />

standards expected in the industry.<br />

The economic downturn is not the sole<br />

reason for the increase of exports of<br />

Chinese manufactured drills. Mr Martin<br />

said there has been a marked increase<br />

in the quality of the Chinese product.<br />

“Demand for cheaper, simpler machines<br />

is increasing at a very fast pace as<br />

the demand for work remains constant<br />

but the money available to purchase<br />

decreases,” he explained.<br />

Chinese rig manufacturers exhibiting<br />

at the Mosow <strong>International</strong> No-Dig<br />

2008.<br />

East meets west<br />

HDD rigs have been manufactured in<br />

China for over a decade. The Chinese<br />

domestic market has grown as people discover<br />

the benefits of trenchless solutions.<br />

Professional relationships between non-<br />

Chinese and Chinese companies have also<br />

encouraged an improvement in the quality<br />

and production capabilities of Chinese<br />

machinery manufacturers.<br />

Hanlyma, founded in 2003, is one of<br />

China’s leading manufacturers of HDD rigs.<br />

Hanlyma spokesperson Jerry Liang said<br />

that rapid growth and strong branding has<br />

culminated in the company supplying 30<br />

per cent of the domestic market.<br />

The first <strong>American</strong> HDD rig was imported<br />

into China in 1988. Ten years later the first<br />

Chinese rig was created. Mr Liang said<br />

that prior to 2003, 90 per cent of the HDD<br />

market was shared between prominent<br />

international companies including Vermeer,<br />

Ditch Witch and Case.<br />

Mr Liang said that over the last five years<br />

Chinese rigs have come to dominate the<br />

Chinese domestic market, accounting for<br />

almost 95 per cent of market share.<br />

There are currently more than 200 contractors<br />

engaged in trenchless construction<br />

in China, using more than 2,000 HDD rigs,<br />

approximately 700 of which were introduced<br />

in 2007 with the biggest HDD rig in<br />

the world now in China.<br />

As the quality of the rigs available has<br />

improved, Chinese companies have begun<br />

to find success on the global stage. Mr<br />

Liang said that Chinese HDD machines<br />

are well priced to compete in the international<br />

market with high quality technological<br />

capabilities. In 2008, Hanlyma exported<br />

112 rigs, or approximately 44 per cent of<br />

their product.<br />

Another concern levelled at Chinese<br />

HDD manufacturers in the past is a lack<br />

of after sales service. Hanylama is currently<br />

focused on increasing the quality of<br />

after sales service. To facilitate expansion<br />

and service capabilities, the company has<br />

sales and service centres in countries<br />

including Australia, Russia, India, Malaysia<br />

and Turkey. The feedback from international<br />

customers had been positive. Mr<br />

Liang said that customers were satisfied<br />

by the good performance and quality of<br />

the Chinese built machines and the level of<br />

service available.<br />

In addition, Chinese companies are now<br />

endeavouring to increase their international<br />

presence through attending <strong>Trenchless</strong><br />

conferences such as the Moscow No-Dig<br />

Conference 2008 and the <strong>Trenchless</strong><br />

Australasia Conference September 2009.<br />

<strong>International</strong> perspectives and relationships<br />

We asked Mr Martin how he thinks people<br />

perceive the quality of Chinese rigs,<br />

“Not surprisingly, there are two qualities<br />

that seem to pervade the perception of<br />

Chinese equipment, those being ‘cheap’<br />

and ‘low quality’.<br />

“Interestingly, from my own research and<br />

experience with newer Chinese manufactured<br />

rigs, I would only partially agree with<br />

those statements,” he said.<br />

Mr Martin concurred with Mr Liang’s<br />

opinion on the technological advancements<br />

Chinese rig manufacturers have achieved.<br />

“The more successful Chinese companies<br />

have made great advances in quality<br />

control, going so far as to source the major<br />

components for the HDD drills from <strong>North</strong><br />

America.” Mr Martin listed motors, hydraulic<br />

components, pups and gearboxes as<br />

the parts most likely to be sourced from<br />

outside of China.<br />

“The resulting machines are more<br />

expensive than their purebred Chinese<br />

counterparts; however they offer much of<br />

the reliability of <strong>North</strong> <strong>American</strong> machines<br />

while still being significantly cheaper.”<br />

Mr Martin concluded from his research<br />

that these Chinese rigs are, on average,<br />

50 per cent less expensive than<br />

a US-manufactured drill with comparable<br />

pullback capacity. Mr Martin did acknowledge<br />

though, that Chinese drills will be<br />

slower and offer fewer options than the<br />

major manufacturers.<br />

The Chinese machines are still in a<br />

process of building a solid reputation.<br />

Some Chinese companies, recognising the<br />

advantages of expertise and longevity,<br />

have sought to forge partnerships with<br />

established international companies.<br />

<strong>American</strong> companies are taking<br />

advantage of the increasing technical<br />

capability and lower manufacturing costs<br />

of the Chinese HDD manufacturers.<br />

In May 2008, Charles Machine Works<br />

(CMW), manufacturer of underground construction<br />

equipment Ditch Witch, signed<br />

a joint venture agreement with Tu Xing<br />

Sun No-Dig Tech of Beijing, China. CMW<br />

said that Tu Xing Sun is considered to be<br />

a leader in the manufacture and distribution<br />

of HDD systems in China. CMW CEO<br />

Tiffany Sewell-Howard said “This venture<br />

allows us to strengthen our position in<br />

China and other emerging markets.”<br />

The Shanghai Gudeng Construction<br />

Machinery manufacturing company, specialising<br />

in HDD, exports to Russia, Ukraine,<br />

Pakistan, India, Malaysia and Singapore.<br />

Their HDD technology recently received<br />

first place in the construction machinery<br />

branch of the China Quality Association’s<br />

awards. In order to expand the business,<br />

the company is establishing a joint venture<br />

in Malaysia to be called Jiangsu Gudeng<br />

Construction Machinery Assembly Group.<br />

The factory will have a production capacity<br />

of 300 HDD machines and 100 static pulling<br />

machines per annum.<br />

Developing the industry<br />

The development of the industry is also<br />

being assisted by the development of professional<br />

organisations. The China Hong<br />

Kong Society for <strong>Trenchless</strong> Technology<br />

or CHKSTT was established in 1999 and is<br />

one of the societies affiliated with the ISTT.<br />

Other societies in the Greater China region<br />

include those in Shanghai (SSTT), Beijing<br />

(BJSTT), Guangdong (GDSTT), and Taipei<br />

(CTSTT).<br />

Chinese HDD companies are beginning<br />

to produce reliable, cost effective machinery<br />

for both the domestic and international<br />

markets. Companies such as Hanlyma are<br />

focusing on after sales customer service<br />

and forging mutually beneficial international<br />

partnerships.<br />

The export of Chinese manufactured<br />

HDD rigs is set to continue as companies<br />

build their brands through improved quality<br />

for the less complex and less expensive<br />

machines.<br />

SPECIAL FEATURE<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

18<br />

19


projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Reconstructing pipes<br />

in Wajima City<br />

By Masatoshi Kasukawa, Komatsu. Translated by Kyoko Kondo<br />

In Wajima City, Noto Island Japan, an earthquake caused the destruction of more than 16 km of<br />

sewer and agricultural pipes. To restore the pipes, a new trenchless technique was applied – the<br />

IM-Rebirth method can crush and remove existing reinforced concrete pipes and install new pipes<br />

along the same trajectory.<br />

The IM-Rebirth solution successfully<br />

overcame some unexpected<br />

difficulties to reconstruct approximately<br />

1.2 km of sewer pipeline, the first pipeeating<br />

project of this scale to be carried<br />

out in Japan.<br />

The entrance of the Wajima city building.<br />

The flag says “Hang in there!” following the<br />

earthquake.<br />

The sewers to be reconstructed were<br />

located at the end of the downstream,<br />

immediately before the Monzenmachi<br />

wastewater management center. The<br />

pipeline was buried below National Route<br />

249 at a depth of 4.2 metres down to 6.3<br />

metres. The Hakkagawa River runs along<br />

the road and there were many cracks<br />

observed at the river wall. It was predicted<br />

that the whole area was affected from<br />

the ground deformation due to the earthquake.<br />

Many existing manholes had been<br />

dislocated due to the water pressure. The<br />

type of soil was water-bearing stratum,<br />

which seemed to have increased the<br />

warping of the ground. Even from above<br />

ground, it was clear that the sewers had<br />

suffered displacements.<br />

Outline of damaged pipes sagging.<br />

Choosing the right technology<br />

After considering the level of sagging<br />

and displacements, CIPP was deemed<br />

an inappropriate method to restore the<br />

sewers, therefore the choice was made<br />

to reconstruct the whole pipe. There were<br />

two options for reconstruction; open cut<br />

and trenchless. Open cut was rejected<br />

as the pipeline was too deep to excavate.<br />

Moreover, taking into account the ground<br />

water level and economic efficiency, the<br />

trenchless method was selected as the<br />

optimum solution. An alternative was to<br />

install a pipeline next to the damaged<br />

pipe using the standard microtunnelling<br />

method. However, microtunnelling needs<br />

disposal treatment of the existing sewers<br />

including removing manholes up to the 1.5<br />

metre level. Considering all of these factors<br />

the pipe eating method was selected.<br />

The types of existing sewers were;<br />

1. Humes pipe for open cut construction<br />

2. Humes pipe for microtunnelling construction<br />

– including stainless steel<br />

collar<br />

3. A Humes pipe as a casing pipe – PVC<br />

pipe of 200 mm diameter was placed<br />

inside.<br />

Pipe eating method A, from the current<br />

reconstruction method listed in the guideline<br />

issued by Japan Microtunnelling Association,<br />

was chosen to crush and remove the existing<br />

damaged pipeline (pictured).<br />

Reconstruction method<br />

The IM-Rebirth method<br />

The IM-Rebirth method is based on<br />

traditional machines, such as Slim-Ark<br />

TA50 and the Iron Mole series, which can<br />

excavate hard cobbles and rocks. The difference<br />

between these machines and the<br />

IM-Rebirth method is the cutting head with<br />

a special cutter, spiral or gear type, which<br />

can crush the existing reinforced concrete<br />

pipes and reinforcing steels bars. This<br />

method not only crushes the existing pipe<br />

but also removes the pieces. This results<br />

in a newly installed pipe. The cutter head<br />

can also crush railroad ties and stainless<br />

collar used between the pipes.<br />

The jacking head torque is high enough<br />

to crush the hard cobbles and rocks<br />

located around the pipes. The starting<br />

shaft can be very small. For pipe diameters<br />

of 250 mm up to 300 mm only a 2<br />

metre shaft is required, and for pipe diameters<br />

of 350 mm up to 500 mm a 2.5 metre<br />

shaft is required.<br />

A cutting head after the excavation test.<br />

Reconstruction methods from the<br />

Japan Microtunnelling Association<br />

Static crushing and jacking method<br />

Dynamic crushing and jacking method<br />

Rotating/ crushing and jacking method<br />

A type<br />

B type<br />

Pull-out and jacking method<br />

Scope of application<br />

Existing pipe diameter: up to 1000 mm<br />

Diameter of new pipe: 250 – 1,000 mm<br />

Total length: 150 metres – depending on condition<br />

Existing pipe type: hume pipe, (for open-cut , jacking pipe with SUS<br />

collar), clay, PVC, PE, FRP<br />

Ground conditions: standard soil, sand gravel, base rock layer<br />

Applications: same diameter to same diameter, reducing diameter,<br />

enlarging diameter, adjusting trajectory.<br />

Crashed pieces at the test excavation.<br />

The IM-Rebirth method was selected<br />

because of the cutter head's ability to<br />

crush reinforced pipes and SUS (stainless)<br />

collars. However, as the project<br />

progressed, it was revealed that a spacer<br />

of 5 mm thickness was used inside of<br />

the casing pipe for placing VU 200 mm.<br />

To negotiate this problem, an excavation<br />

test was carried out before the<br />

actual construction commenced. The test<br />

showed that although the jacking speed<br />

had slowed down greatly and the cutting<br />

face was abraded a little from the excavation,<br />

the machine can drive forward<br />

despite the presence of the spacer.<br />

Some parts of sewer were completely<br />

out of service and temporary bypassing<br />

was carried out. Several drives were<br />

progressing at the same time; therefore a<br />

well-planned bypassing was necessary.<br />

Bypassing of the current live sewers was<br />

carried out by using the proven technique<br />

for long-distance sewers called Mr. Autobypass.<br />

The Mr. Auto-bypass has working<br />

records of 17.5 km and out of this record,<br />

3 – 5 km were bypassed simultaneously<br />

while constructing several, mainly opencut<br />

drives.<br />

Shaft construction<br />

The existing manholes were damaged<br />

from liquefaction and needed to be<br />

replaced. Therefore, the spaces for replacing<br />

manholes were used as departing and<br />

arrival shafts. In 300 mm diameter pipes, a<br />

shaft diameter of 2 metres was used and<br />

for 350 – 400 mm pipes a shaft diameter<br />

of 2.5 metres was used, which contributed<br />

to reduced construction costs.<br />

Infilling existing pipes<br />

The existing pipes suffered displacement,<br />

sagging as well as some<br />

infiltration of waters and surrounding soils.<br />

It was anticipated that the area around<br />

the machine excavation could be a void<br />

and cave-ins might occur after the construction.<br />

To avoid this problem, infilling of<br />

existing pipes was carried out in order to<br />

prevent cave-ins. The filling material was<br />

a cement-mortar.<br />

Removal of pit-head<br />

The waterproofing equipment and sheet<br />

piles used for the first installation, buried<br />

in place, needed to be removed. The<br />

open-face jacking of 1,000 mm diameter<br />

was used to remove this equipment at the<br />

beginning of the drive and then removed<br />

manually.<br />

The cutter head<br />

The cutting head, equipped with the<br />

special cutter to crush reinforced pipes,<br />

progressed smoothly along the planned<br />

paths. At the peak, seven jacking machines<br />

were driving simultaneously. The crushed<br />

pipes, taken in by the jacking machine,<br />

consisted of materials such as reinforced<br />

steel bars, SUS collars, waterproofing<br />

rubbers and PVC pieces. Railway ties<br />

placed below the pipes were also found<br />

in small pieces. The most difficult section<br />

of excavating the 400 mm casing Humes<br />

pipe and 200 mm VU pipe plus spacers<br />

was carried out successfully, although the<br />

driving speed did not reach the planned<br />

rate. The discharged soil was treated as<br />

industrial waste since it contained steel<br />

pieces, concrete, VU and others.<br />

In total, 21 drives were carried out and<br />

there were no serious problems requiring<br />

the driving be halted. The special cutter<br />

equipped at the cutting face had some<br />

ablation from cutting spacers, but was<br />

able to continue the drive.<br />

The pipe eating [and jacking] method<br />

is normally used to replace aged pipes<br />

with new pipes. However, this construction<br />

was carried out to replace existing<br />

pipes damaged greatly from the earthquake.<br />

Many of the damaged pipes had<br />

suffered displacements and sagging and<br />

some sewers had lost function completely.<br />

Komatsu’s first pipe-replacing technology<br />

was achieved in 1995, the time of Great<br />

Hanshin-Awaji earthquake, proving that<br />

this method could be used for replacing<br />

pipes that have experienced large<br />

displacements. Smooth bypassing had<br />

also contributed a great deal in making<br />

the whole reconstruction successful.<br />

Above: Excavation test.<br />

Left: A spacer.<br />

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

20<br />

21


UV light: curing pipe problems<br />

The advantages of the completely trenchless and fast sewer rehabilitation of the pipe lining with a<br />

light-curing reaction resin system were demonstrated in a project in Ostertorsteinweg street at the<br />

edge of the Bremen old town, Germany.<br />

Upstream – No. 3018 Public sewerage restoration works<br />

Existing pipe: 300 mm Humes pipe (for open-cut), 350 mm pipe<br />

jacking Humes pipe, 400 mm diameter jacking Humes pipe for casing,<br />

200 mm VU inside, 450 mm jacking Humes pipe<br />

New pipe: 300 mm jacking Humes pipe, 350 mm jacking Humes pipe,<br />

400 mm jacking Humes pipe for casing (200 mm VU inside)<br />

Total length: 841.50 metres / 16 drives<br />

Ground conditions: sand gravel, conglomerate layer, clay and silt<br />

(contains ground water)<br />

Damage: breakage, displacement (right to left / up and down),<br />

sagging, etc.<br />

Other conditions: railroad ties were placed at the open-cut installed<br />

Humes pipe/spacers were inserted for casing pipes to install 200 mm<br />

pipes.<br />

The street is a promenade, an intensively<br />

used shopping street and an<br />

important traffic artery. Frequent tramlines<br />

travel through the Ostertorsteinweg from<br />

the early morning into the night.<br />

The mixed water conduit, up to 6 metres<br />

below, is as important as the street itself.<br />

Over 104 years of operation has left its<br />

mark on the brick oval profile 800/1200.<br />

Above all, the advanced level of corrosion<br />

of the brick joints made the sewer<br />

a rehabilitation project, according to the<br />

technical assessment of HanseWasser<br />

(Hamburg Water Works). The goal was a<br />

long-term preservation of the structure.<br />

Tight timing<br />

The concrete project planning was triggered<br />

by a rehabilitation project on the<br />

street surface. As the tram rail track of<br />

the Ostertorsteinweg was up for renewal,<br />

the opportunity was taken to repair the<br />

underground assets. The track renewal<br />

determined the timing of the sewer rehabilitation,<br />

which would take place in three<br />

construction sections, according to the<br />

planning of HanseWasser. While the second<br />

and third construction section between<br />

Poststraße, Mozartstraße and Goetheplatz<br />

would be undertaken when the tram traffic<br />

had already been suspended.<br />

The construction of section one between<br />

Bauernstraße and Poststraße was set for<br />

roughly one month earlier and had to be<br />

coordinated with the running tram (ÖPNV)<br />

operation. This resulted in an extremely<br />

tight time schedule. To avoid impeding the<br />

rail traffic, the maximum time frame was<br />

from Friday 9:00 pm (last tram) to Monday<br />

3:00 am (first tram). In this corridor, two<br />

projects<br />

Much research has been conducted<br />

on this method. The record<br />

length achieved by this method stands at<br />

1.2 km. The Wajima City construction<br />

case has proven the effectiveness of this<br />

method, showing the ability to replace<br />

greatly damaged pipes using trenchless<br />

solutions.<br />

This method can also be an optimum<br />

Above: Liquefaction.<br />

Left top: The pipe-eating machine.<br />

Left bottom: Arrival of the cutting head at<br />

the test.<br />

method for solving combined sewer<br />

problems or a new installation due to<br />

redesigning of the pipe diameter, changing<br />

the inclination, and more. Komatsu<br />

continues to conduct research in order to<br />

solve minor problems found in this construction<br />

case and hopes that this method<br />

will be widely recognised as an optimum<br />

method for replacing reinforced pipe.<br />

Downstream: No.3019 Public<br />

sewerage restoration works<br />

Period<br />

Existing pipe: 400 mm pipe<br />

jacking Humes pipe<br />

New pipe: 400 mm jacking<br />

Humes pipe<br />

Total length: 344 metres/ five<br />

drives<br />

Ground conditions: sand,<br />

gravel; containing ground water<br />

Damage: breakage,<br />

displacement (right to left/up<br />

and down), sagging.<br />

Pipe liner at the start shaft in the Bremen old town.<br />

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

2007 Vermeer D100x120 SII<br />

1,080 hrs, 1500’ of drill rod<br />

$495,000 USD<br />

Let us do the legwork!<br />

- We find the equipment - We find you financing<br />

- We arrange the inspections - We will ship it to your door<br />

2005 Vermeer D20x22<br />

500 hrs, full rack of rod<br />

$49,500 USD<br />

2002 ditch witch JT4020 AT<br />

3,275 hrs, 540’ drill rod<br />

$199,900 USD<br />

Visit www.hddbroker.com<br />

for hundreds more<br />

listings in dozens of<br />

categories<br />

we provide:<br />

- independent assessments<br />

- worldwide exposure for<br />

sellers<br />

- worldwide market for<br />

buyers<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

22<br />

23


Insertion of the liner takes about three hours.<br />

Cured liner in the accessible<br />

oval profile.<br />

shaft the liner was equipped with pressure<br />

locks so that it could then be expanded in<br />

the sewer using compressed air.<br />

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

liners of 32.5 metres and 173.6 metres in<br />

length had to be installed, including all<br />

preparatory and related work.<br />

Light-curing GFRP liner<br />

The related work included the opening<br />

of the connection lines that are covered<br />

up by the liner. This work played a decisive<br />

role in the selection of the process<br />

— due to the time factor. The planners<br />

at HanseWasser decided at the outset<br />

that only light-curing GFRP liner systems<br />

were to be considered. With this pipe lining<br />

variant there is no need to consider<br />

the reduction of stresses in the liner,<br />

which can take several days. The lack of<br />

shrinkage means that there are no axial<br />

movements and the connections can be<br />

milled out directly after the curing of the<br />

liner without the risk of changes in length.<br />

Considering the high density of connections<br />

in Ostertorsteinweg and the fact<br />

that behind almost every connection there<br />

is a multi-storey residential building with<br />

retail space at ground floor level, smooth<br />

maintenance of the drainage was especially<br />

important. In order to maintain the<br />

drainage during the rehabilitation, DN 400<br />

free-flow pipelines were installed above<br />

ground for temporary water drainage,<br />

including sufficiently powerful pumps.<br />

At exactly 9:00 pm, the last train had<br />

just disappeared around the corner and<br />

the preparatory cleaning work began in<br />

the collection drain so that at 11:00 pm<br />

the Brandenburger construction crew<br />

could begin with the insertion of the liner<br />

through the start shaft near Poststraße. The<br />

10.4 tonne glass fibre tube was let down<br />

into the opened shaft out of the transport<br />

packaging and, using an electrical<br />

conveyor belt, pulled with a steel cable<br />

connection to the target shaft at the<br />

Weberstraße. A foil that had been laid<br />

down protected it from damage. At 2:00 am<br />

on Saturday morning, the entire 173 metre<br />

length of liner lay in the Ostertorsteinweg<br />

collection drain. At the start and end of the<br />

Lamp train and curing<br />

A lamp train with nine UV modules,<br />

each 1,000 watt maximum power, was<br />

pulled through the form-fit calibrated liner<br />

with pre-calculated speed. The connection<br />

to the new UV technology with the<br />

special resin recipe made it possible to<br />

also achieve curing in a very short time.<br />

The light-curing process lasted a total of<br />

four and a half hours at a train speed of<br />

65 cm per minute and was recorded in<br />

all relevant parameters, including speed,<br />

exposure dose and liner temperature. The<br />

computer-aided documentation of this<br />

data allowed for any eventual deviations<br />

from target values of the technical parameters<br />

to be recognised immediately and<br />

allowed tracking of the curing procedure.<br />

Connection lines<br />

Directly after the curing of the liner,<br />

work began to open the connections. By<br />

midday Saturday, all 48 residential connections<br />

in the rehabilitated collection<br />

drain were milled open and at the start<br />

of the tram traffic on Monday morning at<br />

9:00 am they were all connected according<br />

to the specifications of the client. This<br />

was accomplished with the installation of<br />

glass fibre short liners up to 50 cm over<br />

the first pipe connection. The direct support<br />

area was filled with an epoxy resin<br />

system so that it was waterproof and<br />

had no cavities. The local residents were<br />

hardly affected by the project in terms<br />

of disruptive effects normally associated<br />

with construction projects.<br />

Further construction sections<br />

The combined second and third construction<br />

sections in Ostertorsteinweg<br />

were performed over ten days. As the<br />

tram traffic was already suspended, there<br />

was not the same degree of time pressure<br />

as in the first section. Two 115 and<br />

128 metre long liners were installed with<br />

all preparatory and related work. There<br />

was a work pause of almost four weeks<br />

after the first construction section due<br />

to a large number of residential connections,<br />

in the area of the collection drain<br />

yet to be rehabilitated, that were renewed<br />

in open cut. This entailed excavation<br />

work but also the renewed preparation<br />

of the surrounding drainage conduit. The<br />

independent laboratory inspection, as<br />

a major component of the quality management<br />

system, was performed in the<br />

Ostertorsteinweg project by engineering<br />

company Siebert in Oststeinbek. Their<br />

analysis of the liner samples taken from<br />

the construction site came to the positive<br />

result that all specified parameter nominal<br />

values of all liners were exceeded by<br />

at least ten per cent.<br />

Summary<br />

HanseWasser was pleased with the<br />

successful and on schedule completion<br />

of the rehabilitation project. The successful<br />

Ostertorsteinweg rehabilitation project<br />

accentuated not only the special advantages<br />

of the liner process that was used,<br />

but is also another example for the plus<br />

factors of the trenchless pipe lining technology<br />

as a whole.<br />

The rehabilitation using pipe lining with light-curing<br />

reaction resin systems<br />

The procedure has already proved itself in 26 countries, in which<br />

over 2,000 km of sewers have been installed in diameters from DN<br />

150 to DN 1000. In principle, the Brandenburger pipe liner procedure<br />

is based on the same basic idea as all other liner. A tube support<br />

saturated with reactive synthetic resin is brought into the sewer,<br />

where it is expanded with inside pressure to be form-fitting, i.e.<br />

with no ring gap, and then cured by a chemical reaction of the resin<br />

to a self-supporting inner lining. This technology is consequently<br />

trenchless, as no type of earthworks are necessary. The flexible<br />

liner tubes are typically applied using existing inspection shafts<br />

in the sewer. The special characteristics that differentiate the<br />

Brandenburger liner system from other pipe lining types are:<br />

• Use of seamlessly wound liners out of glass fibre laminate webs,<br />

• Unique saturation of the raw materials before the production of<br />

the pipe liner with UV-reactive UP resin (possibly with addition<br />

of peroxides for the variation “hybrid curing” for larger wall<br />

thicknesses over 10 millimetres)<br />

• Drawing in the liner on a protective foil and form-fitting expansion<br />

using compressed air<br />

• Curing of the liner using precisely dosed UV exposure<br />

(“BLUETEC® technology”).<br />

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

24<br />

25


SPR technology<br />

SPR utilises steel-reinforced interlocking PVC profile strips sealed<br />

in place by a high-pressure grout. The installation equipment can be<br />

utilised via standard manhole access points without site excavation.<br />

Sekisui’s CPT SPR technology can also be installed in vertical<br />

applications such as wet wells, access shafts and other large diameter<br />

structures.<br />

SPR is a spiral winding technique which is particularly well suited<br />

to the renewal of very large diameter pipelines – up to 5 metres. In<br />

addition to standard circular profiles, egg-shaped and horseshoe<br />

profiles, any custom shapes can also be provided. The winding<br />

machine is specially adapted to each project, enabling it to cover<br />

a very wide range of applications. SPR technology is already being<br />

successfully deployed in Asia and the USA to renew large diameter<br />

pipelines.<br />

The SPR process is unique as it can provide a customised structural<br />

solution to aging pipelines. It can be engineered to correct hydraulic<br />

anomalies as well as restore the slope of the original pipe. The<br />

interlocking edges of the profile create an impermeable mechanical<br />

lock that can withstand strong deformational forces.<br />

SPR liners have been tested in accordance with industry standards<br />

and meet or exceed the standards for spiral wound PVC Profile Wall<br />

Liners ASTM F – 1697-02 and F 1741-02a. Furthermore the SPR PVC<br />

profile has a Manning’s coefficient of n = .010.<br />

PROJECTS<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

All wound up in Poland<br />

Szczecin, Poland is the first city in Europe to benefit from a new Japanese renewal technology, spiral<br />

pipe renewal (SPR).<br />

When the tender for a renewal project<br />

in Szczecin, Poland was first issued at the<br />

beginning of 2008, GRP short-pipe lining<br />

was specified. However, after some extensive<br />

research by the customer it was found<br />

that it would be very difficult to maintain the<br />

required water flow rates using the chosen<br />

technique. Severe deformation of the old<br />

pipe, which was not identified during the<br />

planning stage, meant that if a GRP shortpipe<br />

lining was used, the diameter of the<br />

renewed pipe would be much smaller,<br />

and so reduce the capacity of the new<br />

pipeline.<br />

Another challenge was posed by the fact<br />

that the pipeline being renewed in Szczecin<br />

was a main collector in the city centre,<br />

where it would be impossible to construct a<br />

dewatering system. Even though a large pit<br />

for the GRP lining had already been dug,<br />

at the last minute the customer decided<br />

– based on the new demands faced – to<br />

opt for the first ever European use of SPR<br />

technology.<br />

The masonry-lined combination sewer<br />

was built over a century ago. The condition<br />

of the sewer had deteriorated severely<br />

in recent years. As a result of continuous<br />

traffic and other external loads, longitudinal<br />

cracks had formed along the crown of the<br />

pipe, leading to increased deformation.<br />

Renewal had become a matter of urgency.<br />

There were also a large number of deposits<br />

and other obstacles protruding as much as<br />

50 cm into the pipe. Consequently, it was<br />

clear that thorough cleaning and jet-grouting<br />

work would have to be carried out prior<br />

to the renewal process. The SPR installation<br />

process can be divided into three key<br />

stages: the winding of the PVC profile, the<br />

construction of the bracing system and the<br />

grouting of the annulus<br />

Winding process<br />

The winding was executed starting from<br />

the manhole access shaft downstream to<br />

the next shaft. Based on the local conditions<br />

and the existing 18 metre long pit, the<br />

stretch of pipeline scheduled for renewal<br />

was divided into four segments. The winding<br />

machine installed the profile in the existing<br />

pipeline guided the profile and formed it<br />

into the desired shape, with an inner<br />

diameter of 2,240 x 1,600 mm.<br />

The winding machine<br />

moved one<br />

The SPR winding machine pulls the SPR profile into place and<br />

engages the dual locking mechanism.<br />

profile width forward on each rotation of the<br />

profile, locking the profile edges to form a<br />

water-tight pipe in the process.<br />

As soon as the machine’s forward<br />

momentum had taken it to the next shaft,<br />

the winding process was stopped and<br />

the profile separated. The team from the<br />

Polish construction company, together with<br />

the Japanese engineers, laid the<br />

winding machine and<br />

the profile reel to the<br />

next shaft, which<br />

then served as the<br />

new starting<br />

Bracing the shaft.<br />

point for the next installation phase and as<br />

the conduit through which the profile was<br />

again guided by the winding machine, as<br />

in the first phase.<br />

Bracing system<br />

In the next step, when the winding process<br />

was complete, the expert team constructed<br />

the bracing system. The braces were introduced<br />

through the shaft into the spiral<br />

wound pipe and carefully installed. The<br />

constructed cross-section of the bracing<br />

system prevents lifting of the new spiral<br />

wound pipe during subsequent grouting<br />

and prevents deformation.<br />

Grouting<br />

The grouting process for each renewal<br />

segment comprised injection of the grout<br />

into the annulus between the old pipe and<br />

the spiral wound PVC profile and curing of<br />

the grout. The team executed the grouting<br />

work in three stages. Then the braces<br />

were dismantled and installed in the next<br />

renewal segment. The pit area was grouted<br />

to a statically determined height above the<br />

spiral wound PVC profile.<br />

SPR technology in Poland.<br />

Below: SPR PVC profile is unreeled and fed<br />

into the winding machine.<br />

For further information contact Christopher Moritz at KMG LinerTec GmbH:<br />

christopher.moritz@sekisuicpt.com<br />

Summary<br />

All work was carried out by the team<br />

comprising workers from the local Polish<br />

agent of Sekisui CPT and Japanese technical<br />

specialists. The renewed sewer<br />

is beneath one of the main streets in<br />

Szczecin, and collects the rainwater and<br />

sewage from all the smaller surrounding<br />

systems. Work was interrupted several<br />

times due to flooding and above average<br />

rainfall, and lost time had to be made up<br />

for at night. However, since SPR can also<br />

be applied with drainage, the installation<br />

could be resumed without problem following<br />

the enforced breaks.<br />

Headed by Christopher Moritz, an<br />

expert team provides technical know-how<br />

and support covering all aspects of the<br />

new technology. “One of the key benefits<br />

of the SPR PVC profile from Sekisui is its<br />

environmental sustainability – including 60<br />

per cent less fossil fuel consumption, 30<br />

per cent less energy use and four times<br />

lower CO2 emissions in production.<br />

“That is one of the factors that will<br />

enable us to achieve our goal of delivering<br />

premium renewal solutions and becoming<br />

the market leader in the renewal of<br />

large-diameter pipelines in Europe,” said<br />

Mr Moritz.<br />

Despite the very difficult weather conditions,<br />

the European premiere of SPR<br />

technology was successfully completed<br />

within approximately two months.<br />

PROJECTS<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

26<br />

27


Alleviating flooding<br />

in Ashbourne<br />

Severn Trent has embarked on an extensive program to upgrade the wastewater system – using<br />

trenchless solutions such as pipe jacking and CIPP – to alleviate flooding in Derbyshire, England.<br />

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Ashbourne is a picturesque market<br />

town in the Derbyshire Dales with a population<br />

of just over 7,000. The Ashbourne<br />

Flood Alleviation Scheme has been<br />

designed to reduce 16 flooding problems<br />

within the central area of Ashbourne,<br />

Derbyshire. Hydraulic analysis of the<br />

sewer network revealed that the primary<br />

cause of the sewer flooding within the<br />

centre of Ashbourne, affecting 14 out of<br />

the 16 flooding locations, was the lack of<br />

spill capacity from the existing combined<br />

sewer overflow (CSO), situated near the<br />

town centre, and the hydraulic capacity of<br />

sewers passing flow to it.<br />

To increase the hydraulic capacity in<br />

the sewer system, the existing CSO was<br />

relocated to a position downstream of its<br />

current location to an area of public open<br />

space and a short length of upstream<br />

sewer was upsized to enable unrestricted<br />

flows to reach the new CSO location. A<br />

new outfall sewer was constructed from<br />

this CSO to enable flows to be discharged<br />

much further downstream than the existing<br />

CSO outfall position, where additional<br />

hydraulic outfall capacity in the Henmore<br />

Brook had been gained.<br />

The scheme solution involved the upsizing<br />

of several lengths of both the surface'<br />

and combined sewer system together with<br />

the rationalisation of three existing CSOs<br />

into one new overflow, and the provision of<br />

a new surface water outfall structure.<br />

The construction of the 675 metre,<br />

900 mm diameter outfall sewer formed a<br />

major element of the project solution in<br />

that it provided an unrestricted surface<br />

water outlet from the Town Centre. This<br />

sewer incorporated the 32 metre long nodig<br />

crossing of the Station Road – King<br />

Edward Street junction.<br />

Also included as part of the project<br />

were sewer rehabilitation works on the<br />

combined sewer upstream of the existing<br />

CSO location and the surface water sewer<br />

in Dig Street, Ashbourne.<br />

Pipe jacking prevents disruption<br />

The pipe jack was constructed beneath<br />

the Station Street – King Edward Street<br />

traffic siganalised junction. This road junction<br />

is the primary access points to one of<br />

Ashbourne’s two main car parks, which is<br />

Top: Completed pipe jack line.<br />

Bottom: Pipe jack thrust manhole.<br />

also the car park to the town’s Sainsbury’s<br />

Supermarket store. The Project designers<br />

felt that although the new sewer could<br />

be constructed across this road junction<br />

using an open cut construction method,<br />

doing so would cause considerable disruption<br />

to Ashbourne’s traffic system and<br />

its car parking, as well as unacceptable<br />

disruption to the supermarket.<br />

The main project contractor was<br />

Whitehouse Construction. Kiamm Ltd was<br />

the specialist subcontractor for the pipe<br />

jacking work. The pipe jack constructed in<br />

Ashbourne was a 1,200 mm hand driven<br />

open face pipe jack.<br />

The pipe jack was constructed across<br />

the road junction between thrust and<br />

reception pits situated on either side of the<br />

junction over a distance of 32 metres. The<br />

depth to the sewer at the thrust and reception<br />

pits was just over 4 metres, with a<br />

cover to the pipejack of approximately 2.8<br />

metres over its whole length. The ground<br />

conditions primarily comprised slightly<br />

sandy, gravelly clay. There were no problems<br />

experienced during construction and<br />

the pipe jack was driven successfully over<br />

a period of six hour working shifts.<br />

No-Dig on Dig Street<br />

The lining process used in Ashbourne<br />

was OnSite’s Premier-Pipe lining system.<br />

Premier-Pipe is a CIPP renovation process,<br />

which is installed without the need for<br />

costly and disruptive excavation. Premier-<br />

Pipe liners are individually manufactured<br />

to suit the dimensions of the pipes to be<br />

lined; the lining thickness being determined<br />

by individual design requirements.<br />

The lining tube is made of polyester felt<br />

with an outer coating of polyurethane,<br />

which is impregnated thoroughly with a<br />

liquid resin chosen to suit the working<br />

environment of the pipe.<br />

Two main sewer runs were relined as<br />

part of the Ashbourne Flood Alleviation<br />

Project. The first sewer being a 640 mm<br />

x 430 mm brick egg combined sewer<br />

of a total length of 135 metres and the<br />

second sewer being a 600 mm x 660 mm<br />

rectangular brick surface water sewer of<br />

125 metes in length. Both sewer lengths<br />

were situated on Dig Street in Ashbourne,<br />

which is one of the towns main commercial<br />

streets. Once impregnated with resin,<br />

the Premier-Pipe was installed using the<br />

scaffold tower inversion method from<br />

existing manholes situated on Dig Street.<br />

The relining was carried out on both<br />

of the sewer lengths to resolve structural<br />

problems discovered during investigation<br />

of the town's flooding problems and<br />

also to improve the hydraulic perforation<br />

of the sewer lengths. Due to the location<br />

of the proposed work, the relining<br />

was carried out under a ten day road<br />

closure. This time period was, however,<br />

vastly reduced than the time period that<br />

would have been required for conventional<br />

open cut replacement.<br />

Severn Trent supplies water and sewerage<br />

services to more than 3.7 million<br />

households and business customers in<br />

a region stretching from Mid Wales to<br />

Rutland and from Bristol Channel to the<br />

Humber. The water authority is responsible<br />

for 54,000 km of sewers and 1,000<br />

sewage treatment works.<br />

Mayfield Rd<br />

Station St<br />

Church St<br />

Station Rd<br />

Buxton rd<br />

Union St<br />

King St<br />

St John’s St<br />

Park rd<br />

Ashbourne<br />

Approximately 10 metres through pipe jack 2.<br />

Derby Rd<br />

Brandenburger<br />

cured-in-place-lining<br />

Belper Rd<br />

BLUETEC ® UV equipment<br />

- Quickest resin curing by using several performance<br />

levels 400/600/1000 W at various diameters<br />

- Newly developed UV lamps with high output<br />

- Permanent quality control and documentation<br />

using the control software Reline Control 3.0<br />

- Several types of UV equipment for different conditions<br />

and requirements at the construction site<br />

Arrival at reception pit.<br />

The High Tech procedure with UVA light-curing process for quick, environmentally sound and durable rehabilitation<br />

of sewer pipes circle profiles DN 150 - 1000 and egg-shaped profiles 200/300 - 800/1200. More than 2.0<br />

million metres of installed liners in 26 countries since 1993.<br />

A system with many years of installation experience, all aspects of the system developed from one company:<br />

Liner production, equipment, technology, service & support.<br />

GFRP pipe liner<br />

- Seamlessly wound with high and durable strength<br />

- Uniform resin distribution by unique impregnation<br />

- Factory-prepared, employing Advantex ® E-CR<br />

glass fibre and special resins<br />

- Quality management acc.<br />

DIN EN ISO 9001:2000<br />

Brandenburger<br />

Brandenburger Liner GmbH & Co. KG<br />

Taubensuhlstraße 6<br />

D - 76829 Landau/Pfalz<br />

Tel. +49 63 41 / 51 04 -0<br />

Fax +49 63 41 / 51 04 -155<br />

e-mail:info@brandenburger.de<br />

www.brandenburger.de<br />

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

28<br />

29


projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Rehabilitation of a return<br />

line for cooling water<br />

An innovative low pressure pipeline repair technique has been tested at a power plant in Berlin.<br />

Michael Roeling describes the procedure and successful outcome of the test.<br />

With a capacity of 600 MW, Reuter<br />

West is the most powerful heat and power<br />

plant in Berlin, Germany. It consists of<br />

two equal units, each with an output of<br />

300 MW (block D and E), which were put<br />

into operation in 1987 and 1989 respectively<br />

and located next to the existing old<br />

power plant, Reuter.<br />

During recent routine maintenance<br />

checks it was noticed that two of the four<br />

return pipes connecting the side coolers<br />

with the main cooling return line between<br />

the cooling tower and unit E were showing<br />

leakages caused by pitting corrosion. The<br />

leaking pipes are made of welded steel,<br />

with a nominal diameter of 600 mm and are<br />

operated with a maximum pressure of 29<br />

psi. The pipeline had been partly assembled<br />

by welding half pipes together on site,<br />

causing tolerances in diameter, an unusual<br />

trait for steel pipelines.<br />

The return lines, together with many other<br />

lines, are installed in a service duct below a<br />

pavement designed for heavy-duty trucks.<br />

The replacement of larger pipe sections<br />

would have required the opening of the<br />

pavement, digging a trench and removing<br />

the reinforced concrete floor. This method<br />

was rejected from the beginning; primarily<br />

due to the obstruction it would cause to<br />

internal plant traffic, but also for cost reasons.<br />

The replacement of small sections<br />

inside the closed service duct by hand was<br />

also discussed as a possible alternative.<br />

However, the cost would have been quite<br />

high. In either case, the replacement could<br />

never have been executed within the time<br />

frame.<br />

BKP Berolina Polyester GmbH & Co<br />

offered to install the new Berolina-LP-Liner,<br />

the first field test of the product. This<br />

renovation solution promised cost advantages<br />

for the power plant’s owner Vattenfall<br />

Europe. Plant management decided to<br />

renovate a test section using the liner and<br />

await a result before making a final decision<br />

about the method of renovation or<br />

replacement.<br />

Preparation<br />

As the condition of the leaking pipes —<br />

except the pitting holes — was generally<br />

still good, the final decision on method was<br />

postponed for several months. The leakages<br />

were closed by welding steel plates<br />

over the holes. A 40 metre test section was<br />

left for the liner renovation test. This section<br />

was limited by a 90 degree bend with a<br />

wall duct that followed on one side. On the<br />

other side of the section, and an additional<br />

90 degree bend led into an extension section.<br />

The distance between the upper pipe,<br />

which had to be renovated, and the ceiling<br />

measured only 3 to 5 cm. First the bends<br />

were removed because the liner installation,<br />

and subsequent curing by using<br />

UV-light, required reasonably straight sections.<br />

Afterwards the section was scheduled<br />

to be cleaned by high pressure jetting.<br />

Unfortunately this was not sufficient as the<br />

pipe was encrusted with a hardened buildup<br />

that could have damaged the liner.<br />

An intensive cleaning and levelling of the<br />

pipe’s inner surface was carried out using<br />

a special scraper known as a ‘go-devil’<br />

(pictured).<br />

The insertion of the light train.<br />

Installation of the liner<br />

The liners were fibre reinforced plastics<br />

(FRP), using several layers of glass-fibre<br />

mesh reinforcement together with polyester<br />

resin which is cured by using UVA-light.<br />

So far the Berolina-Liners have been used<br />

for renovation of storm water or sewer<br />

pipes. The water tightness test in those<br />

cases followed the procedures of EN 1610<br />

with a maximum test pressure of 7.25 psi<br />

when using water and 1.45-2.90 psi when<br />

using air as a pressure medium. Based on<br />

the existing liner products the company<br />

ventured into a new product line to enable<br />

the renovation of pressure pipes.<br />

In this project, the liner for low pressure<br />

pipes was chosen to complete the test.<br />

Following the pipe cleaning, a polyethylene<br />

gliding foil was pulled in the pipe to<br />

protect the liner from damage by welding<br />

burrs or any remaining hardened build-up<br />

when being pulled in.<br />

Then the liner was pulled into the pipe<br />

with a hydraulic winch and closed with<br />

end caps.<br />

The liner was then inflated by air pressure<br />

in order to insert the UVA-light source.<br />

The light source consisted of a light train<br />

with eight metal halide lamps. The light<br />

spectrum was synchronised to the photo<br />

catalysts in the polyester resin. A curing<br />

unit, type Compact and made by HC<br />

PipeTech, was used for curing the liner.<br />

Due to the very small external dimensions<br />

of this equipment, the installation crew<br />

was able to bring the unit into the service<br />

duct by hand and through a door only 90<br />

cm wide.<br />

After the insertion of the light train, the<br />

liner was expanded close fit to the inner<br />

wall of the host pipe. The special design<br />

of the liner allows it to dialate over a<br />

relatively wide range of diameters – from<br />

5 per cent under measurement up to 5<br />

per cent over measurement compared<br />

with the specified size of the host pipe.<br />

Therefore, the large tolerances in diameter<br />

of the host pipe were not an issue for<br />

the liner.<br />

After dilatation, the light source was<br />

ignited and pulled through the liner at a<br />

defined speed. The UVA-light enabled the<br />

polymerisation of the polyester resin.<br />

After the curing had been completed<br />

the liner ends were cut with precision and<br />

the installed liner could be examined. The<br />

smoothness of the inner liner surface was<br />

striking. In a public sewer system the job<br />

would have been completed by this stage.<br />

In this case, the connection to the existing<br />

pipeline had to be made. Flange collars,<br />

also made of FRP, were bonded to the<br />

protruding liner ends and the continuing<br />

pipeline components with flange joints<br />

attached. This design was necessary for<br />

two reasons. Firstly, the design allowed for<br />

the opening of the test section for future<br />

inspections without destroying any part of<br />

the pipeline. Secondly, a joint by laminating<br />

was not possible because of the very<br />

narrow distance between the pipeline<br />

and the reinforced concrete ceiling. Even<br />

for the flange type of connection used in<br />

this project, the concrete cover had to<br />

be removed at some locations to allow<br />

enough working space.<br />

Summary<br />

The project described above has been<br />

accomplished in an extremely short time<br />

frame, especially considering the very<br />

tight working space. The renovation of the<br />

straight section, including cleaning with<br />

the ‘go-devil’, pulling in of gliding foil and<br />

liner, curing and exact cutting was done<br />

in a single day. The replacement of the<br />

pipe section with half pipes would have<br />

taken three to four weeks. The time taken<br />

for connecting the liner with the rest of<br />

the pipeline, as well as for the preparing<br />

works for removing the old steel bends,<br />

was within the normal time frame for this<br />

kind work. The pipe section renovated by<br />

ID 150 mm (~ 6‘‘) up to<br />

ID 1000 mm (~ 40‘‘)<br />

Glass fibre and/or polyester<br />

webs impregnated with resin<br />

Brief installation time<br />

Bridging of profile<br />

differences and cross<br />

sections<br />

Chemical resistant<br />

Suitable for all profiles<br />

Seamless construction<br />

Smooth surface<br />

Ready for installation<br />

Berolina-Liner System<br />

®<br />

Lightspeed sewer rehabilitation in 5 continents<br />

CIPP with UV-light<br />

The renovated pipe section.<br />

using the Berolina-LP Liner has been in<br />

full and unrestricted operation for over six<br />

months at the time of writing. From testing<br />

so far the Berolina-LP-Liner can be<br />

rated as reliable for this kind of pipeline<br />

renovation in power plants and other low<br />

pressure pipes.<br />

BKP Berolina Polyester GmbH & Co. KG, Berlin, Germany. For more information visit www.bkp-berolina.de or<br />

contact +49-30-36471-400 email info@bkp-berolina.de<br />

BKP Berolina Polyester GmbH & Co. KG<br />

Am Zeppelinpark 22<br />

13591 Berlin, Germany<br />

®<br />

UV-light source<br />

Tel.: +49 (0) 30 / 36471-400<br />

Fax: +49 (0) 30 / 36471-410<br />

info@bkp-berolina.de<br />

UVA-light in action.<br />

Insertion of the Berolina-LP-Liner.<br />

Less space required<br />

projects<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

30<br />

31


obotics<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

The role of robotics in the<br />

trenchless industry<br />

by Paul Heenan<br />

The official definition of a robot is “a machine or device that operates automatically or by remote<br />

control,” yet this does not really define the information and functions that the robots in the<br />

<strong>Trenchless</strong> Technology industry provide to engineers from local water authorities, municipalities and<br />

other utility owners.<br />

It can be argued that the first step<br />

towards what we know today as ‘robots’<br />

was the use of tube cameras to inspect<br />

mainline sewers – CCTV inspection. This<br />

system of cleaning and winching the camera<br />

through the sewer was very labour<br />

intensive and, due to these manpower<br />

requirements, quite expensive. Despite<br />

this, the information gathered was invaluable<br />

in the asset management project.<br />

The problem with the winch system was<br />

that it required an entry and exit manhole;<br />

to operate this system two access points<br />

were required. For example, laterals that<br />

connect from the property directly into<br />

the main sewer lack the appropriate<br />

access. The advent of the cable and<br />

drain rods pushing system facilitated<br />

these inspections. This was further developed<br />

by Pearpoint Limited of the UK<br />

(now part of SPX) when the conductors<br />

that transferred the camera image to the<br />

control screen were incorporated inside<br />

a semi rigid rod, removing the need for<br />

a separate cable and rod. Finally the<br />

advance in technology of CCDs that<br />

produce the image surpassed the use of<br />

tube cameras and monochrome pictures<br />

were replaced by colour.<br />

The first camera-mounted robots –<br />

crawlers/tractors – provided completely<br />

new scope of possibilities. These robots<br />

enabled increased inspection distances,<br />

single entry point inspection and eventually<br />

‘pan and tilt’, which allowed the<br />

inspection of laterals from the main sewer<br />

to the building. It was a major step for<br />

the industry. Whether they were ‘shaft<br />

driven’ or ‘chain driven’, the only limitation<br />

became the loss of picture quality over<br />

greater distances.<br />

The risk of explosion created in sewers<br />

or confined spaces produced the next<br />

generation of robots. The advance in this<br />

particular industry gave rise to explosion<br />

proof systems, either by means of ‘flame<br />

paths’ or ‘inert gas-filled,’ the robots can<br />

now travel and inspect pipes that, 20<br />

years ago, were uncharted territory.<br />

All of this advancement had to be coordinated<br />

and the results assessed using<br />

a single system of examination.<br />

In 1974, the Water Research Centre in<br />

Swindon, UK provided such a method of<br />

evaluation. The system of fault classification<br />

and fault severity is used worldwide<br />

in both normal sewer (OX20) and brick<br />

sewer (OX21). The classification of grading,<br />

1 (good) to 5 (collapsed or near<br />

collapse), allows local water authority<br />

engineers, municipalities or other utility<br />

owners to set priorities in the next step<br />

of sewer robotics – sewer rehabilitation.<br />

So were CCTV inspection cameras the<br />

original robots According to the definition,<br />

cameras with remote functions such<br />

as focus, iris and rotate functions, and<br />

crawler/tractors obviously qualify. They<br />

were and still are an extension of the<br />

human eye.<br />

Robots in sewer rehabilitation<br />

If CCTV inspection is an extension of the<br />

human eye, repair robots are an extension<br />

of the human hand. These types of<br />

robots are performing tasks remotely<br />

and the benefits they provide, either<br />

financially or solution wise, are incalculable.<br />

The introduction of <strong>Trenchless</strong><br />

Technology gave local engineers a more<br />

cost effective and cost efficient method<br />

to maintain the sewer systems within their<br />

control. Especially pertinent in today’s<br />

financial situation, using trenchless solutions<br />

makes the sewer infrastructure<br />

rehabilitation budget stretch that little bit<br />

further. The old idea of ‘dig it and fill it’ is<br />

expensive and intrusive; in comparison<br />

non-disruptive, remote repair by robot is<br />

unobtrusive and inexpensive.<br />

There are two main classes of rehabilitation<br />

robot, those that grind or cut<br />

and those that repair leaking joints or<br />

laterals.<br />

Grinding or cutting robots are the<br />

teeth of the sewer rehabilitation industry,<br />

removing intruding laterals or re-opening<br />

the laterals of relined pipes can be done<br />

with ease. The fundamental question that<br />

arises is how the grinding/cutting can be<br />

achieved quickly and cost effectively.<br />

There are two main methods:<br />

1. Air driven systems: air driven motors<br />

that are used in the grinding produce<br />

a good result in some materials, but<br />

not in all. The torque produced at<br />

the point of grinding/cutting can be<br />

considerably less than the alternative,<br />

hydraulic driven. The other problem,<br />

as most people are aware, is reliability<br />

and maintenance. The amount<br />

of debris and vibrations created during<br />

the process can cause slow and<br />

expensive repairs.<br />

2. Hydraulic driven systems: the use of<br />

hydraulic methods has shown that the<br />

vibrations and debris have no effect on<br />

the reliability of the system. The torque<br />

produced at the point of grinding/cutting<br />

easily and quickly deals with any<br />

material. This makes the system more<br />

cost effective and efficient. Although<br />

the amount of investment required in<br />

owning such a system can be higher<br />

than air driven systems, the difference<br />

is soon recovered with the increase of<br />

productivity.<br />

KATE-PMO AG of Freienbach,<br />

Switzerland, a leading manufacturer of<br />

hydraulic driven grinding/cutting robots<br />

for over 20 years, pioneered the use of<br />

this type of robot system and still has<br />

originally manufactured systems working<br />

in Germany today.<br />

Lateral repairs<br />

In 2004, an independent German<br />

organisation IKT (Institut für Unteridische<br />

Infrastruktur), together with 26 sewage<br />

network operators from different cities,<br />

assessed the different methods available<br />

for the repair of sewer pipe lateral connections.<br />

In order to assess the products<br />

capability of sealing internally and externally,<br />

the repairs ranged from standard<br />

damage to strong damage. A system of<br />

measurement was introduced:<br />

• Very good – 1.0 to 1.5<br />

• Deficient – 5.6 to 6.<br />

Seven robotic systems were tested and<br />

comparatively evaluated. In these tests it<br />

was shown that the system of repair from<br />

KATE-PMO AG was the highest rated<br />

product. Using the lateral shield, more<br />

than one repair can be carried out in the<br />

sewer length at any one time. The shield<br />

can be adjusted to suit the angle of entry<br />

into the sewer making a perfect mould for<br />

the resin to bond to the pipe material.<br />

Alternative robots in the sewer<br />

The use of sewers to deploy cables<br />

is not a new idea; it was first pioneered<br />

by the French in Paris at the turn of the<br />

1900s. Robots have been developed by<br />

companies, including KATE-PMO AG, to<br />

deploy fibre optic cables in sewers with<br />

diameters from 200 mm up to and including<br />

700 mm. What is special about this<br />

system is the software that creates a<br />

map of the sewer line. Each joint, lateral<br />

or defect is measured and recorded.<br />

The position of the tubes is set by the<br />

clamps installed in the sewer length in<br />

order to avoid interfering with laterals<br />

and the primary use of transportation of<br />

waste material. More than 400,000 metres<br />

have been installed to date with minimum<br />

excavation, making it an environmentally<br />

friendly solution for telecommunication<br />

companies, disaster recovery situations<br />

and local authorities.<br />

The Future<br />

The future for robotics in sewers is<br />

vast, and the ever increasing market in<br />

<strong>Trenchless</strong> Technology will no doubt<br />

provide new advances in the design,<br />

manufacture and materials. Reliability<br />

and quality must be maintained in order<br />

to consolidate the trenchless industry in<br />

today’s market place.<br />

Paul Heenan is the <strong>International</strong><br />

Sales and Marketing Manager<br />

for KA-TE.<br />

Robotics<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

32<br />

33


Locating laterals in Toronto<br />

Benko Sewer Services of Ontario uses four IBAK Lateral Launch Systems (LISY) in order to maintain<br />

essential services in the city of Toronto, Canada.<br />

A guide to manual<br />

coating application<br />

products anD services<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Benko, a division of Badger Daylighting, is a multi-disciplinary<br />

company that specialises in CCTV inspections, maintenance and<br />

flushing\cleaning of sewers, catch basin cleaning, smoke and<br />

air testing, and hydro-excavating. For the past 15 years, Benko<br />

has serviced and supported customers from all regions of<br />

Ontario. Benko uses only industry leading products from the most<br />

respected manufacturers in the world today, offering diverse<br />

applications to meet the needs of both private and municipal<br />

clients.<br />

The IBAK - LISY lateral launch system was introduced in 1993.<br />

The first of its kind, the LISY has evolved throughout the years<br />

and still provides users with unparalleled control, capability and<br />

picture quality.<br />

Over the past year, the company has increased its existing<br />

fleet of CCTV trucks by acquiring four IBAK lateral launch units<br />

to complement and maintain essential wastewater services. The<br />

trucks have been used to carry out lateral launch contracts in<br />

both the municipal and private sectors and have to date pushed<br />

over three thousand lateral launches as well as increasing the<br />

capacity for regular mainline contracts.<br />

Benko has had great success with these units in respect to<br />

productivity, reliability and quality of the end product. The picture<br />

quality is constantly noticed by clients and maintains a consistently<br />

high quality in any pipe size. The operating platform for the<br />

CCTV operators is quite different from the rest of the fleet, but<br />

training has been of minimal effort due to the user-friendly nature<br />

of the control system.<br />

The company focuses on quality equipment, such as the<br />

Badger Hydrovac units, and sees this as being the key to achieving<br />

success in the industry. The company believes that IBAK has<br />

been the equivalent on the CCTV side of the business and has<br />

given the ability to mix high quality equipment with high quality<br />

operators to achieve a superior service.<br />

Benko has been employed on a contract within the city of<br />

Toronto, which requires locating the depth and line of the sewer<br />

connections up to the building line. The advantage of this method<br />

is that there is no intrusion to residential property (in order to<br />

remove toilets) to achieve the same location results. The main<br />

contract being carried out at present is lateral locating using the<br />

IBAK - LISY. The trucks are pushing lateral launches every day.<br />

A Benko spokesperson said “we have faced many different<br />

scenarios with the condition, line, material of the pipe, but the<br />

IBAK Lisy has been consistent in giving us the results we are<br />

looking for. One area in particular would be where there is a<br />

‘Y’connection within the sewer lateral.<br />

“We are able to push both ways through the ‘Y’ by using the<br />

pan and tilt motion and the guide rod to direct us into each line<br />

as required.”<br />

The spokesperson said another key advantage with the system<br />

has been the capability of carrying out a manline ‘manhole<br />

to manhole’ run and to seamlessly carry out required lateral<br />

launches along the line using the same camera and data collection<br />

software without the need to produce separate video files<br />

and reports.<br />

A truck with IBAK - LISY on board.<br />

RapidView IBAK <strong>North</strong> America distributes IBAK products through a dealer network in the United States,<br />

Canada and the Caribbean Islands.<br />

The rehabilitation of pipes damaged by corrosion has resulted in the creation of innovative and<br />

effective solutions. The following provides a ‘how to’ guide for the manual application of mortar<br />

coatings.<br />

The coating of drinking water pipes has been offered<br />

within Germany since 1970. Cement mortar coatings, as per<br />

DWGW W 343, DIN 2880, DIN 2614 and EN 805, are carried<br />

out in situ on pipes from DN 80 diameter upwards. The centrifugal<br />

spray technique is a clear favourite application method.<br />

Sewer pipes have been coated with mortar in Germany since<br />

1982. The applications methods are:<br />

1. Manually applied coating<br />

2. Wet spray coating<br />

3. Centrifugal spray coating<br />

4. Displacement process<br />

Shafts and other installations in the German public drainage<br />

system have also been coated with mortars since 1982.<br />

Manually applied and wet spray coatings were the predominant<br />

methods, however the centrifugal spray M-coating<br />

process has gained more popularity recently.<br />

Manual Coating<br />

Equipment:<br />

Mortar mixing container, bucket, two-paddle mixer, trowel,<br />

steel float, sponge board, coarse sponge, graduated water<br />

container, brush or soft broom<br />

Applying the bond layer:<br />

The first step is to create a bond layer using the renovation<br />

mortar. The grout needs to be mixed to a consistency between<br />

soft and plastic and then brushed onto the prepared substrate.<br />

The bond layer should be approximately 1-2 mm thick. If the<br />

substrate shows signs of damage or cavities, these must be<br />

filled in with mortar.<br />

Mixing the pipe renovation mortar:<br />

The appropriate ERGELIT-KS mortars are mixed according<br />

to their particular instruction sheet. Always take care to<br />

put the water into the mixing receptacle first. The amount of<br />

water, calculated as a percentage in relation to the dry weight<br />

of the mortar must be exact in order to guarantee the desired<br />

water-solid ratio of 0.4 or less. The water-solid ratio is usually<br />

provided as this is more practical for mixing dry mortars on<br />

site. It is also extremely important to mix the mortar for the<br />

recommended time.<br />

Coating:<br />

The mortar coating is applied by trowel and float, wet-onwet,<br />

to the bond layer applied previously. Using the trowel to<br />

apply the mortar, as is done with ordinary cement mortars, is<br />

difficult in this case because of the high adhesion factor and<br />

is not advisable. However, there are often occasions when<br />

technically there is no alternative. As a rule, several wet-on-wet<br />

applications are required depending on the depth desired.<br />

It is essential that the surface be lightly roughened between<br />

coats with a sponge or sponge board to ensure the application<br />

of the next coat. The surface of the final coat is smoothed with<br />

a damp brush in order to prevent water and air becoming<br />

trapped during the final steel coat smoothing.<br />

When repairing damage caused by biogenic sulphuric acid,<br />

if using ERGELIT-KS 2b as coating mortar, the fresh mortar’s<br />

high thixotropy must be taken into account. This means that<br />

the fresh mortar will stiffen in the mixing container after about<br />

5-10 minutes if mixing is interrupted. If this occurs, the mortar<br />

can be re-mixed for 20-30 minutes to recover its original consistency.<br />

In order to speed up the setting time, some mortars can be<br />

modified by the use of compatible accelerators, however the<br />

manufacturer should be consulted.<br />

Ambient temperature influences working time and must<br />

be observed. Working times for the different mortars can<br />

be obtained from technical data sheets available from the<br />

manufacturer. As manual coating has little impact energy, it is<br />

generally considered to be a top surface coating technique.<br />

In the past manual coating was the most popular technique.<br />

In the future it is anticipated that the wet-spray technique will<br />

be used for larger and irregularly shaped installations.<br />

products and services<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

34<br />

35


Risky business<br />

by Roderick Lovely<br />

asset management<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

1%<br />

20%<br />

36%<br />

3%<br />

Total miles of pipe by material<br />

9%<br />

52%<br />

3%<br />

Managing assets<br />

in Las Vegas<br />

<strong>Trenchless</strong> Technology contributes substantially to asset management across the world. Charles Scott<br />

from the Las Vegas Valley Water Department spoke with <strong>Trenchless</strong> <strong>International</strong> about their asset<br />

management program.<br />

Las Vegas is the most populous<br />

city in the USA state of Nevada. The<br />

Las Vegas Valley, a 600 square mile<br />

(1600 km²) basin and surrounding area, is<br />

part of Clark County in southern Nevada.<br />

Mr Scott says the Las Vegas Valley<br />

Water District (LVVWD) is responsible for<br />

over 4,500 miles of pipe in Las Vegas and<br />

unincorporated Clark County. Mr Scott<br />

says “We also manage over 100 miles of<br />

pipe in separate small water systems in<br />

the communities of Jean, Searchlight, Blue<br />

Diamond, Laughlin, and Kyle canyon.”<br />

The breakdown of total miles of pipe by<br />

material is shown below.<br />

The largest steel pipe, including mortar<br />

lined steel pipe, bar wrapped steel pipe<br />

and pre-tensioned wire wrapped pipe is<br />

102 inches in diameter. Most pipe in this<br />

class ranges from 24-48 inches in diameter.<br />

PVC pipe ranges from 4 inches up<br />

to 42 inches and ACP from 4 inches to<br />

60 inches. Most PVC and ACP pipe are<br />

from 6 – 8 inches.<br />

Mr Scott says that because of Las Vegas’<br />

phenomenal population growth over the<br />

past ten years, the average age of all pipes<br />

in the distribution system is only about 18<br />

years. The average age for PVC pipe is<br />

eight years compared to ACP, which has<br />

an average age of between 29 and 34<br />

years.<br />

ACP has the highest break rate per mile<br />

compared with all other pipe materials.<br />

When asked what portion of assets the<br />

LVVWD inspects every year, Mr Scott says<br />

they are currently focusing assessment<br />

activities on ACP and steel pipe. “For ACP,<br />

our assessments are prioritised based on<br />

our CARE-W [computer aided rehabilitation<br />

of water networks] model that ranks pipe in<br />

terms of risk of failure – based on statistical<br />

failure modelling and hydraulic criticality –<br />

based on hydraulic modelling tool re-net.<br />

Asbestos cement<br />

Cast Iron<br />

Unknown<br />

Ductile iron<br />

PVC<br />

Polyethylene<br />

Mortar lined steel<br />

“We also try to employ the<br />

best available technology<br />

and use non-invasive<br />

techniques as much as<br />

possible.”<br />

“Other criteria such as impact to customers,<br />

potential damage to rods and<br />

types of customer served are also important<br />

considerations,” says Mr Scott.<br />

For steel, the LVVWD assessments are<br />

prioritised based on corrosion potential<br />

information collected from the Cathodic<br />

Protection system, as well as the potential<br />

consequences of failure, impact to customers<br />

and break history.<br />

“We have just this year implemented<br />

our CARE-W model, and have started a<br />

full-blown assessment program,” says Mr<br />

Scott. “This year we will assess approximately<br />

10 miles of ACP, and from 10 up to<br />

15 miles of steel pipe.”<br />

Mr Scott says that the total amount of<br />

ACP to be assessed each year will vary<br />

depending on the output of the model. The<br />

LVVWD plans on assessing approximately<br />

20 miles of steel pipe annually.<br />

<strong>Trenchless</strong> <strong>International</strong> asked if the<br />

District has adequate funding to conduct<br />

the inspection and repair programs. Mr<br />

Scott answered “Funding is a challenge<br />

for all utilities, this is why we are careful to<br />

assess only those pipes at the most risk.”<br />

The LVVWD is just beginning to investigate<br />

the advantages of <strong>Trenchless</strong><br />

Technology following a successful CIPP<br />

project. The District will be evaluating the<br />

applicability of <strong>Trenchless</strong> solutions on a<br />

case by case basis.<br />

Quantifying risk is fundamental to any physical asset management program, the following article<br />

presents how this information can be obtained and used to assess risk.<br />

Water and wastewater infrastructure<br />

managers make decisions every day<br />

that are aimed at reducing the risk of costly<br />

failures. For most, the decision process is<br />

ingrained, based on years of experience<br />

and knowledge in system management.<br />

But over time systems change, people<br />

retire, the knowledge base is lost, assets<br />

age, and the probability of costly failures<br />

increases. This is especially true in<br />

developed countries where underground<br />

utilities have been in place for over a hundred<br />

years, and the people who manage<br />

them are nearing retirement.<br />

As a new generation of managers<br />

emerges, they are being asked to manage<br />

assets that are nearing the end of<br />

their useful life with fewer resources, and<br />

tougher regulatory requirements, such as<br />

California’s Sanitary Sewer Management<br />

Plan, or SSMP. To cope with these challenges,<br />

savvy managers are turning to<br />

computer applications with physical asset<br />

management (PAM) features to allocate<br />

limited resources more strategically.<br />

Fundamental to PAM is prioritisation of<br />

assets based on a risk model. At a minimum,<br />

this involves knowing how assets<br />

might fail and what would happen if a<br />

failure were to occur. In PAM we define<br />

‘how assets might fail’ as the probability<br />

of failure (PoF) and ‘what would happen a<br />

failure were to occur’ as the consequence<br />

of failure (CoF). Risk is simply the product<br />

the PoF and CoF:<br />

Risk = PoF x CoF.<br />

Probability of failure<br />

To determine the PoF of any asset we<br />

must first determine how it may fail in terms<br />

of failure modes. When we categorise how<br />

an asset may fail there are at least four<br />

failure modes to consider that are common<br />

to all assets.<br />

Condition<br />

Condition may be put in terms of a<br />

Condition Rating by quantifying the number<br />

and extents of defects, or by direct measures<br />

such as a vibration analysis. It may be<br />

helpful to measure condition in both O&M<br />

Condition and Physical Condition. O&M<br />

Condition can be addressed through tasks<br />

such as cleaning and lubrication, while<br />

Physical Condition may call for capital remedies<br />

such as overhaul and replacement.<br />

Probability<br />

What it means<br />

100 per cent Failure likely to occur within a year<br />

90<br />

90 per cent chance of Failure in any year – Failure likely within 2<br />

years<br />

50 50 per cent chance of Failure within any year<br />

20 20 per cent chance of Failure within any year<br />

10<br />

2<br />

10 per cent chance of Failure within any year – 90 per cent<br />

chance it won’t<br />

2 per cent chance of Failure within any year - 98 per cent<br />

chance it won’t<br />

Age<br />

For age to have meaning we must<br />

first determine the life expectancy of any<br />

asset. Life expectancy can be influenced<br />

by many factors such as the surrounding<br />

environment, construction material, and<br />

installation techniques. Although age is<br />

often a good predictor of condition, an<br />

asset that appears to be in good condition<br />

may start to deteriorate rapidly or suddenly<br />

fail as it approaches the end of its<br />

useful life. Knowing how close your assets<br />

are to the end of their life expectancy may<br />

influence how often you inspect them or<br />

how you develop a replacement strategy<br />

to avoid costly failures.<br />

Capacity<br />

Does the demand placed on the asset<br />

exceed its original design capacity<br />

Influences such as population increases<br />

can certainly affect capacity. You must<br />

know what the demands are on your<br />

assets to measure capacity. Bear in mind<br />

that assets that are substantially underutilised<br />

could also lead to a higher PoF.<br />

Level of Service<br />

Perhaps the asset was put into place<br />

before new regulatory requirements were<br />

enacted. Stakeholder expectations for<br />

issues such as noise, odour, and safety<br />

may be more stringent now. Or it may<br />

be that newer alternatives have been<br />

developed that reduce the cost of operation<br />

to the point that it will be less costly<br />

to replace than to continue to operate.<br />

Establishing acceptable levels of service<br />

will help you make these determinations.<br />

Your actual list of failure modes will vary<br />

depending on the asset types that you<br />

are rating, but they will all most likely fall<br />

into one of these four categories. As you<br />

develop your criteria, take into account<br />

that ‘failure’ does not always mean a<br />

catastrophic failure, but it does mean that<br />

continuing to operate the asset without<br />

taking action will be more costly than<br />

doing something about it.<br />

Quantifying probability of failure<br />

When it comes to age, we humans<br />

inherently know that the probability of end<br />

of life increases as we grow older, and that<br />

probability increases at an accelerating<br />

rate. However, we have no way of determining<br />

precisely when the end will occur.<br />

The same is true for physical assets. But<br />

what we can do is apply a probability<br />

based on experience and historical data<br />

when available. Below is a sample table<br />

that shows how one might interpret levels<br />

of probability in a risk model.<br />

For the failure mode of age, the graph<br />

for static assets such as pipes and manholes<br />

where failure rarely occurs early in<br />

life can be illustrated in an age based<br />

curve.<br />

Mechanical and electrical assets are<br />

more prone to failures early in life and<br />

hence the probability of failure curve<br />

associated with these types of assets is<br />

often referred to as a ‘bathtub’ curve.<br />

If reliable historical data is available<br />

then the PoF should be based on the percentage<br />

of failures actually experienced.<br />

Similar curves can be created for other<br />

failure modes such as capacity where<br />

asset management<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

36<br />

37


Regarding criticality<br />

An asset that would cause<br />

severe consequences if it failed<br />

is inherently more critical to<br />

the operation of a system than<br />

assets that do not receive<br />

a high CoF rating. Thus,<br />

CoF ratings may be used to<br />

determine an asset’s criticality<br />

rating. For example if a 76 cm<br />

(30 inch) water transmission<br />

line failed it could flood out<br />

businesses, disrupt service for<br />

thousands, ruin public relations<br />

and cost a significant amount<br />

to repair so it would get a high<br />

CoF rating. In comparison a 15<br />

cm (6 inch) distribution line at<br />

the end of a residential street<br />

would not be anywhere near<br />

as consequential if it failed and<br />

therefore its criticality rating<br />

will be lower than the 76 cm (30<br />

inch) pipe.<br />

the PoF may plot as a bathtub curve<br />

because an asset that operates significantly<br />

under capacity is often more likely<br />

to fail than one operating at 50 – 75 per<br />

cent capacity.<br />

Consequences of failure<br />

Consequences of failure are often put<br />

in terms of the cost to fix and/or recover<br />

from a failure. In this sense it would be<br />

ideal to measure all consequences in<br />

terms of actual costs, but for most it is<br />

impractical to accurately forecast the<br />

cost of all failures and therefore most<br />

systems rate the CoF on an arbitrary<br />

scale. Other traits of CoFs are that they<br />

tend to reflect the service level expected<br />

and the priorities of stakeholders. For<br />

instance, the public places a high value<br />

on the environment, as does the EPA.<br />

Therefore, a sanitary sewer overflow that<br />

spills into a natural water body would<br />

be highly consequential when one considers<br />

environmental impact, aesthetic<br />

impact, and other impacts including the<br />

cost to contain and clean the spill.<br />

Some CoF examples include:<br />

• Threat to employee life and health<br />

• Threat to public life and health<br />

• Environmental damage<br />

• Regulatory compliance<br />

• Disruption of service<br />

• Property damage<br />

• Cost to repair<br />

• Loss of revenue<br />

• Public relations<br />

Generally it is more difficult to affect<br />

consequences than failure probabilities<br />

but factors such as backup and<br />

redundancy should be considered when<br />

rating them. To develop CoF ratings for<br />

the types of assets you manage you<br />

should.<br />

Develop a list of consequences that<br />

could occur if an asset fails. Typically<br />

all assets of the same type should be<br />

assigned the same list of consequences<br />

for comparative purposes.<br />

Rank the importance of each consequence<br />

relative to other consequences<br />

in the list. This is done in recognition that<br />

some consequences carry higher costs<br />

than others, for instance ‘life and health’<br />

would typically be weighted higher than<br />

‘public relations’.<br />

Develop criteria for determining a<br />

CoF rating for each asset. For instance,<br />

if a sewer manhole is within a certain<br />

distance and upstream of a water body<br />

then the CoF rating for ‘environmental<br />

damage’ will be higher than a manhole<br />

located further away from the water<br />

body.<br />

Quantifying risk<br />

Once you have determined thefailure<br />

modes, PoFs, consequences and CoF<br />

ratings, you can combine this informa-<br />

tion to calculate risk in a matrix for each<br />

asset. A risk matrix accounts for all of<br />

the CoFs and PoFs to calculate the risk<br />

for each asset<br />

In the risk matrix the consequences,<br />

along with their relative priority, are<br />

listed on the left. The asset is then<br />

rated according to the potential for<br />

each consequence to occur if the asset<br />

were to fail. The CoF score is calculated<br />

by multiplying the priority by the rating<br />

and adjusted to an arbitrary scale<br />

of 10 (where 10 signifies the highest<br />

consequence). Failure probabilities are<br />

developed from measures on the asset<br />

and entered into the table for each<br />

failure mode. Each CoF score is then<br />

multiplied by each PoF to generate risk<br />

scores. The highest risk score for each<br />

consequence is highlighted in red. The<br />

highest risk value falls out of the table as<br />

the risk factor.<br />

Developing the risk model requires<br />

this same analysis to be performed on<br />

each asset. If you are dealing with just<br />

a few assets you could perform the calculation<br />

by hand. However, if you are<br />

dealing with hundreds or thousands of<br />

assets then you should consider using<br />

a computer application to develop the<br />

model. Once the model is developed<br />

you should see patterns emerge.<br />

Planning for the future<br />

Managers have always conducted<br />

studies to gather information about their<br />

systems for decision making purposes.<br />

However, with the advent of PAM we<br />

now have a means to utilise this information<br />

qualitatively in a risk model as<br />

a basis for strategic decision making.<br />

When dealing with a large number of<br />

assets the use of computer software<br />

with PAM capabilities can help develop<br />

a risk model and assist in prioritising<br />

O&M and capital project activities. Risk<br />

assessment should be central to any<br />

asset management program as there are<br />

many tactics in PAM that use the same<br />

information pool generated from the risk<br />

model including cost/benefit analysis,<br />

triple bottom line analysis, optimised<br />

budget forecasting and reliability centered<br />

maintenance. For more information<br />

visit http://epa.gov/owm/assetmanage/<br />

index.htm .<br />

Roderick Lovely is the Vice President of Product Management at VUEWorks, Inc., developers of GISintegrated<br />

work order and asset management solutions. Mr Lovely also serves as vice chair of the New<br />

England Water and Environment Association’s Asset Management Committee.<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

asset management<br />

ASSET management<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

38<br />

39


Deterioration Factors<br />

Distress Indicators<br />

Preliminary Detailed Preliminary Detailed<br />

Covering your assets<br />

by Hesham Osman and Kevin Bainbridge<br />

Water pH Corrosion potential Leak detection RFEC/TC<br />

Pipe embedment Soil resistivity Visual inspection (test pits) Ultrasonic wall thickness<br />

Backfill type Soil pH, chlorides Pit depth measurement Visual inspection<br />

Cathodic protection<br />

Rate of wire breaks<br />

asset management<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

With the Infrastructure deficit in Canada and other countries climbing along with the changing<br />

economy, there is a real need for municipalities and utilities to take a hard look at the way they view<br />

the management of their infrastructure assets. The “asset management” era is upon us and many<br />

municipalities across Canada and internationally are recognising the necessity to change their service<br />

delivery model, essentially re-evaluating how they do business.<br />

The effective management of<br />

municipal water distribution pipes is no<br />

exception and as such, many municipalities<br />

and utilities across the country and<br />

internationally have significantly changed<br />

their philosophical and pragmatic<br />

approach to managing their distribution<br />

systems.<br />

Essential infrastructure<br />

There is a growing need for cities and<br />

water utilities to find better ways to prioritise<br />

their infrastructure asset maintenance,<br />

rehabilitation and replacement projects<br />

and to intefrate infrastructure asset management<br />

techniques into their decision<br />

making. As infrastructure ages, it becomes<br />

increasingly more challenging to assign<br />

limited capital expenditures to the repair,<br />

rehabilitation or replacement of the assets.<br />

The prudent management of water mains<br />

requires a reasonable assessment of its<br />

current condition coupled with a reliable<br />

methodology to forecast future condition<br />

State<br />

Time to second<br />

failure<br />

Time to forth failure<br />

Time to sixth failure<br />

Wiebull Parameter<br />

under different management scenarios.<br />

It can be argued that water mains are<br />

one of the most difficult infrastructure<br />

assets to properly manage in a total asset<br />

management framework. This can be<br />

partly attributed to the difficulties associated<br />

with ascertaining a reliable measure<br />

for their physical condition. Faced with this<br />

challenge, the City of Hamilton embarked<br />

on an ambitious series of studies in 2006<br />

geared towards the creation of a comprehensive<br />

tool set for managing water<br />

mains. The studies encompassed four<br />

main components:<br />

1. Water Main Criticality Model; As the<br />

starting point for risk management,<br />

the criticality model classifies assets<br />

based on their ramifications of failure.<br />

The model encompasses economic,<br />

environmental, social and operational<br />

consequences of pipe failure. The<br />

model defines the subsequent management<br />

practices that will be used<br />

for high, low, and medium criticality<br />

Table 1: Sample Weibull parameters for various material types and failure occurrences.<br />

Pipe Material type/vintage<br />

pipe. For low criticality pipe, failure<br />

can be tolerated and the goal is to<br />

develop sound management policies<br />

that balance life-cycle costs with<br />

acceptable levels of service. For high<br />

criticality pipe, failure is not acceptable<br />

and hence more proactive policies<br />

driven by actual pipe condition and<br />

deterioration factors are sought.<br />

2. Water Main Performance Model; The<br />

challenge associated with developing<br />

a performance model for water mains<br />

stems from the lack of reliable data<br />

on which to base the notion of ‘pipe<br />

condition’. The performance model<br />

is developed for low criticality pipe<br />

and uses the number of breaks as<br />

a proxy for condition. By mining the<br />

break history of various pipe vintages<br />

(ductile iron, cast iron pit cast, and<br />

cast iron spun cast), a life regression<br />

model is calibrated for times between<br />

subsequent breaks. The model is<br />

subsequently used as a forward look-<br />

Ductile CIPIt CISP1 CISP3<br />

Alpha 61.25522 37.27617 37.41538 31.16957<br />

Beta 0.571146 0.720985 0.572962 0.624836<br />

MTTF 98.5903 45.91374 59.94733 44.57487<br />

Alpha 9.02527 11.55926 10.66693 6.648598<br />

Beta 0.450631 0.542016 0.673825 0.704786<br />

MTTF 22.30006 20.13408 14.02286 8.361831<br />

Alpha 8.038522 3.426698 6.747531 4.09902<br />

Beta 0.486966 0.726976 0.49988 0.67752<br />

MTTF 16.90065 4.189806 13.50105 5.358<br />

Soil type<br />

ing predictive model to forecast the<br />

expected failure times. The model was<br />

used to assist in the development of<br />

economic intervention strategies for<br />

replacement and/or rehabilitation, longterm<br />

budget forecasts of repair and<br />

rehabilitation needs in addition to aiding<br />

at the tactical level in rationalising<br />

the coordination of capital works with<br />

sewers and road.<br />

3. Critical Water Main Management; A<br />

unique approach for critical water mains<br />

is developed based on the proactive<br />

collection of condition information. The<br />

framework is composed of two main<br />

components: a condition assessment<br />

rationalisation framework and a condition<br />

rating consolidation framework.<br />

4. Information Management Framework;<br />

The aforementioned components all<br />

require sound and reliable information.<br />

This framework aims to standardise the<br />

way information is used to make decisions<br />

pertaining to water main assets.<br />

The framework is currently developing<br />

standard information policies and practices<br />

that include all stakeholders who<br />

interact with water main information<br />

throughout its life cycle. In addition,<br />

the framework is investigating the most<br />

optimum use of HANSEN (CMMS) to<br />

support existing and evolving business<br />

processes within the City.<br />

Water Main Criticality Model<br />

The premise behind this model stems<br />

from the risk-based prioritisation and decision<br />

making concepts that are entrenched<br />

in the city’s overall approach to asset<br />

management. The intent of this model is<br />

to answer questions such as ‘Which water<br />

mains will have the greatest impact to<br />

the city, should a break occur’ in order<br />

to focus resources and effort on these<br />

assets before they fail. Prior to the establishment<br />

of the criticality model, there was<br />

no standard method for the creation of a<br />

Water Main Criticality Model. It remains a<br />

subjective process in which the municipality<br />

must be heavily involved with the<br />

selection and ranking of parameters that<br />

they feel affect water main rehabilitation<br />

and replacement costs for the local area.<br />

Pressure data<br />

Table 2: Listing of some common distress indicators and deterioration factors.<br />

Because of this, the parameters affecting<br />

cost of rehabilitation and replacement of<br />

water main infrastructure were selected<br />

and ranked within a joint effort between<br />

the consultant and the City of Hamilton.<br />

Examples of criticality parameters<br />

include pipe characteristics such as material<br />

and underground depth, type of land<br />

use in which the pipe is situated, whether<br />

the pipe is connected to major water users<br />

or to important public health facilities such<br />

as hospitals and dialysis centres, whether<br />

the pipe is located in steep slopes or environmentally<br />

sensitive areas.<br />

The application of GIS is particularly<br />

well suited to the development of<br />

Criticality Models because of its ability to<br />

apply many of the criticality parameters<br />

to the segments representing the water<br />

main assets through spatial analysis. Risk<br />

elements were organised into four main<br />

categories:<br />

1. Economic –<br />

influence of the<br />

asset’s failure<br />

on monetary<br />

resources<br />

2. Operational –<br />

influence of the<br />

asset’s failure on<br />

operational ability<br />

3. Social – influence<br />

of the asset’s failure<br />

on society<br />

4. Environmental –<br />

influence of the<br />

asset’s failure on<br />

the environment.<br />

The result of the<br />

criticality model was<br />

the categorisation of<br />

the citys inventory<br />

of water mains into<br />

three distinct groups;<br />

high, medium and<br />

low criticality water<br />

mains. The model<br />

categorised approximately10<br />

per cent<br />

of the network as<br />

having a high criticality,<br />

approximately<br />

20 per cent of the network as medium criticality<br />

and the remainder as low criticality.<br />

Water Main Performance Model<br />

The performance model is geared<br />

towards addressing the needs of low<br />

criticality water mains. The model is based<br />

on a statistical approach founded on<br />

developing mathematical models that utilise<br />

past failure history to forecast future<br />

trends and variations in breakage rates.<br />

As mentioned in the introduction to this<br />

paper, the ST-LR approach models the<br />

time between successive water main failures.<br />

The approach models each failure<br />

number (i.e. 1st failure, 2nd failure, etc…)<br />

as a separate and distinct condition state.<br />

Five distinct cohorts were modelled; three<br />

vintages of Cast Iron (spun cast), pit cast<br />

iron, and Ductile Iron. Other material types<br />

were in use (Hyprotec ductile and plastic)<br />

The Right Tool<br />

Manhole<br />

Renewal<br />

Tool Box<br />

Permacast® Liners<br />

Cor+Gard® Coatings<br />

Permaform ®<br />

Con MIC Shield®<br />

Calcium Aluminate Cements<br />

Water Plug & Patch<br />

COR+ROC Structual Polymer<br />

I & I Barrier®<br />

Top Seal TM CIPP Chimney Liners<br />

Spray Equipment<br />

Applicators<br />

Worldwide in<br />

Denmark,<br />

Ireland, UK,<br />

Singapore,<br />

Israel,<br />

Norway,<br />

Sweden<br />

and USA.<br />

For Every Problem!<br />

AP/M PERMAFORM ®<br />

Fax: +515.276.1274 • www.permaform.net<br />

asset management<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

40<br />

41


asset management<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

An example graph.<br />

but did not have sufficient failure history to<br />

warrant a standalone analysis.<br />

Sample results of the calibration process<br />

are shown in table 1. Results show a<br />

relatively long mean time to first failure for<br />

ductile iron pipes compared to cast iron<br />

pipes. However, for mean time to subsequent<br />

failures (especially after the 4th<br />

failure) cast iron pipes tend to outperform<br />

ductile iron. No significant differences<br />

were noticed in the performance of spun<br />

and pit cast iron pipes.<br />

The performance model was used to<br />

predict the following:<br />

• Long-term funding requirements for<br />

repair and replacement/rehabilitation<br />

under different level of service scenarios.<br />

Level of service was measured<br />

by number of failures experienced on a<br />

water main segment.<br />

• Using a Monte Carlo simulation to predict<br />

future failure patterns on various<br />

water main vintages, the optimum time<br />

to replace/rehabilitate was computed<br />

as a function of the ratio to repair<br />

to replacement cost. This minimum<br />

expected economic loss (MEEL) was<br />

found to be somewhat large for typical<br />

cost ratios (8-12 failures on a water<br />

main segment). This indicated that the<br />

governing criterion is more likely to be<br />

a level of service indicator set by the<br />

municipality rather than pure economics.<br />

In addition to the use of the model at the<br />

strategic planning level, the performance<br />

model was used to develop two important<br />

tools for water main management at the<br />

tactical/operational level. The coordinated<br />

infrastructure renewal tool and the early<br />

replacement tool set.<br />

Critical Water Main Management<br />

The approach for managing critical<br />

water mains differs considerably from that<br />

for noncritical mains. Some of these key<br />

differences include:<br />

• Repair policy: With noncritical water<br />

mains, breaks can be tolerated and<br />

hence a run-to-end of service life<br />

approach can be accepted. Conversely,<br />

critical water mains with zero tolerance<br />

for failure, a proactive maintenance and<br />

rehabilitation policy should be sought.<br />

• Tolerance to uncertainty: Whereas<br />

with noncritical water mains and their<br />

run to failure management approach<br />

uncertainty in condition state can be<br />

tolerated, no such tolerance can be<br />

allowed for critical water mains. This<br />

has ramifications on the amount of<br />

information being collected and the<br />

level of detail at which this information<br />

should be stored.<br />

The critical water main management<br />

framework consists of three main tool<br />

sets.<br />

1. Assessment rationalisation framework:<br />

2. Condition rating consolidation<br />

framework: This tool set attempts to<br />

standardise the way the results of<br />

assessment techniques are interpreted<br />

and subsequently used to drive decisions.<br />

The framework is developed<br />

for ductile iron and cast iron water<br />

mains as they compose the majority<br />

of the city’s critical inventory. The<br />

framework utilises Fuzzy Logic and<br />

the Analytical Hierarchy Process to<br />

combine condition rating results into an<br />

overall rating for the condition state as<br />

well as the expected deterioration rate<br />

of the pipe.<br />

3. Planning cycle decision analysis tool:<br />

The purpose of this tool is to equip<br />

the asset manager with a consistent<br />

methodology for decision-making<br />

during each planning cycle. Within<br />

a planning cycle, the asset manger<br />

must make one of three decisions<br />

for the critical water main inventory;<br />

schedule intervention, schedule<br />

inspection and revisit at next planning<br />

cycle.<br />

In order to make an informed decision,<br />

the asset manager must consider the following<br />

aspects:<br />

• Condition State. This is analogous to<br />

the probability of failure.<br />

• Pipeline Risk. This corresponds to the<br />

consequence of failure.<br />

• Extent of condition/deterioration<br />

information currently available. The<br />

tool performs a trade-off between<br />

the available amount of condition/<br />

deterioration information and the risk<br />

associated with operating the pipeline.<br />

• Level of uncertainty associated<br />

with inferring the condition state.<br />

Associated with the condition state<br />

that is inferred from the consolidation<br />

tool will be a measure of uncertainty.<br />

This factor must be considered in the<br />

decision process.<br />

This study is still ongoing and aims<br />

to re-evaluate what information is collected,<br />

and the way information is stored<br />

and handled throughout the lifecycle of<br />

the water main assets.<br />

Conclusion<br />

With these tools built, the city has established<br />

the foundation for the effective<br />

management of its watermain infrastructure.<br />

Furthermore, as these tools are<br />

integrated into the daily business decision<br />

process, they will be refined and<br />

improved to reflect the increasing knowledge<br />

growth within the city. They will also<br />

form the basis for clearly articulating the<br />

ramifications of decisions. This includes<br />

the need to focus resources, particularly<br />

financial, on the assessment of critical<br />

infrastructure, which in many cases has<br />

not yet failed or otherwise caused operational<br />

issues. These types of studies are<br />

often expensive and do not result in new<br />

tangible assets, but rather an improved<br />

understanding of the probability of failure.<br />

As such, these types of expenditures can<br />

often be challenging for cities and utilities<br />

to get funding approval for with out being<br />

able to demonstrate the non tangible<br />

benefits.<br />

This article is an edited version of a paper entitled Water Main Asset Management in the City of Hamilton: A Comprehensive Overview of Policies, Practices, Tools,<br />

and Technology by Hesham Osman and Kevin Bainbridge. The paper is to be presented at No-Dig 2009 Toronto, Canada. Please refer to the paper for more detailed<br />

information, references and acknowledgements.<br />

Delivering desalinated<br />

water to Sydney<br />

The $US419.5 million water delivery infrastructure project, part of<br />

the Sydney’s Desalination Project, aims to secure the city's water<br />

supply for future generations by constructing about 24 km of<br />

pipelines across Botany Bay, Australia.<br />

The new pipeline and its associated<br />

infrastructure and systems will carry the<br />

desalinated water from Kurnell, across<br />

Botany Bay, to Sydney's main water supply,<br />

the City Water Tunnel at Erskineville.<br />

Three tunnel boring machines (TBMs)<br />

will be employed to minimise the disturbance<br />

to residents and also to protect<br />

unique tracts of seagrass on the floor of<br />

Botany Bay.<br />

TBM: managing the environment<br />

The southern shore of Botany Bay contains<br />

extensive seagrass beds, which<br />

are a valued and protected part of the<br />

estuarine environment. Three species of<br />

seagrass are present off Silver Beach at<br />

Kurnell: zostera capricorni or eelgrass;<br />

posidonia australis or strapweed; and<br />

halophila ovalis or paddleweed. Posidonia<br />

requires the greatest consideration due to<br />

its slow reproduction and poor propagation<br />

by seed.<br />

Stretching about 6,500 metres in a westerly<br />

arc from Silver Beach at Kurnell to<br />

Lady Robinson’s Beach at Kyeemagh, the<br />

twin and single steel pipelines will impact<br />

approximately one per cent of the overall<br />

area of Botany Bay. Along the entire route,<br />

however, less than half of one per cent<br />

of existing seagrass along the southern<br />

shore (0.45 per cent) and Botany Bay<br />

(0.42 per cent) will be removed as a result<br />

of pipeline construction.<br />

Trenching through these seagrass beds<br />

would have required a seagrass management<br />

plan to be implemented during and<br />

after construction, and a compensatory<br />

seagrass package involving steps like<br />

transplantation. Instead, Sydney Water<br />

has chosen to microtunnel the pipeline<br />

from its Silver Beach construction area<br />

under Botany Bay for a distance of about<br />

800 metres in order to protect the seagrass.<br />

The Water Delivery Alliance will join<br />

the single 1,800 mm diameter pipeline<br />

from Silver Beach to the twin 1,400 mm<br />

diameter pipeline about 800 metres from<br />

the shoreline, and (as always) protection<br />

of the environment will be a key<br />

consideration. Pit construction is nearing<br />

completion at the Silver Beach site. This<br />

pit is supported by secant piling, has<br />

internal jet grouting and is around ten<br />

metres deep. Land-based sections of the<br />

pipeline will be constructed first. Material<br />

that has been dug up from the pit is being<br />

used on site where possible, in order to<br />

minimise truck movements. Continuous<br />

water quality monitoring is being carried<br />

out around the Silver Beach construction<br />

area. Recent monitoring of the site has<br />

indicated good water quality conditions,<br />

with similar results both inside and outside<br />

the silt curtain.<br />

TBM onshore<br />

A TBM is also an essential tool to minimise<br />

disruption onshore. The bore passes<br />

beneath Tasman and Dampier Streets,<br />

Kurnell, to install pipeline. The model<br />

shown is (page 45) a Herrenknecht earth<br />

pressure balance and AVN machine,<br />

weighing approximately 100 tonnes.<br />

The first microtunnelling drive through<br />

a residential area is now complete. The<br />

TBM tunnelled 640 metres from the<br />

launch pit in Cook Park, under General<br />

Holmes Drive and under Tancred Avenue<br />

to the receival pit at Muddy Creek. The<br />

TBM used was chosen specifically for the<br />

conditions at Cook Park. The pipe liner<br />

and services will be installed on this section<br />

of pipe in the coming months.<br />

The TBM has also finished tunnelling<br />

645 metres from Canal Road to<br />

Botany Freight Rail Line, which was the<br />

first tunnel completed on the project.<br />

Microtunnelling from Marsh Street<br />

Arncliffe, under the Cooks River to Tempe<br />

Recreation Reserve will begin in March.<br />

Choosing the route<br />

The pipeline route across Botany Bay<br />

was chosen because it avoids known<br />

areas of contamination. Every practical<br />

effort is being made to protect the<br />

Bay environment during construction.<br />

Water quality monitoring is ongoing<br />

during construction activities, in accordance<br />

with the Construction Water Quality<br />

Management Plan. The results of this<br />

monitoring will help the project team<br />

manage their work.<br />

environment<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

42<br />

43


environment<br />

Supplying the community<br />

Water supplied from the<br />

desalination plant will increase<br />

the total volume of water<br />

available to all customers<br />

across the whole Sydney<br />

Water area, including the Blue<br />

Mountains, the Illawarra and<br />

Sydney.<br />

The desalination plant will be<br />

capable of producing up to 250<br />

megalitres of water per day<br />

(ML/d), and will be able to be<br />

modified to produce 500 ML/d<br />

if required. With a nominal<br />

capacity of 500 ML/d, the new<br />

pipeline will be able to operate<br />

for short periods at up to 550<br />

ML/d, to allow the flow to<br />

integrate into Sydney Water’s<br />

existing water supply network.<br />

The pipeline and associated<br />

infrastructure is under<br />

construction by the Water<br />

Delivery Alliance, made up of<br />

Bovis Lend Lease, McConnell<br />

Dowell, Kellogg Brown & Root,<br />

Worley Parsons, Environmental<br />

Resources Management and<br />

Sydney Water Corporation. All<br />

of the parties to the alliance are<br />

responsible for the works to<br />

be designed, constructed and<br />

commissioned.<br />

This project is breaking new ground<br />

to achieve the distances set for the<br />

tunnel drives, while the sizing of the<br />

lay barge operations require laying<br />

twin 1,400 mm diameter pipe in a predredged<br />

trench across the vast Botany<br />

Bay waters, which is likely to be challenging.<br />

Some of the tunnels will be<br />

the longest ever undertaken by pipe<br />

jack method in Australia and potentially<br />

within the Southern Hemisphere. No twin<br />

pipeline of this diameter, laid simultaneously<br />

from a barge for 8 km, has been<br />

executed previously in Australia.<br />

Notwithstanding the considerable<br />

challenges that exist, the Water Delivery<br />

Alliance team is well-skilled and committed<br />

to overcoming them, utilising innovation<br />

and a team culture that is striving for the<br />

completion of this project on time, in a<br />

safe manner and surmounting technical<br />

challenges to break new ground.<br />

Herrenknecht tunnel boring machine.<br />

environment<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Project scope<br />

The main project works are:<br />

• A drinking water pumping station on<br />

the site of the desalination plant in<br />

Kurnell;<br />

• Infrastructure from the pumping<br />

station to the existing water supply<br />

system in Erskineville, via Silver<br />

Beach and Kyeemagh, including<br />

associated connections and flow and<br />

pressure controls;<br />

• Marine works consisting of twin<br />

7.5 km long, 1,400 mm diameter steel<br />

pipelines across Botany Bay;<br />

• Approximately 6.4 km of 1,800<br />

mm diameter mild steel cementlined<br />

onshore pipe, slipped inside<br />

2,100 mm diameter concrete pipes<br />

and installed by trenchless microtunnelling;<br />

and<br />

• Approximately 3 km of 1,800 mm<br />

diameter onshore pipeline, installed<br />

by conventional dig and lay trenching<br />

methods, with sheetpile and trench<br />

box shoring as required.<br />

Overcoming challenges<br />

Given the size of the project, and<br />

the locations it must traverse, considerable<br />

pre-planning and consultation<br />

has taken place with various regulatory<br />

authorities and the many wider stakeholders,<br />

including the community that<br />

will be affected by construction operations<br />

along the pipeline route. The<br />

Water Delivery Alliance has in place a<br />

structured team of proven community<br />

and environmental personnel, providing<br />

support to the wider team and ensuring<br />

that all approvals have been obtained<br />

and that stakeholders are well informed<br />

of both the program and methods of<br />

the activities that will take place in their<br />

vicinity. Community feedback has been<br />

encouraged and adjustments to the<br />

method or timing of activities has been<br />

made to accommodate their concerns,<br />

wherever possible.<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

44<br />

45


pipe and conduit<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Pipe and conduit<br />

Part one - a brief history and guide<br />

The choice of pipe material is an important consideration when designing road, river and rail<br />

crossings and other trenchless installations. These materials have evolved to fulfil specific purposes<br />

in modern towns and cities. To help planners decide on the most appropriate pipe for the job<br />

<strong>Trenchless</strong> <strong>International</strong> provides the first in a two part series about the history and uses of pipe.<br />

<strong>Trenchless</strong> techniques minimise disturbance to residents, business and traffic, reduce environmental impacts and deliver<br />

long term economic advantages. However, asset managers need to be informed about the characteristics, strengths and weaknesses<br />

of the pipe materials most commonly used in trenchless installations.<br />

The construction of pipes and underground conduits dates back thousands of years and is one of the earliest forms of civil engineering<br />

construction. The Romans developed cement and concrete similar to that used today. They mixed slaked lime with a pozzolanic<br />

volcanic ash from Mt Vesuvius to produce cement.<br />

The information below provides an overview of the various types of pipe available, history of the technology, the most common<br />

trenchless applications and where the technologies is most suitable. For more detailed information, readers should consult the associations<br />

and companies involved in the manufacture and distribution of pipe. Don’t miss the next issue of <strong>Trenchless</strong> <strong>International</strong><br />

which will feature the second part in our pipe and conduit series, concentrating on the rehabilitation and repair of underground infrastructure.<br />

Concrete pipe<br />

<strong>Trenchless</strong> applications: microtunnelling,<br />

pipe jacking<br />

Best suited for: storm sewer, waste water<br />

or culvert projects<br />

The oldest recorded modern-day concrete<br />

pipe installation is a sanitary sewer<br />

constructed in 1842 at Mohawk in New<br />

York State, USA. It remained operational<br />

for over 100 years. The French were the<br />

first to incorporate steel-reinforcement in<br />

concrete pipe in 1896.<br />

Concrete pipe is a rigid pipe system that<br />

is over 85 per cent dependent on the pipe<br />

strength and only 15 percent dependent<br />

on the strength derived from the<br />

soil envelope. Pre-cast concrete drainage<br />

products have a reputation for strength<br />

and durability. They will not burn, corrode<br />

prematurely, deflect or move off grade<br />

to reduce hydraulic performance. Steel<br />

reinforcement in concrete pipe adds to<br />

its inherent strength. The steel is shaped<br />

into cages.<br />

Concrete pipe is commonly joined using<br />

a confined O-ring gasket or profile gasketed<br />

joints. Common diameters range<br />

from 300 up to 3,600 mm.<br />

Bodies such as the <strong>American</strong> Army<br />

Corp of Engineers recommend a design<br />

life of 70-100 years for precast concrete<br />

pipe.<br />

Ductile iron pipe<br />

<strong>Trenchless</strong> applications: microtunnelling,<br />

HDD, pipe bursting, jacking<br />

and boring<br />

Best suited for: water and waste<br />

water<br />

The strength, durability and long<br />

service life of ductile’s predecessor,<br />

gray Cast Iron pipe, are widely recognised.<br />

The first official record of Cast<br />

Iron pipe installation was in 1455 in<br />

Siegerland, Germany. In 1664, King<br />

Louis XIV ordered construction of a<br />

Cast Iron pipe main extending 15<br />

miles from a pumping station at Marlyon-Seine<br />

to Versailles to supply water<br />

to the fountains and town. This pipe<br />

served the palace gardens for more<br />

than 330 years. Ductile Iron was introduced<br />

to the market place in 1955.<br />

Ductile Iron pipe has high tensile<br />

strength, good elasticity and excellent<br />

ductility, making it suitable for<br />

high stress applications and where<br />

pressure surge may be experienced.<br />

It offers high corrosion resistance;<br />

hydraulic flow; high working pressure<br />

and ease of installation.<br />

Ductile Iron is available in pressure<br />

ratings up to 350 psi in all diameters<br />

from 75 to 1,600 mm. It is joined by a<br />

variety of different rubber-gasketed<br />

joints, mechanical joints, flanged joint,<br />

grooved or shouldered joints, balland-socket<br />

joints are also available.<br />

When properly installed Ductile Iron<br />

has a design life of over 100 years.<br />

Steel pipe<br />

<strong>Trenchless</strong> applications: microtunnelling,<br />

directional drilling, pipe ramming<br />

Best suited for: gas, water and waste<br />

water.<br />

Early development and expansion of<br />

steel pipe manufacturing was made possible<br />

by the development of a process<br />

for refining iron into steel. The Bessemer<br />

process developed in 1855 and the openhearth<br />

process developed in 1861 were<br />

both techniques not only made steel, but<br />

also made it stronger, more ductile, and<br />

more cost effective. It was now possible to<br />

cold form steel sheets into large diameter<br />

pipes.<br />

Virtually all the early steel pipes were<br />

produced by rolling lengths of steel plate,<br />

usually 4-8 feet long, into cylinders and<br />

riveting the seams and joints to fabricate<br />

lengths of steel pipe of up to 30 - feet in<br />

overall length. The first recorded installation<br />

of steel pipe with riveted seams<br />

occurred in Railroad Flat, California in<br />

1858. Records show that some installations<br />

of steel pipe in San Francisco that<br />

were laid in 1863 are still in use today.<br />

Steel pipe is joined by welding, threading-and-coupling<br />

or compression fittings.<br />

Common diameters range from 3 up to<br />

1,500 mm.<br />

The design life varies depending upon<br />

the size, grade and coating applications.<br />

Polyvinyl Chloride (PVC)<br />

<strong>Trenchless</strong> applications: sliplining, HDD, close fit pipe lining<br />

Best suited for: water, waste water and storm water<br />

Polyvinyl chloride was discovered late in the nineteenth century. Scientists<br />

observing the newly created chemical gas, vinyl chloride, also discovered that when<br />

the gas was exposed to sunlight, it underwent a chemical reaction (now recognised<br />

as polymerisation), resulting in an off-white solid material. But, this material was so<br />

difficult to work with that it was cast aside in favour of other materials.<br />

Years later in the 1920s, rubber scientist Waldo Semon was hired by BFGoodrich<br />

to develop a synthetic rubber to replace increasingly costly natural rubber. His<br />

experiments eventually produced polyvinyl chloride. Although product developers<br />

began to use PVC in a variety of ways – in shoe heels, golf balls, and raincoats, to<br />

name just a few – its application increased significantly during World War II. PVC<br />

turned out to be an excellent replacement for rubber insulation in wiring and was<br />

used extensively on US military ships. After 1945, its peace-time usage exploded,<br />

first used for sanitary sewers in the 1930s.<br />

Plastic pipe systems account for over 75 per cent of the pressure reticulation<br />

pipelines being installed across Australia today and over 90 per cent of the sewer<br />

reticulation pipelines.<br />

PVC slipliner pipe has a gasketed joint and close-fit is butt fused. HDD may be<br />

butt fused or a gasketed joint locked together with a spline or stainless steel pins.<br />

Common diameters for gasketed PVC pipe range from 40 up to 1,500 mm for gravity<br />

sewer and up to 1,200 mm for pressure pipe.<br />

A properly designed, installed and operated system will last in excess of 100<br />

years.<br />

Vitrified clay pipe (VCP)<br />

<strong>Trenchless</strong> applications: microtunnelling, pipe bursting, pilot tube tunnelling, HDD<br />

Best suited for: waste water and storm sewers<br />

Vitrified clay is a material that arises after firing high quality clay in controlled circumstances at a temperature of approximately<br />

1,200 degrees Celsius. Vitrified clay is chemically and mechanically resistant and also, in part due to its excellent hydraulic characteristics,<br />

has a lifespan greater than 100 years.<br />

New clay may be differentiated from old clay pipe by factory-applied flexible compression joints, no joint leakage, computerised<br />

drying and firing schedules that increases strength and reduce dimensional variation with vacuum de-airing during extrusion<br />

producing a denser body.<br />

VCP is joined with a compression joint with a low profile stainless steel collar in common diameters of 100 up to 1,200 mm.<br />

Project design life is greater than 100 years.<br />

E Engineering GmbH<br />

Pischeldorfer Str. 128<br />

9020 Klagenfurt | Austria<br />

T +43.463.48 24 24<br />

F +43.463.48 21 21<br />

info@hobas.com<br />

www.hobas.com<br />

CC-GRP Pipe Systems<br />

High performance solutions for trenchless and open-dig applications<br />

Sewage<br />

Potable Water<br />

Raw Water & Irrigation<br />

Drainage<br />

Hydro Power<br />

Thermal Power Cooling<br />

Industrial Wastewater<br />

pipe and conduit<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

46<br />

47


Record SWP down under<br />

Interflow, an Australian pipeline renewal contractor, recently installed the world’s longest and largest<br />

continuous spirally wound pipe liner from a fixed winding machine as part of a sewer rehabilitation<br />

project in Sydney.<br />

PIPE AND conduit<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

High-density polyethylene (HDPE)<br />

<strong>Trenchless</strong> applications: HDD, pipe bursting, microtunnelling, sliplining<br />

Best suited for: water and wastewater, natural gas, fibre optics<br />

Paul Hogan and Robert Banks discovered crystalline polypropylene, and a similar<br />

plastic that could be produced using ethylene in 1931. When Hogan and Banks<br />

first created a reaction between ethylene and benzaldehyde using two thousand<br />

atmospheres of internal pressure, their experiment went askew when all the pressure<br />

escaped due to a leak in the testing container. On opening the tube they found<br />

a white waxy substance that looked a lot like some form of plastic.<br />

After repeating the experiment, they discovered that the loss of pressure was<br />

not due to a leak at all, but was a result of the polymerisation process. The residue<br />

polyethylene resin was a milky white, translucent substance derived from ethylene<br />

(CH2=CH2). Polyethylene was produced with either a low or high density. Highdensity<br />

polyethylene was developed in 1951.<br />

HDPE is flexible, tough, lightweight and impact resistant for lower cost installation.<br />

HDPE has performed well during earthquakes, tsunamis and corrosive environments.<br />

HDPE can be either fused or mechanically joined and is commonly available<br />

in diameters 15 to 160 mm.<br />

The life span of HDPE pipes is up to 100 years depending on design requirements<br />

and water quality.<br />

Polymer concrete pipe<br />

<strong>Trenchless</strong> applications: microtunnelling,<br />

pipe jacking<br />

Best suited for: waste water<br />

Polymer concrete is similar to conventional<br />

concrete in that it contains selected<br />

blends of aggregates and fillers that are<br />

held together using a binder. In polymer<br />

concrete the binder is high strength, corrosion<br />

resistant, thermosetting resin. This<br />

resin requires a curing agent which, when<br />

combined with the resin, transfers the<br />

resin and curing agent from a liquid to a<br />

solid that bonds the aggregate, various<br />

fillers and internal reinforcement.<br />

Advantages of polymer concrete include<br />

rapid curing at ambient temperatures,<br />

good adhesion to most surfaces, good<br />

long term durability with respect to freeze<br />

and thaw cycles, good chemical resistance,<br />

lightweight and high tensile and<br />

flexural.<br />

The standard joint for tunnelling and<br />

jacking installations incorporates a pushon<br />

stainless steel collar in common<br />

diameters of 200 up to 2,600 mm.<br />

F i b r e g l a s s reinforced pipe<br />

<strong>Trenchless</strong> applications: microtunnelling,<br />

jacking, slipling, tunnel lining<br />

and casings<br />

Best suited for: water, waste water,<br />

irrigation and drainage<br />

Fibreglass reinforced thermosetting<br />

plastic (‘fibreglass’) first became a<br />

viable alternative to protected steel,<br />

stainless steel and exotic materials<br />

in 1950. That year, centrifugal cast<br />

fibreglass piping was first used in<br />

the crude oil production industry as a<br />

solution to corrosion problems. It was<br />

during the 1960s that manufacturers<br />

began to develop nationally recognised<br />

standards and test methods<br />

for fibreglass storage and fibreglass<br />

piping systems.<br />

Fibreglass piping contains glass<br />

fibre reinforcement embedded in<br />

cured thermosetting resin. This composite<br />

structure typically contains<br />

additives such as pigments and dyes.<br />

By selecting the proper combination<br />

of resin, glass fibres, additives and<br />

design, the fabricator can create a<br />

product that meets the equipment<br />

designer’s performance standard.<br />

Fibreglass pipe is joined with pushtogether;<br />

gasket-sealed joints in<br />

common diameters of 450 up to 3,000<br />

mm with larger diameters possible.<br />

The design life is in excess of fifty<br />

years.<br />

This article is intended as a guide only; we recommended readers seek appropriate advice before selecting<br />

pipe material. This article was compiled with information from: <strong>American</strong> SpiralWeld pipe (www.acipco.<br />

com/aswp), Oxford Plastics Inc. (www.oxfordplasticsinc.com), Plastic, Pipes and Fitting Association (www.<br />

ppfahome.org), <strong>American</strong> Iron and Steel Institute (www.steel.org//AM), Fibreglass tank and pipe (www.<br />

fiberglasstankandpipe.com), Uni-Bell PVC Pipe Association (www.uni-bell.org), Plastic Industry and Pipe<br />

Association www.pipa.com.au, <strong>American</strong> Concrete Pipe Association (www.concrete-pipe.org), Ductile Iron<br />

Pipe Research Association (www.dipra.co),<br />

Hobas Pipe (www.hobas.com), National Association of Steel Pipe Distributers Association (www.naspd.com)<br />

and the National Clay Pipe Institute (www.ncpi.org).<br />

The pipe liner was 633 metres long,<br />

the equivalent of more than six football<br />

fields in length, 2.4 metres in diameter, and<br />

weighed almost 100 tonnes.<br />

The previous record for the longest continuous<br />

spirally wound pipe liner installed<br />

from a stationary winding machine was 340<br />

metres of an 800 mm diameter pipe liner.<br />

The installation method used by Interflow<br />

involved producing an in-situ pipe by spirally<br />

winding a composite plastic strip at a<br />

fixed diameter within the host pipe.<br />

The pipe liner was formed by feeding a<br />

profiled composite strip into a hydraulically<br />

powered winding machine positioned inside<br />

the existing access chamber. Adjacent profile<br />

strips were extrusion welded together<br />

inside the winding machine to form a high<br />

strength, water-tight pipe. As more strip<br />

was fed into the machine, the newly formed<br />

pipe corkscrewed its way to the downstream<br />

access chamber. The total length<br />

of 633 metres was achieved over a period<br />

of several days.<br />

Spirally winding pipes and pipe liners is<br />

not new. Various systems and techniques<br />

have existed for decades. Up until this<br />

point the practical limitation for the maximum<br />

length and size of pipe that could<br />

be produced was governed by the torque<br />

of the winding machine and its ability<br />

to overcome the frictional forces of the<br />

newly wound pipe as it rotates inside the<br />

host pipe. In the last few years, Interflow<br />

has perfected a technique for reducing<br />

the frictional forces by floating the newly<br />

formed pipe while being wound. In doing<br />

this, Interflow is able to use the flow inside<br />

the pipe to its benefit and obtain the added<br />

bonus of not needing to bypass the sewer<br />

in the act of renewal. Interflow’s technique<br />

involves controlling the water levels inside<br />

and outside the liner to achieve optimum<br />

buoyancy. In performing this work there<br />

was no indication that 633 metres was the<br />

limit of the technology. Based on the performance<br />

of the machine and the torque<br />

readings, Interflow has its sights firmly set<br />

on breaking through the one kilometre barrier<br />

in the future.<br />

This record installation by Interflow is<br />

a significant innovation for the trenchless<br />

sewer renewal industry not only because<br />

of the feat itself but also for the fact that<br />

it has opened up the potential for making<br />

very long pipelines from a single location,<br />

whether for pipe relining or tunnel boring or<br />

any other similar application. Interflow has<br />

plans to build on this platform and explore<br />

further opportunities.<br />

In this particular project, installing a pipe<br />

liner at this diameter and this length was<br />

essential because the distance between<br />

successive access chambers was uncharacteristically<br />

long. In a sense there were<br />

few other options available to reline the<br />

pipe, demonstrating once more that the<br />

<strong>Trenchless</strong> Technology industry continues<br />

to respond to the ever increasing challenges<br />

that the asset owners put to the<br />

market.<br />

The installation method, as more profile<br />

is fed into the winding machine the pipe<br />

travels towards the downstream access<br />

chamber. By the time it reached its destination<br />

100 tonnes of pipe was all turning at<br />

once.<br />

The Project<br />

The NGRS pipeline is a 2.515 metre<br />

diameter concrete sewer that runs from<br />

the Sydney suburbs of Landsdowne in<br />

the West to Arncliffe in the East. It was<br />

constructed in the 1950s and in some<br />

parts was gas attacked and in need of<br />

rehabilitation. The major challenges for<br />

Interflow were firstly to provide a structural<br />

pipe liner at such a large diameter<br />

and secondly to install a liner from existing<br />

access chambers and in continuous<br />

lengths between access chambers.<br />

In the trenchless sewer rehabilitation<br />

market, where the majority of pipe diameters<br />

are less than 1 metre, the most<br />

commonly used pipe products are made<br />

from plastic or resins. At these diameters<br />

plastic can provide a cost effective<br />

pipe, stiff enough to resist the applied<br />

loads. However, as pipe sizes increase<br />

beyond 1 metre in diameter, the range of<br />

plastic products that can provide a pipe<br />

stiff enough to resist the applied loads<br />

diminish, making it increasingly difficult<br />

to provide a practical and cost-effective<br />

liner.<br />

Interflow’s product of choice for these<br />

large diameter projects is RiblineTM, a<br />

unique steel reinforced spirally wound<br />

high density polyethylene liner. Ribline<br />

was developed by Rib Loc in 2005. A<br />

major advantage of Ribline is that the<br />

composite action between the steel and<br />

the plastic produces a pipe liner with a<br />

high strength to weight ratio and gives<br />

both the strength of steel and durability<br />

of polyethylene. For this application the<br />

Ribline pipe liner was designed to the<br />

required stiffness by using a specific size<br />

of steel reinforcement inside the plastic<br />

ribs of the profile that forms the liner.<br />

This allowed Interflow to offer its client<br />

a strong pipe with a minimum loss of<br />

cross sectional area. In fact the hydraulic<br />

performance of the lined pipe is actually<br />

enhanced as a result of relining.<br />

To put the strength to weight ratio of<br />

Ribline into perspective, a 1 metre long<br />

section of liner at 2.4 metre in diameter<br />

weighed only 150 kg. An equivalent<br />

concrete jacking pipe at the same diameter<br />

and the same strength would have<br />

weighed almost 3,000 kg.<br />

The steps involved in renewing the pipe<br />

include the following. Firstly the existing<br />

pipe and conduit<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

48<br />

49


pipe and conduit<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

The sewer had to remain operational at all times so work was performed in live flow.<br />

pipe is cleaned, with all the debris and<br />

silt removed from the pipe. The next step<br />

was to setup the Ribline installation equipment<br />

at the upstream manhole. From<br />

here the profile strip was fed from spools<br />

above ground into the Ribline winding<br />

machine stationed in the manhole below.<br />

Controlled from above ground, the Ribline<br />

winding machine wound the profile strip to<br />

produce a 2.4 metre fixed diameter pipe.<br />

Spools of Ribline profile were delivered to<br />

site as they were required. The size of the<br />

site footprint at all times during the project<br />

was surprisingly small.<br />

The liner was installed with live flow running<br />

constantly as the sewer had to remain<br />

in operation at all times. Bypass pumping<br />

and diverting the flow was not an acceptable<br />

option in this case. The flow levels<br />

were continuously monitored to make sure<br />

that buoyancy was maintained.<br />

Prior to commencement on site, extensive<br />

community consultation was necessary as<br />

many of the site works were adjacent to<br />

residential houses. Environmental sensitivity<br />

was also a key concern as the access<br />

pits and the site compound were located<br />

within an established nature reserve that is<br />

home to endangered species of flora and<br />

fauna including the Green and Golden<br />

Bell Frog, Regent Honeyeater, and the<br />

Downy Wattle Shrub. The reserve is also<br />

a recreational site that is popular with the<br />

general public because it has extensive<br />

bicycle and walking tracks. Community<br />

and Environmental Management plans<br />

were prepared to deal with these issues.<br />

Interflow’s safety performance on this<br />

project has also been outstanding with<br />

zero time lost to injuries recorded to date.<br />

This is a testament to Interflow’s management<br />

systems and also to the fact that<br />

the method used to renew the pipeline is<br />

inherently very safe.<br />

To date Interflow has successfully<br />

installed, over 1.8 km of 2.4 mm diameter<br />

Ribline pipe liner as part of this project.<br />

The company is on track to complete the<br />

project by early 2010.<br />

Interflow has demonstrated industry<br />

leadership and world class engineering<br />

innovation to overcome the challenges<br />

of the project and deliver to the client an<br />

effective and successful solution. In turn<br />

Interflow has extended the boundaries of<br />

trenchless large diameter pipeline renewal<br />

beyond the limits of what was previously<br />

considered possible.<br />

For more information about this<br />

project and Interflow visit<br />

www.interflow.com.au<br />

<strong>Trenchless</strong> Technology –<br />

building the economy<br />

by Kate Pemberton<br />

United States President Obama has signed the $US787 billion <strong>American</strong> Recovery and Reinvestment<br />

Act into law. The stimulus package, including billions of dollars to fast track ‘shovel-ready’<br />

infrastructure projects across the United States, is an effort to create jobs and grow the economy.<br />

The economic plan aims to save<br />

or create 3.5 million jobs, address the<br />

housing crisis and invest in infrastructure<br />

projects, including water and wastewater<br />

projects as well as an expansion of<br />

the broadband network. The legislation<br />

includes approximately $US150 billion<br />

in spending on ‘shovel-ready’ infrastructure<br />

projects with additional funds<br />

set aside for safe drinking water programs.<br />

There is reportedly $US4 billion<br />

slated for assistance to improving water<br />

quality and wastewater infrastructure<br />

needs and a further $US2 billion for<br />

drinking water infrastructure improvements.<br />

President Obama said of the stimulus<br />

package that “There will now be<br />

shovels in the ground, cranes in the<br />

air-rebuilding our crumbling roads and<br />

bridges and repairing our faulty levees<br />

and dams. It is the first step on the road<br />

to economic recovery.”<br />

Exploring<br />

<strong>North</strong> America<br />

In this special <strong>North</strong> America feature, <strong>Trenchless</strong> <strong>International</strong><br />

looks at the projects and politics fostering the growth of the<br />

<strong>Trenchless</strong> Technology industry in the Unites States and Canada.<br />

United States President Barack Obama is anticipating an economic<br />

recovery led by a reinvestment in essential infrastructure. The NASTT is confident<br />

that the trenchless industry will play an important role in developing these<br />

projects with a minimum of disturbance and comparatively greener credentials<br />

than the alternative.<br />

This section investigates the use of <strong>Trenchless</strong> Technology in diverse projects<br />

including whether a HDD reaming pass can remove extreme alignment doglegs;<br />

the inspection and maintenance program on New York’s New Croton Aqueduct<br />

and auger boring through hard rock, with the assistance of a disk cutter, in<br />

Pennsylvania. The trenchless aspects of the Hampton Roads Crossing in<br />

Virginia and TransCanada’s Keystone Pipeline are also featured in this overview<br />

of <strong>North</strong> America.<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

50<br />

51


north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Livingston Online, Michigan<br />

– “Up to $4.8 million could be<br />

pumped into Howell’s three year<br />

water and sewer projects.”<br />

Albany Herald, New York<br />

– “Public Works Director Phil<br />

Robertson had a list of some 18<br />

infrastructure projects [including]<br />

$34 million to rehabilitate storm<br />

and sanitary sewer system.”<br />

Lancaster Online, Pennsylvania<br />

– “44 projects are ‘shovel-ready’<br />

totalling $262…the most expensive<br />

city project proposed for funding is<br />

the construction of an underground<br />

sewer storage facility.’<br />

Kitsap Sun, Washington –<br />

“Kitsap County officials came up<br />

with 60 ‘shovel-ready’ projects<br />

including a $13 million sewer service<br />

from Bremerton Airport to the<br />

treatment facility.”<br />

Danvers Herald, Massachusetts<br />

– “Danvers submitted a list of<br />

‘shovel-ready’ projects [including]<br />

the Bates and Riverside Street renovation<br />

of water and sewer, road<br />

and sidewalk surfaces, at $1.7 million.<br />

There has been something like<br />

4,500 projects submitted by the 350<br />

cities and towns in Massachusetts.”<br />

The Daily Journal, Illinois –<br />

“Will County Executive Larry Walsh<br />

said ‘We have a list of around $60<br />

million in ‘shovel-ready’ projects.’<br />

Largest of those is a $20 million<br />

sewer infrastructure project for the<br />

Ridgewood area of Joliet.”<br />

The Bridgeport News,<br />

Connecticut – “Governor Rell’s<br />

office has received more than 215<br />

project list requests from municipalities,<br />

state legislators, state agencies,<br />

non-profit groups, regional organisations,<br />

and for-profit entities<br />

[including requests for] sewer plant<br />

improvements.”<br />

“There is an ever-growing need for<br />

<strong>Trenchless</strong> Technology as a viable solution<br />

for solving America’s underground<br />

infrastructure problems.”<br />

Governors, mayors and city officials are working overtime to<br />

identify the projects that meet the ‘shovel-ready’ qualifications<br />

set by the government. The trenchless industry looks set to<br />

benefit from the injection of funding and a renewed interest in<br />

green or sustainable projects.<br />

The nuts and bolts<br />

In late January, the US conference of Mayors released the<br />

fourth in a series of reports addressing Mainstreet Economic<br />

Recovery on infrastructure projects that are “ready to go”.<br />

The report said that in 779 cities across the country a total of<br />

18,750 local infrastructure projects are ready. These projects<br />

represent an infrastructure investment of $US149 billion that<br />

would be capable of producing an estimated 1.6 million jobs<br />

in 2009 and 2010.<br />

<strong>American</strong> towns and cities are coping with the ageing of<br />

underground assets while also attempting to keep pace with<br />

new installations. Although the infrastructure is not a visible<br />

expenditure, like bridges and roads, it is essential to the<br />

health, living standards and economy of the nation.<br />

The <strong>American</strong> Water Works Association, an authority on<br />

safe water, said that “More than $US10 billion in infrastructure<br />

projects around the nation are ‘shovel-ready’ and can be<br />

underway as soon as funds are committed.<br />

“These projects would put more than 400,000 <strong>American</strong>s to<br />

work on aging water mains, leaking pipes, treatment plants,<br />

pumps stations, storage reservoirs, elevated tanks and other<br />

needs.”<br />

President Obama, addressing Congress, said the enormous<br />

cash injection will enable the Government to “Build an<br />

economy that can lead this future, we will begin to rebuild<br />

America. Yes, we’ll put people to work repairing crumbling<br />

roads, bridges, and schools by eliminating the backlog of wellplanned,<br />

worthy and needed infrastructure projects. It means<br />

expanding broadband lines across America, so that a small<br />

business in a rural town can connect and compete with their<br />

counterparts anywhere in the world.”<br />

<strong>Trenchless</strong> industry to lead the way<br />

NASTT Chairman Chris Brahler said “Despite a sluggish US<br />

economy, I am optimistic about the outlook for the trenchless<br />

industry in the coming year. There is an ever-growing need<br />

for <strong>Trenchless</strong> Technology as a viable solution for solving<br />

America’s underground infrastructure problems.<br />

“The environmental benefits of <strong>Trenchless</strong> Technology will<br />

be attractive to those cities that are ‘going green’. Current<br />

research shows that CO2 emissions are reduced when trenchless<br />

methods are used versus open-cut. This translates to a<br />

direct-cost benefit for cities that are facing carbon taxation.”<br />

Mr Brahler said that from the green construction aspect<br />

to the heightened awareness of infrastructure, <strong>Trenchless</strong><br />

Technology looks to play a strong role in 2009 and beyond. He<br />

also emphasised that the NASTT is well-positioned to face the<br />

challenges that lie ahead.<br />

“Our industry is made up of quality manufacturers, smart<br />

engineers and talented contractors and great municipalities and<br />

end users. That’s a winning combination for any industry.”<br />

Testing the limits of HDD<br />

by J Murphy, G Fyfe, T Giesbrecht and W Dyck<br />

In 2008, Pembina Pipelines completed the construction of a pipeline project to supply oil pipeline<br />

services to one of the new Oil Sands mines in northern Alberta, western Canada. Near the middle of<br />

the project on a section of NPS 24 pipeline, an HDD was required due to access, environmental and<br />

land constraints encountered.<br />

Pembina Pipelines Trust operates<br />

approximately 8,350 km of pipelines in<br />

British Columbia and Alberta. Pembina<br />

was awarded the contract to supply<br />

pipeline services to the new Oil Sands<br />

Project.<br />

The pipeline project included the completion<br />

of five pipeline loops along the<br />

Alberta Oil Sands Pipeline (AOSPL) pipeline.<br />

Existing AOSPL right of ways (ROWs)<br />

were used wherever possible to limit the<br />

quantity of new disturbance caused by<br />

the pipeline project, which is preferred<br />

by government regulators. Construction<br />

of the Horizon Pipeline Project started<br />

in 2006. Construction management was<br />

handled by Sambrosa Engineering of<br />

Edmonton, Alberta.<br />

One of the five new pipeline loops was<br />

the 17.3 km NPS24 Pine Creek Loop,<br />

which followed the existing pipeline corridor<br />

through the environmentally sensitive<br />

La Biche Wildland Provincial Park. There<br />

were many construction related challenges<br />

to deal with on this particular portion of the<br />

project. This loop involved the crossing of<br />

two water bodies, the La Biche River at<br />

the north boundary of the Park and Pine<br />

Creek at the south boundary. These water<br />

bodies constitute portions of the northern,<br />

eastern and southern boundaries of the<br />

park.<br />

After 2002, new pipeline construction in<br />

the park was no longer permitted, as was<br />

demonstrated when another large diameter<br />

pipeline that was to be constructed<br />

at about the same time as the Pine Creek<br />

Loop was forced to reroute around the<br />

park because Pembina's existing ROW<br />

through the park was only licensed for a<br />

single pipeline. Pembina was given permission<br />

to construct the Pine Creek Loop<br />

within the Park because it had a permit<br />

for multiple pipelines within the AOSPL 30<br />

metre ROW.<br />

The original report was based on an isolated,<br />

trenched crossing design. However,<br />

this method of crossing was rejected by<br />

Alberta Tourism, Parks and Recreation<br />

based on the successful HDD crossing<br />

of the La Biche River at the north end of<br />

the La Biche River Wildland Park. Alberta<br />

Tourism requested and Fisheries and<br />

Oceans Canada subsequently permitted<br />

an HDD crossing method as a first attempt<br />

Horizon / AOSPL Route Map.<br />

with the trenched method as last resort.<br />

Worley Parsons (WP) began reviewing<br />

the various configurations for a directional<br />

drill and subsequently determined that at<br />

least some new ROW would be needed<br />

within the Park. Although summer construction<br />

would occur during the 16 April<br />

to 15 July restriction period, approval<br />

to proceed was obtained as a result of<br />

the change to a trenchless construction<br />

technique, which would not be required in<br />

stream work.<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

52<br />

53


During the above process WP was<br />

planning for the Pine Creek HDD.<br />

Success of the HDD was contingent on<br />

obtaining adequate subsurface geotechnical<br />

information to assist in engineering<br />

the crossing; the geotechnical investigation<br />

was completed in January 2007.<br />

Construction of the Pine Creek Loop was<br />

carried out successfully, with the Pine<br />

Creek HDD slated for July 2007.<br />

Due to the protected status of the La<br />

Biche River Wildland Park, no additional<br />

ROW was being granted within the park.<br />

WP attempted to design an HDD crossing<br />

with this restriction in mind but could<br />

not achieve the desired results based on<br />

the following:<br />

• The existing AOSPL ROW configuration<br />

was designed to accommodate<br />

the previously installed trenched<br />

crossing. There were changes in horizontal<br />

direction both upstream and<br />

downstream of the crossing.<br />

• A number of adjacent pipelines within<br />

the area had to be crossed along the<br />

HDD path.<br />

• The minimum design radius of curvature,<br />

required clearance from the<br />

bottom of Pine Creek and the required<br />

entry and exit angles.<br />

To ensure Pembina would be successful<br />

in obtaining the required approvals,<br />

WP chose the final alignment to utilise<br />

only existing cleared areas for the<br />

Above: Construction on hot lines with mats.<br />

Below: Direct Horizontal Rig AA 440,000 lb.<br />

necessary ROW required by the HDD<br />

alignment. The final design involved<br />

entry and exit angles of 10 degrees.<br />

Entry angles are typically steeper in<br />

order to minimise the potential for fluid<br />

releases to surface near entry and exit<br />

but 10 degrees was essential to limit<br />

the overall length of the HDD. The depth<br />

under the creek was set at the required<br />

minimum of 15 metres as noted in the<br />

geotechnical report. The alignment and<br />

length chosen had under crossings of<br />

the Suncor and Shaw cable utilities. As<br />

access on the north side of the crossing<br />

within the Park was limited, the drill entry<br />

point was established on the south side,<br />

even though the elevation was slightly<br />

higher than the north side. The total<br />

design length was about 440 metres. As<br />

a result of the alignment of the drill and<br />

the adjacent hot lines, extensive rig mats<br />

were required to allow work to be carried<br />

out over the top of these lines as well as<br />

most other aspects of the work.<br />

Ledcor Pipelines was awarded the<br />

mainline contract for the Horizon Pipeline<br />

Project. Ledcor subsequently awarded<br />

the HDD subcontract to Direct Horizontal<br />

of Stoney Plain Alberta. Direct completed<br />

the NPS 24 La Biche River crossing with<br />

an <strong>American</strong> Auger DD440 and moved<br />

the same drill rig to the south side of Pine<br />

Creek in July 2007. The selected drill rig<br />

(pictured) can be set up to enter at a<br />

minimum of 12 degrees, steeper than the<br />

designed entry of 10 degrees. Due to this<br />

change in the vertical alignment and the<br />

deepening of the bore profile as a result<br />

of steering difficulties, the total length of<br />

the drill ended up at 494.3 metres, an<br />

increase in length of about 12 percent.<br />

Problems with fluid releases close to<br />

the rig were encountered as a result of<br />

the soft ground and the shallow depth<br />

due to the shallow entry angle. Ultimately<br />

the contractor chose to put in 40 metres<br />

of 42 inch casing and then installed 70<br />

metres of 12 inch casing to minimise the<br />

fluid releases to surface. The 12 inch<br />

casing was utilised during the pilot hole<br />

drilling to try to ensure that the pilot hole<br />

was not lost as a result of the tripping in<br />

and out of the pilot hole in the soft clay<br />

formation.<br />

In addition, the contractor requested<br />

changes to the drill path to allow for a<br />

deeper drill path to minimise fluid releases.<br />

The minimum radius for the drill was set at<br />

600 metres at any point along the drill.<br />

Due to the soft nature of the clay, steering<br />

was somewhat difficult, requiring frequent<br />

adjustments. Ultimately the contractor was<br />

successful in completing the pilot hole<br />

and the first ream.<br />

At this point the engineer was provided<br />

the as-built drill profile survey data for<br />

review. Engineering Technology Inc of<br />

Calgary (Entec) was contracted to review<br />

the survey data and provide information<br />

regarding the drilled radius of the crossing.<br />

Entec used the industry accepted<br />

‘dogleg’ method to calculate the minimum<br />

radius along the drill path. The smallest<br />

radius found was 270 metres and another<br />

16 points where the radius was below the<br />

Above: View of product pipe.<br />

Below: Successful pipe pull.<br />

minimum recommended radius of 600<br />

metres.<br />

The 270 metre radius was calculated<br />

to be close to failure under installation<br />

stresses and beyond failure under operating<br />

stresses. Due to the large discrepancy<br />

between the pilot hole minimum radius of<br />

270 metre and the recommended minimum<br />

radius of 600 metres a more refined<br />

analysis of the crossing would be required<br />

to accurately determine if the current pilot<br />

hole drill path was in fact acceptable.<br />

There are a number of methods available<br />

for calculating the combined stress<br />

within an HDD drill path. The Tresca, Von<br />

Mises and limit states approaches are<br />

all recognised within the CSA Z662 and<br />

offer varying degrees of conservatism.<br />

Regardless of the method chosen stress<br />

is analysed for a pipeline within the HDD<br />

path for the maximum operational conditions.<br />

The presence of applied loads in more<br />

than one direction results in a much more<br />

complex state of stress than for applied<br />

loads in only one direction (uniaxial). The<br />

predominant stresses in pipelines are typically<br />

biaxial, with internal pressure acting<br />

in the circumferential (hoop) direction and<br />

thermal loads and beam bending acting<br />

in the longitudinal direction. The yielding<br />

of the steel under these conditions is<br />

considerably more complex, and there<br />

are two widely accepted approaches for<br />

determining the combination of stress in<br />

various directions that result in yielding<br />

of ductile material (such as steel); the two<br />

approaches are the Tresca theory and the<br />

von Mises theory (Please refer to the conference<br />

paper for further information).<br />

The combined stress as per CSA Z662<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

north america<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

54<br />

55


north america<br />

is a biaxial stress, which is a combination<br />

of hoop stress due to internal pressure<br />

and longitudinal stress due to bending<br />

of the pipe to achieve the curved shape<br />

of the HDD path added to the stress<br />

imposed on the pipeline due to thermal<br />

differential. A large positive thermal differential,<br />

together with internal pressure<br />

is typically the worst case.<br />

Shortly after deciding to complete<br />

the 36 inch ream the project team recognised<br />

it may not be reasonable to<br />

expect the 36 inch ream, to improve the<br />

current minimum pilot hole radius from<br />

270 metres to the minimum calculated<br />

radius of 425 metres as calculated in<br />

the Tresca analysis. This led to another<br />

refinement of the combined stress calculation.<br />

A more realistic approach is to<br />

compute combined stress as per the Von<br />

Mises formula, which uses similar inputs<br />

as Tresca with modest time and effort<br />

required. The Von Mises calculation<br />

method is also known to be more realistic<br />

for ductile steel such as employed in<br />

modern oil and gas pipeline systems.<br />

For the Pine Creek crossing the soil<br />

within the drill path was assumed to<br />

be a ‘soft formation’ based on feedback<br />

from the drilling contractor, the<br />

difficulty experienced with down hole<br />

steering and the results of the geotechnical<br />

investigation carried out by AMEC<br />

Earth and Environmental. This resulted<br />

in the use of soil category A.<br />

Analysis of the drill path was completed<br />

using the Von Mises method<br />

with the above parameters. The resultant<br />

minimum acceptable radius was<br />

determined to be 385 metres, a marginal<br />

improvement on the previous<br />

425 metres. The 385 metre radius would<br />

need to be compared to the calculated<br />

minimum radius in the drill path after<br />

completion of the 36 inch ream.<br />

The ream was completed two days<br />

later. Entec analysed the drill profile<br />

data and calculated a minimum dogleg<br />

radius of 284 metres, with a number<br />

of other radii less than 385 metres.<br />

The subsequent survey tool run was<br />

completed later in the same day. Entec<br />

analysed these results and calculated<br />

a minimum radius of 170 metres<br />

with a number of other radii less than<br />

385 metres. The ever decreasing calculated<br />

minimum radius confirms that the<br />

progression of the calculations is from<br />

conservative to more realistic.<br />

Pembina and its construction manager<br />

subsequently decided to pull the NPS24<br />

pipe, as seen on page 55, into the hole<br />

and the project team agreed to continue<br />

analysing the available information to<br />

determine if in fact the 36 inch reamed<br />

drill path was acceptable.<br />

First, the project team completed a<br />

sensitivity analysis to determine if reducing<br />

the MOP of the pipeline or increasing<br />

the pipe grade would be a viable alternative.<br />

After careful review, the required<br />

MOP reduction to 4,400 kPa or pipe<br />

grade increase to 545 MPa were still not<br />

sufficient to provide acceptability for the<br />

Pine Creek crossing.<br />

The next and only viable alternative<br />

for analysing the crossing was to determine<br />

the absolute stress level within<br />

the pipe at this location. The Tresca<br />

and Von Mises methods are both stress<br />

based, conservatively not accounting<br />

for the nonlinear steel properties. Due<br />

to tight bend radii determined in the<br />

field, the group agreed to undertake a<br />

third method of analysis; a nonlinear<br />

strain analysis, which is permitted by<br />

CSA-Z662 Annex C as a limit states<br />

design approach. This strain analysis is<br />

much more complex than either stress<br />

method, but it also is a more rational<br />

and usually less restrictive approach.<br />

Determination of the longitudinal strain<br />

with nonlinear steel properties and subject<br />

to biaxial stresses is performed with<br />

a finite-element computer program.<br />

Subsequent to the very detailed review<br />

of the stresses involved in this installation,<br />

the current drill alignment was<br />

supported by Worley Parsons Calgary,<br />

based on the maximum calculated strain<br />

being below the maximum allowable<br />

strain for the crossing using limit states<br />

analysis. Colt used the minimum drill<br />

path radius of 170 metres and compared<br />

the strain at this location to the maximum<br />

strain allowable for the NPS24 crossing<br />

pipe. The results were deemed acceptable<br />

as per the above discussion.<br />

In addition, Colt has recommended<br />

running a geo-pig through the crossing<br />

within two years of the start of pipeline<br />

operation. This can be used to verify the<br />

geometry of the pipe within the crossing<br />

and reconfirm the results of the limit<br />

states analysis. It is anticipated that the<br />

final geometry of the drill profile will be<br />

better than the lowest indicated radius<br />

of 172 metres.<br />

The purpose of this article is not to<br />

support less conservative analysis as<br />

a general rule for HDD installations but<br />

rather, given the difficult circumstances<br />

encountered at the site, to illustrate that<br />

this method of analysis is applicable and<br />

required in certain circumstances. HDD<br />

installations of pipelines beneath pipeline<br />

route obstructions are technically<br />

challenging, as are the determination of<br />

the construction stresses. These installations<br />

are such that future repair and<br />

cleanup if a problem develops, are<br />

not possible or are extremely difficult<br />

due to the location and depth of these<br />

installations. Therefore, a conservative<br />

approach to the design provides some<br />

assurance that problems should not<br />

occur at this type of crossing.<br />

This article is an edited version of a paper entitled<br />

Does the HDD reaming pass remove extreme<br />

alignment dog-legs: Case History by James P.<br />

Murphy, Glen Fyfe, Trevor Giesbrecht and Wes<br />

Dyck. The paper is to be presented at No-Dig<br />

2009 Toronto, Canada. Please refer to the paper<br />

for references and acknowledgements.<br />

Below: Crossing Alignment at Pine<br />

Creek- ROW sandwiched between<br />

adjacent ROWs.<br />

Rehabilitating New<br />

York City’s NCA<br />

By A Noble, D Roberts and A Fareth<br />

Constructed between 1885 and 1891, the New Croton Aqueduct<br />

(NCA) in New York State is a 50 km tunnel conveying water from<br />

the Croton watershed north of New York City to distribution<br />

systems in the Bronx and Manhattan. The NCA has benefited from<br />

an extensive design, inspection and rehabilitation program.<br />

The NCA rehabilitation program<br />

has been underway in phases since 1993,<br />

with inspections scheduled to minimise<br />

outages, allowing this strategic aqueduct<br />

to remain in service during critical seasonal<br />

periods. Between 1993 and 1997<br />

a series of in-tunnel investigations were<br />

performed in the open channel portion of<br />

the NCA, consisting of field inspection,<br />

non-destructive geophysical testing, and<br />

coring of the brick liner.<br />

Between November 2004 and<br />

September 2005, a major inspection<br />

program was conducted to assess the<br />

condition of the 11 km long pressurised<br />

section and all shafts, headhouses and<br />

blow-off structures along the entire 50 km<br />

alignment. Inspection methods included<br />

using an underwater remote operated<br />

vehicle (ROV) equipped with sonar and<br />

cameras to inspect the deep siphon, fibre<br />

optics examinations of probe holes drilled<br />

through and beyond the brick lining, and<br />

core holes and geophysical inspections to<br />

assess properties of the liner and behindthe-liner<br />

materials. A water pressure and<br />

test grouting program was conducted<br />

to assess methods and expected grout<br />

takes for the rehabilitation work in the<br />

pressurised sections. The rehabilitation<br />

program is anticipated to be completed<br />

in 2010.<br />

Part 1: planning and design<br />

The overall concept for rehabilitation<br />

of the NCA was developed in the early<br />

1990s, at which time a far-reaching program<br />

for achieving a logical and practical<br />

approach to the work was established.<br />

Since outages could only take place seasonally,<br />

contracts for any program had to<br />

be appropriately sized to coincide with<br />

the seasonal outages, while taking into<br />

account the operational needs of other<br />

water supply aqueducts owned and operated<br />

by NYCDEP.<br />

The design for the NCA rehabilitation<br />

was initially based on the results of previous<br />

investigations performed within the<br />

aqueduct’s gravity flow section in 1993<br />

and 1996. The field investigation program<br />

in 1993 included:<br />

• Visual inspection of 9.6 km of tunnel<br />

• Geophysical surveys of 9.6 km of tunnel<br />

• Remote operated vehicle (ROV) inspections<br />

• Gould’s Swamp siphon<br />

• Harlem River siphon<br />

• Probe and core drilling<br />

• Fibre optic scope inspection.<br />

The field investigation program in 1996<br />

included:<br />

• Visual inspection of the remaining 29<br />

km of gravity flow tunnel<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

The NCA is a 3.73 to 4.34 metre diameter, brick-lined circular, and horseshoe-shaped water tunnel.<br />

Except at two siphons, the aqueduct operates as an open channel conduit from the New Croton Reservoir<br />

downstream 39 km to the Jerome Park Reservoir in the Bronx. The remaining 11 km is operated as a<br />

pressurised conduit and includes a major siphon, of circular cross-section, under the Harlem River. A total of<br />

163 million bricks were used in the construction, enough to build a 48 km wall around Manhattan Island,<br />

3 metres thick and 15 metres high.<br />

The aqueduct has a flow capacity of approximately 1,100 million litres of water per and supplies on average<br />

ten per cent of New York City’s drinking water. The City’s water supply system is operated and maintained<br />

by the New York City Department of Environmental Protection (NYCDEP). Until a partial inspection in 1982,<br />

the NCA had flowed continuously since its completion nearly 100 years before. Flow tests have confirmed<br />

that the NCA can convey up to 290 million gallons per day.<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

56<br />

57


north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

• Geophysical surveys of 29 km of tunnel<br />

• Probe and core drilling<br />

• Fibre optic scope inspection<br />

• Test grouting program<br />

• Epoxy mortar lining – test section<br />

• High quality video recording<br />

• Walk-through inspections in 5.3 km<br />

length of pressurised section of NCA.<br />

In general the design phase focused on<br />

restoration of the brick lining rather than<br />

its replacement with concrete or shotcrete.<br />

Where significant defects had been<br />

observed in previous inspections and were<br />

determined to require larger-scale repairs,<br />

in situ concrete was used. (Figure 2). The<br />

design phase also considered temporary<br />

structures, such as the design of standby<br />

bulkheads to fit inside the shafts in the<br />

pressurised section of the NCA. These<br />

temporary bulkheads would serve as a<br />

means of restoring the service of the NCA<br />

should it be required to provide water<br />

to the city in the event of an emergency<br />

situation elsewhere in the water supply<br />

system. In addition, the design phase<br />

included mechanical engineering for the<br />

inspection and replacement of ageing<br />

infrastructure such as pipes, gates and<br />

valves.<br />

Diagram showing the horseshoe-shaped<br />

brick liner of the New Croton Aqueduct in<br />

the gravity flow portions of the alignment.<br />

The profile on the left shows a typical cutand-cover<br />

section: the profile on the right is<br />

typical of the mined sections. Source: The<br />

City of New York Aqueduct Commission,<br />

1895.<br />

Part 2: inspection<br />

Objective<br />

The objective of the shaft and tunnel<br />

inspections was to locate and document<br />

defects. Information gathered during the<br />

visual inspection was used to establish<br />

focal areas for both future repair contracts<br />

and further field investigation, which<br />

included coring, probe drilling, fibre optic<br />

scope inspection and test grouting.<br />

Inspection of the tunnel and shafts<br />

The scope of the inspection work<br />

under the construction contract included<br />

assessing the condition of the 9.6 km long<br />

pressurised section of NCA and inspection<br />

of shafts, headhouses and blow-off structures<br />

in both the pressurised and gravity<br />

sections.<br />

Tunnel inspection was performed<br />

between stations. Brick-lined portions of<br />

the tunnel and shafts were sounded, and<br />

the entire tunnel alignment was visually<br />

inspected. Potential voided areas were<br />

recorded in the field log and marked on the<br />

wall for possible future probe hole drilling.<br />

The lowest part of the invert was typically<br />

covered with water 100 to 200 mm deep,<br />

preventing inspection; but defects were<br />

noted when observed.<br />

The siphon under the Harlem River<br />

extends to a depth of 122 m. The purpose<br />

of performing an ROV inspection instead<br />

of dewatering the siphon and performing<br />

a walk-through inspection, was to minimise<br />

the risk of the lining buckling due<br />

to external water pressure acting on an<br />

empty lining. The siphon has never needed<br />

dewatering since it was brought into operation<br />

in 1891. The ROV was equipped with<br />

high resolution video and dual imaging<br />

sonar instruments. The objective was to<br />

verify shaft and siphon lining materials and<br />

construction features, to assess sediment<br />

levels and debris accumulations, to locate<br />

defects and to obtain video and sonic<br />

records of the structures.<br />

Testing<br />

the ground<br />

Non-destructive geophysical testing was<br />

performed within Gould’s Swamp and a<br />

fibre optic testing program was conducted<br />

at locations that appeared from the visual<br />

and geophysical investigations to merit<br />

Test grouting operations in the Bronx pressurised<br />

aqueduct.<br />

further investigation.<br />

Continuous diamond core drilling was<br />

performed on selected areas of the aqueduct<br />

to obtain samples of the tunnel lining,<br />

mortared and grouted rubble, and foundation<br />

bedrock for material identification and<br />

laboratory testing to determine engineering<br />

properties. Test grouting was performed in<br />

both the Bronx and Manhattan pressurised<br />

tunnels and at two shaft locations.<br />

The comprehensive field investigation<br />

program was used to assess the current<br />

condition of the NCA and to design a<br />

rehabilitation program. Overall, the tunnel<br />

and shafts are in very good condition,<br />

with reparable leaks or defects at some<br />

locations. The visual inspection identified<br />

tunnel defects and the geophysical inspection<br />

determined the condition of the brick<br />

liner and the grouted and mortared rubble<br />

backing. Visual and geophysical inspection<br />

findings frequently complement the laboratory<br />

test results. The test grouting program<br />

successfully stopped or decreased<br />

inflows into the test areas. The locations<br />

of abandoned shafts were verified using<br />

geophysical methods. Investigations of the<br />

‘soft rock zone’ determined that the area is<br />

geologically stable.<br />

There are a total of 49 shafts along the<br />

aqueduct alignment, ranging from large<br />

chambers in cut-and-cover sections, to<br />

small diameter shafts up to 113 m deep.<br />

Seventeen of these shafts were filled at<br />

the end of construction and are difficult<br />

to detect from the ground surface or from<br />

within the tunnel. Eight shafts were lined<br />

with a combination of brick and Cast Iron.<br />

Most were rimmed with granite collars, typically<br />

350 mm thick, at the surface. Collars<br />

at the tunnel intersection are up to 600 mm<br />

thick. Most shafts had steel ladders from<br />

the ground surface to the tunnel crown<br />

which often exhibited oxidation, tuberculation<br />

and/or section loss. The shafts were in<br />

very good to excellent condition, overall.<br />

The Harlem River siphon and associated<br />

structures were successfully inspected by<br />

a ROV and found to be aligned according<br />

to historic drawings and without evidence<br />

of major displacement or defects.<br />

Heavy groundwater inflow encountered<br />

after drilling into a water-filled void. Inflow<br />

rates subsided over the following 48 hours<br />

and were significantly reduced after grouting.<br />

Part 3: rehabilitation<br />

The goal of the project was to restore<br />

the gravity flow section of the aqueduct<br />

to optimal operating condition, thus<br />

extending the lifespan of this significant<br />

water supply for the New York City<br />

metropolitan area. A large-scale contact<br />

grouting program was performed in the<br />

horseshoe-shaped gravity flow sections<br />

of the aqueduct, with the objective of<br />

filling identified voids behind the liner,<br />

filling fractures in broken mortared and<br />

grouted rubble and foundation bedrock<br />

materials, and reducing water infiltration<br />

into the tunnel.<br />

Cover depths of the aqueduct vary considerably,<br />

ranging from a few to hundreds<br />

of metres, typically consisting of hard<br />

rock. Primarily mined using conventional<br />

methods of the late 1800s, construction<br />

of the NCA also employed cut-and-cover<br />

methods in several low-lying sections of<br />

the alignment, totalling approximately 1.6<br />

km. The NCA passes through numerous<br />

lithologic changes, fault/shear zones and<br />

under several significant water bodies,<br />

including the Pocantico and Saw Mill<br />

Rivers and the Tarrytown Reservoir. It<br />

also passes under the Harlem River as a<br />

siphon at a depth of approximately 122<br />

metres below grade.<br />

Soon after construction, reports on the<br />

NCA from The Aqueduct Commission<br />

documented prominent defects in the tunnel,<br />

such as large voids behind the lining.<br />

More recently, large-scale inspections<br />

of the gravity flow section, performed<br />

during the 1990s, and a 2004 inspection<br />

of portions of the pressurised sections,<br />

have revealed additional defects, such<br />

as open and/or deteriorated masonry<br />

joints/cracks, leaks ranging from trickles<br />

to several gallons per minute into and out<br />

of the aqueduct, missing bricks, formed<br />

openings, and in one place, a rupture<br />

through the liner with discernible offset.<br />

Despite these defects, the generally<br />

good condition of the NCA is remarkable.<br />

It is not uncommon to traverse several<br />

miles through the aqueduct without noting<br />

any significant defects.<br />

Major liner repair<br />

Major liner repair work consisted of<br />

cast-in-place reinforced concrete for filling<br />

of existing formed openings located at<br />

or near the crown of the tunnel and areas<br />

of brick heave located within the tunnel<br />

invert. Areas requiring brick replacement<br />

were minimal, totalling only 14.8 square<br />

metres.<br />

The successful rehabilitation of the<br />

38 km long gravity flow section of the<br />

New Croton Aqueduct resulted from<br />

good management and positive working<br />

relationships among the owner,<br />

the engineering consultants and the<br />

contractor. The rehabilitation was completed<br />

on schedule within approximately<br />

17 months, with crews working a typical<br />

eight-hour work shift five days a week.<br />

This is an edited version of a paper by A. Noble,<br />

D. Roberts and A. Fareth. Please refer to the paper<br />

for more detailed information, acknowledgements<br />

and references.<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

58<br />

59


disc cutter heads to work through the bore<br />

at a pace. This ensures a steady flow of<br />

the rock cuttings, and prevents any significant<br />

hindrance to the spoil return process.<br />

For this job, the spoils varied from a powdery<br />

dirt substance to finger nail clipping<br />

size remnants.<br />

The RPM rate must be balanced to<br />

coincide with the thrust pressure being<br />

produced by the auger boring machine.<br />

Throughout the total distance bored, the<br />

auger boring crew had to keep a careful<br />

eye on the variable factors that influence<br />

the amount of thrust to apply including: psi<br />

level of the rock being cut, total size of the<br />

bore, rate of spoil return, diameter of the<br />

cutting head, and overall machine torque<br />

output and speed. The bore maintained a<br />

variable output of 220,000 ft-lbs. of thrust.<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Auger boring through hard rock:<br />

overcoming the challenge<br />

by Rob Foster<br />

Hard rock is the true nemesis of the auger boring contractor, the evolution of auger boring knowhow<br />

and its increased recognition as a more widely used and understood method of underground<br />

technology has introduced disc cutter head product tooling.<br />

The disc cutter concept borrows<br />

on a smaller diameter platform than the<br />

cutting method that large tunnelling<br />

machines utilise to rotate, fracture, and<br />

remove rock chip spoils from the bore<br />

path. Manufacturers such as <strong>American</strong><br />

Augers (AA) are developing and seeing<br />

proven field results in their version<br />

of the disc cutter head. One example<br />

of creating success with man, machine,<br />

and technology is an auger boring job in<br />

Pennsylvania, USA through an unyielding<br />

rock formation.<br />

Cutting through<br />

The contract in Doylestown, Pennsylvania<br />

called for the installation of a 37 metre<br />

long gas pipeline under a two lane roadway.<br />

Henkels and McCoy subcontracted<br />

Case Boring Corporation from Gasport,<br />

Advantages of a disk cutter<br />

From the perspective of the contractor, the advantage to using a disc<br />

cutter head is that the unit is mounted directly to the product casing,<br />

which enhances cutter head stability and allows for longer cutter life.<br />

The individual cutters are manufactured with high strength steel that<br />

allows for increased working life because during use they perform a<br />

rolling motion that creates no friction. The disc cutter also benefits the<br />

operator by maximising performance in various geological formations<br />

and is designed to withstand the severe loading of mixed face<br />

conditions.<br />

Disc cutter heads have the ability to be industry wide contributors<br />

because they are compatible to any make or model of auger boring<br />

machine and auger section that is fitted with a 4 inch or 5 inch hex.<br />

New York to install the pipeline.<br />

Confronting the span of the bore was a<br />

sandstone deposit that the disc cutter was<br />

more than capable of surmounting, as the<br />

engineering design is suitable for intrusive<br />

rock formations up to 25,000 psi.<br />

Case Boring Corporation representative<br />

Mark Case said “The AA disc cutter head<br />

was the exact right choice for the job. It<br />

was effective and productive in both solid<br />

and very fissured rock, the type of rock<br />

that can give a boring contractor fits with<br />

other types of tooling.”<br />

The Case Boring crew created a<br />

15 metre long and 3 metre deep shored<br />

pit, operating on 30 feet of auger boring<br />

extension track, which would set the stage<br />

for either achieving success or create less<br />

than ideal conditions.<br />

Using a 1990 model of a 60-1,200<br />

auger boring machine and a brand new<br />

36 inch diameter disc cutter head, the<br />

Case Boring operator began pushing<br />

the product through the sedimentary<br />

landscape at a steady rotational speed.<br />

Maintaining consistent speed in a slow,<br />

but optimum range of 17 – 25 RPM allows<br />

Excavator<br />

An excavator was also used when the<br />

excavator bucket was placed on the product<br />

casing in close proximity of the disc<br />

cutter to apply pressure and to aid in the<br />

stability of the cutter as the machine made<br />

the initial penetration of the rock wall.<br />

This practice is typical for most disc cutter<br />

head jobs because the critical nature<br />

of the cutters first contact with earthen<br />

embankment will create some vibration<br />

that if not supported or monitored could<br />

cause the line of the bore to be compromised.<br />

The excavator was withdrawn<br />

shortly after the entire disc cutter had<br />

disappeared into the formation, and the<br />

vibration ceased because the head and<br />

the product casing was now shrouded<br />

in the compact composition of the earth,<br />

and the operators of the bore had settled<br />

the machine into a ‘sweet spot’ that would<br />

allow them to steadily progress.<br />

The bore<br />

The bore was done at zero percent<br />

grade. If maintaining line and grade is<br />

required, the disc cutter is equipped with<br />

power assisted steering jacks, ensuring<br />

steering corrections can be made with<br />

ease. In total, it took one and a half days<br />

to complete the bore. A traditional auger<br />

bore, without the disc cutter, would have<br />

been difficult and time consuming.<br />

AA Field Service Technician Jim Lee<br />

said “Using conventional product tooling<br />

this bore would have been possible, but<br />

we may have only been able to bore five<br />

to eight feet per day. I know from experience<br />

using a traditional rock cutting<br />

head in that type of sandstone would of<br />

required constant maintenance in replacing<br />

the carbide bullet tips every two or<br />

three feet.”<br />

Mr Case agreed, “Without the disc cutter<br />

the bores would have taken three times<br />

longer to complete, involving considerable<br />

re-tooling and time spent pulling and<br />

reinserting the auger. The head turned<br />

very easily, greatly reducing wear and<br />

tear on our auger string and drive train.”<br />

Auger boring for tough conditions<br />

Auger boring and its associated<br />

equipment or tooling, like disc cutter<br />

heads, are typically less expensive and<br />

reduce downtime more so than the conventional<br />

practice of open trenching.<br />

In neighbourhoods, metropolitan zones,<br />

wetlands/waterways, and in infrastructure<br />

development areas auger boring<br />

creates less physical disruption and can<br />

save a considerable amount of expense<br />

on product installation, reduce restoration<br />

costs and provides a tremendous<br />

amount of goodwill to the community and<br />

its inhabitants.<br />

Another down time limiting factor for<br />

disc cutter heads is that the large diameter<br />

of the head allows the head to retract<br />

from the face without moving the product<br />

casing. Having a retractable cutting<br />

head also allows for cutter change and<br />

service that can be accomplished outside<br />

of the heading.<br />

Auger boring itself is a test of both man<br />

and machine, but when those two factors<br />

are confronted with tough ground formations<br />

that can stress human emotions and<br />

mechanical muscle, the real test is how<br />

utilising proven practices and today’s<br />

technology, like disc cutter heads, can<br />

prevail in complicated situations.<br />

“The disc cutter head will allow us to<br />

make bores in a much more cost effective<br />

way than ever before. We will be<br />

able to entertain boring longer crossings<br />

than ever before due to the easy turning<br />

nature of the head and the unique steering<br />

advantages the head give us,” said<br />

Mr Case.<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

60<br />

61


north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

HRX: heading across the harbour<br />

A record was recently set on the Virginia Natural Gas Hampton Roads Crossing (HRX) HDD bore.<br />

Project Manager Les Flora spoke with <strong>Trenchless</strong> <strong>International</strong> about the innovative and challenging<br />

project.<br />

The aim of the project is to support<br />

distribution company Virginia Natural Gas<br />

(VNG), a subsidiary of AGL resources.<br />

The project itself comprises 21 miles<br />

of 24 inch diameter pipeline, extending<br />

transmission gas facilities under Hampton<br />

Roads Harbour, Virginia. The harbour is<br />

one of the largest natural harbours in the<br />

world. The harbour is also home to the<br />

largest naval base in the world and has<br />

a significantly high degree of commercial<br />

maritime traffic. The crossing of the harbour<br />

itself includes four miles of pipeline<br />

from Newport News to Newport News.<br />

In addition the project involves an<br />

HDD crossing of the Elizabeth River.<br />

This crossing demanded a 7,300 feet<br />

(2,225 metres) HDD drive in 24 inch pipeline<br />

– a bore record.<br />

Project Scope<br />

Currently, the VNG distribution system is<br />

divided into two non-contiguous pipeline<br />

systems – southern and northern – due<br />

to the geography of the Hampton Roads<br />

harbour. On a peak day, each system is<br />

fed by a single gas supplier; Columbia<br />

Gas Transmission in the Southern system<br />

and Dominion Transmission in the<br />

<strong>North</strong>ern system, making them vulnerable<br />

to gas disruptions. This project will ensure<br />

reliability of supply and future availability.<br />

The project includes the construction<br />

of approximately three miles of onshore<br />

pipeline in Hampton, four miles of onshore<br />

pipeline in Newport News, four miles of<br />

onshore pipeline in Norfolk, and ten miles<br />

crossing the Hampton Roads Harbour.<br />

The project will also include upstream<br />

pipeline compression facilities in Hanover<br />

and Charles City Counties, and a city<br />

gate station at the termination point in<br />

Norfolk.<br />

Design and construction<br />

The marine construction project team<br />

included Weeks Marine, Mears Horizontal<br />

Directional Drilling and Bradford<br />

Brothers.<br />

Weeks Marine is the general contractor<br />

on the marine portion, providing all of<br />

the marine equipment and diver support.<br />

Mears and Weeks teamed up to complete<br />

the HDD with their pipeline subcontractor,<br />

Bradford Brothers.<br />

Crossing the harbour<br />

The harbour crossing consists of five<br />

separate HDDs ranging in length from<br />

3,000 – 3,800 feet.<br />

Mr Flora said that <strong>Trenchless</strong><br />

Technology was selected for a number<br />

of reasons. The two main drivers were<br />

the environmental permits and the US<br />

Army Corps permits required as the pipe<br />

path bisected an anchorage area.<br />

The Marine Resources Commission<br />

is very active in protecting the area.<br />

Alternative methods such as conventional<br />

dredging, laying pipe on the bottom<br />

or even jetting it in were considered.<br />

However, Mr Flora said that “because of<br />

the environmental impacts, or I should<br />

say, perceived environmental impacts,<br />

the Marine Resources Commission would<br />

not permit it. So we had to directionally<br />

drill under their biggest area of concern.<br />

“On the Army Corp side there is<br />

approximately 5,000 feet of pipe to go<br />

under an anchorage area. The anchorage<br />

space is so valuable to the maritime<br />

community that the decision was made<br />

to directionally drill this section of the<br />

pipeline.”<br />

Finally, a natural shipping channel is<br />

also a part of this crossing. Mr Flora said<br />

that the company was aware that this<br />

section would be directionally drilled in<br />

order to reach the depth that would be<br />

required under the channel.<br />

The depth of the channel is 15 metres<br />

with a design depth of 19 metres. The<br />

drill path was required to be a minimum<br />

of 6 metres under the design<br />

depth. Therefore the shipping channel<br />

drill was approximately 25 metres below<br />

the water.<br />

Mr Flora continued “Three of [the<br />

drives] are marine to marine drills so<br />

we’re drilling from a barge and the<br />

receiving rig is on another barge.<br />

“We’re building those pipe sections<br />

out on the end of Craney Island, which<br />

is basically a beach, out into the harbour<br />

and then towing those sections by tying<br />

them to tug boats. Towing them off the<br />

end of the island and floating them into<br />

place and then sinking them and then<br />

hooking them back to the drill rigs for<br />

the pull back.”<br />

Mr Flora said there is also another area<br />

requiring trenchless expertise. “We are<br />

doing a bunch of small directional drills,<br />

on the Upland piece of this project. We<br />

have 7 miles (11.2 km) of pipe on land<br />

in Newport news, and about 4 miles (6.4<br />

km) in Norfolk. They are very heavily<br />

urban quarters, there are just not a lot of<br />

good places to put pipe, much less 24<br />

inch pipe.”<br />

For example, for the first mile onshore<br />

of Newport News, the pipe was directionally<br />

drilled under a tidal wetland creek as<br />

there was not a less congested route for<br />

the pipe. This pipe was separated into<br />

two drills, each approximately 2,800 feet<br />

(853 metres). Mr Flora said that space<br />

was incredibly tight, “the pipe looked<br />

like a pretzel wrapped around a tree.”<br />

Mr Flora said that without <strong>Trenchless</strong><br />

Technology the sections directionally<br />

drilled, in most cases, could not have<br />

been completed in an alternative method<br />

in a cost effective way.<br />

A challenging crossing<br />

The Elizabeth River crossing was one<br />

of the most ambitious and challenging<br />

parts of the project as this demanded<br />

the laying out of a string of pipe 7,300<br />

ft long.<br />

Fortunately Craney island, a government<br />

owned area, is located right in<br />

the middle of the project. The island<br />

is a US Army Corps dredge disposal<br />

management area. The contractors had<br />

to share the very small island area with<br />

Army Corp Engineers and the associated<br />

traffic.<br />

Mr Flora explained that the Dominion<br />

University is located on the other side of<br />

the river where the pipe was to be pulled<br />

back. During the semester this area is<br />

filled with approximately 24,000 students.<br />

Therefore the team could only operate<br />

from 12 May until 20 August.<br />

Elizabeth River Crossing: pullback.<br />

Elizabeth River Crossing.<br />

Harbour Crossing: pull head with<br />

hose connections for pipe flooding.<br />

Elizabeth River Crossing: pullback.<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

62<br />

63


“We had a very tight window to get<br />

the work done, which meant that had<br />

anything had delayed the project we’d<br />

have been stuck there in that parking lot<br />

and probably incurred some very high<br />

costs.<br />

“Fortunately, we made the time, in fact<br />

we got out 20 August around noon, and<br />

the University opened the next day and<br />

the students came back into the dorm.”<br />

Elizabeth River Crossing<br />

Length: 7,300 feet (2,225 metres)<br />

Diameter: 24 inches<br />

Pilot hole: 660,000 lb. drilling rig<br />

Pullback: 22 hours<br />

Community Consultation<br />

The project began in August 2006.<br />

In the initial months, VNG developed<br />

a communications plan and contacted<br />

regulatory agencies and elected officials<br />

at both a state and city level. The public<br />

watchdog groups were also included in<br />

the environmental issues encountered<br />

when planning the project.<br />

Mr Flora explained “We spent a lot of<br />

time with those folks, talking to them.<br />

They saw the benefits, especially in<br />

crossing the harbour. They were the<br />

first groups to really talk about drilling<br />

as opposed to dredging, to protect the<br />

environment. So we were looking at drilling<br />

all along from the beginning of that<br />

project.”<br />

Keep in touch<br />

with the<br />

hole world<br />

Free subscription to all Toronto No-Dig attendees<br />

north america<br />

Future<br />

The transmission network will increase<br />

the supply to up to 100,000 tonnes a<br />

day into the southern region and will<br />

also move another 25,000 decathons to<br />

Columbia Gas in Virginia to their account<br />

in Portsmouth.<br />

The HRX project is scheduled for<br />

completion by November 2009. Once<br />

operational, the gas pipeline will ensure<br />

a reliable supply well into the future for<br />

the communities of Virginia.<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Subscribe online by entering the code TND09 at<br />

64


HDD is the key to the<br />

Keystone Pipeline<br />

by Lyndsie Mewett<br />

TransCanada is undertaking an innovative, cost-competitive way to accommodate the expected<br />

growth in Canadian crude oil production over the next decade. The Keystone Pipeline project is unique<br />

compared with other projects in that it combines both the construction of a new 2,219 km pipeline in<br />

the US and the conversion of an existing 864 km existing pipeline from natural gas to oil service. HDD<br />

is essential to preserve the stunning landscape and achieve the necessary river crossings.<br />

“The challenge for the<br />

Pembina River HDD is<br />

ensuring we protect the<br />

special features and the<br />

natural beauty of the area<br />

while getting the pipe in place<br />

to deliver oil.”<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

The 3,456 km Keystone Pipeline is also<br />

set to serve the interests of the United<br />

States by providing a secure and reliable<br />

supply of Canadian crude oil to meet<br />

the growing demand by US refineries<br />

and markets. TransCanada spokesperson<br />

Cecily Dobson says that the project is<br />

seen as an innovative and economic way<br />

to accommodate the expected growth in<br />

Canadian crude oil production during the<br />

next decade.<br />

Canada is the largest importer of crude<br />

oil to America, supplying 2.2 MMbbl/d.<br />

TransCanada has secured commitments<br />

for 910,000 bbl/d over an average term<br />

of 18 years for the Keystone Pipeline. Ms<br />

Dobson says that this represents 83 per<br />

cent of the system’s commercial design.<br />

Approximately 2,219 km of new pipeline<br />

is to be constructed in the United States.<br />

The Canadian portion of the project<br />

includes the construction of approximately<br />

373 km of new pipeline and the conversion<br />

of approximately 864 km of existing<br />

TransCanada pipeline from natural gas to<br />

crude oil transmission.<br />

HDD: protecting the environment<br />

The project crosses several large rivers,<br />

including the Mississippi, Missouri, South<br />

Saskatchewan and Red Deer rivers, using<br />

horizontal drilling technology.<br />

TransCanada spokesperson Terry<br />

Cunha outlined the details of one HDD<br />

The pipeline<br />

The pipeline is set to be 76 cm<br />

in diameter to Illinois and 91<br />

cm from the Nebraska/Kansas<br />

border to Cushing, Oklahoma.<br />

The pipeline will be buried with<br />

a minimum depth of cover of<br />

1.2 m, depending on land use.<br />

The estimated operating<br />

pressure of new pipeline<br />

sections will be 9,930 kPa. The<br />

existing pipeline proposed<br />

for conversion to crude oil<br />

transportation will be operated<br />

at its current approved<br />

allowable operating pressure of<br />

6,067 kPa.<br />

drive, the Pembina River crossing, west of<br />

Walhalla. The <strong>North</strong> Dakota State Forest<br />

Service acquired 432 acres of Pembina<br />

Gorge land in 1970 that now is Tetrault<br />

Woods State Forest. In May 2006, the<br />

Forest Service started to negotiate with<br />

representatives of Keystone Pipeline.<br />

The commission said TransCanada had<br />

to use HDD to bury the pipe in some<br />

locations, including parts of Pembina and<br />

Sargent counties. The technique will avoid<br />

the need to cut down trees in the Tetrault<br />

Woods state forest, and a Sheyenne River<br />

Valley scenic area in <strong>North</strong> Dakota's southeastern<br />

corner.<br />

In Pembina County, the crossing<br />

involved setting up a drill rig on the<br />

south side of the Pembina River. A 4 to<br />

6 inch diameter pilot hole was drilled at<br />

an inclined angle, 7 to 9 metres below the<br />

surface of the ground and river.<br />

Sections of pipe were then hooked to<br />

the drill head and pulled on rollers through<br />

the hole, under the river, to the other side<br />

a distance of 1,051 metres. Bentonite<br />

clay was used to fill the hole around the<br />

pipeline.<br />

The drive involved approximately 15<br />

workers in making the hole to feed the<br />

pipe under the Pembina Gorge.<br />

Mr Cunha said that similar to other<br />

HDD drives on the project, “the challenge<br />

for the Pembina River HDD is ensuring<br />

we protect the special features and the<br />

natural beauty of the area while getting the<br />

pipe in place to deliver oil.”<br />

Stakeholder involvement at length<br />

Not only is the Keystone Pipeline project<br />

unique in the fact that it involves the conversion<br />

of an existing pipeline, but the<br />

project's length means that it is being<br />

overseen by various provincial, state and<br />

federal regulators in both Canada and the<br />

United States.<br />

Ms Dobson says that a comprehensive<br />

stakeholder engagement program, developed<br />

and adapted to specific stakeholder<br />

needs according to the nature, location<br />

and potential effects, has been implemented.<br />

Stakeholders include landowners and<br />

residents; community leaders; federal,<br />

provincial and local elected representatives;<br />

aboriginal and Native <strong>American</strong><br />

stakeholders; regulatory agencies; emergency<br />

services organisations; special<br />

interest groups; and, co-located right of<br />

way owners.<br />

“We recognise the importance of incorporating<br />

public input into our project<br />

plans,” says Ms Dobson. “We believe<br />

that through consultation we can address<br />

questions and concerns, and integrate<br />

important public input into our activities.<br />

“We share project information and<br />

gather input throughout the planning<br />

phase and incorporate feedback into our<br />

project design and implementation as<br />

appropriate,” she says.<br />

Converting to oil<br />

Converting the existing facilities and<br />

constructing new facilities in Canada,<br />

<strong>North</strong> Dakota and northern South Dakota<br />

began in 2008, while construction of<br />

new facilities in South Dakota, Nebraska,<br />

Kansas, Missouri and Illinois will begin<br />

this year.<br />

“It is estimated that more than 5,000<br />

individuals will have worked on the design<br />

and construction of the Keystone project<br />

by the time it’s been completed,” says Ms<br />

Dobson.<br />

Ms Dobson says that the first task of the<br />

converting of the natural gas pipeline to<br />

oil service was to isolate the natural gas<br />

pipeline from the other pipeline to which it<br />

was interconnected. Existing natural gas<br />

in the pipeline was transferred to other<br />

natural gas pipelines using a portable<br />

transfer compressor.<br />

According to Ms Dobson, the greatest<br />

challenge of the conversion was to<br />

separate the converted pipeline from the<br />

other gas pipelines in a safe manner while<br />

ensuring there was no impact to existing<br />

shippers.<br />

Once the pipeline has been purged of<br />

natural gas, it will be ready for the removal<br />

of drip tanks and tie-over assemblies.<br />

Following the isolation of the pipeline,<br />

an in-line inspection using a pigging tool<br />

will be completed to ensure the integrity<br />

Timeline<br />

of the pipeline and that it is ready for oil<br />

service.<br />

Overcoming challenges<br />

In addition to the challenge of the HDD<br />

crossing, Ms Dobson said the weather was<br />

also a factor to be overcome. The Keystone<br />

project experienced some extremely wet<br />

conditions during the 2008 construction<br />

season. In <strong>North</strong> Dakota, it was one of<br />

the wettest years recorded in history. Ms<br />

Dobson said that TransCanada was forced<br />

to extend the construction season later<br />

into the year and postpone clean up until<br />

2009.<br />

Keystone Wood River Pakota – expected to be in service in 2009<br />

Keystone Cushing – expected to be in service in 2010<br />

Keystone Gulf Coast – expected in be in service in 2011<br />

Keystone Steele City – expected to be in service 2012<br />

north america<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

66<br />

67


Undersea HDD rescue<br />

in Saudi Arabia<br />

About ISTT/Membership<br />

The ISTT is the umbrella organisation for trenchless technologists in over 40<br />

countries of the world. In 22 countries groups of trenchless technologists have<br />

their own national groups which are affiliated while the remainder are registered<br />

directly with the ISTT.<br />

In 2007-08 a pioneering HDD project was started using <strong>Trenchless</strong><br />

Technology on the Berri Causeway and Abu Ali Island on the<br />

Persian Gulf coast of Saudi Arabia. Two parallel 3,050 metre long<br />

steel pipelines were to be installed under the bay.<br />

<strong>Trenchless</strong> technology covers the repair, maintenance, upgrade and new<br />

installation of underground utility services using equipment and techniques<br />

which avoid or considerably reduce the need for excavation. The ISTT promotes<br />

research, training and the more extensive use of trenchless technology<br />

through publications, co-operation with other NGOs, an annual international<br />

conference and an interactive website.<br />

oil and gas<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

The smaller 24 inch pipe was to be<br />

used as an oil trunk line and the larger<br />

30 inch, with a total steel pipe weight<br />

of more than 1,500 tonnes, to serve as<br />

a water injection line. The project was<br />

reported to be the world’s longest undersea<br />

HDD crossing.<br />

In November 2008, Middle East specialist<br />

HDD contractor Digital Connection Co<br />

Ltd of Al-Khobar, Kingdom of Saudi Arabia<br />

sought technical advice and assistance<br />

in the recovery of a 42 inch hole-opener<br />

that had become stuck along with the<br />

3 km drill string beneath the seabed during<br />

a pre-ream pass on the second of two<br />

subsea pipeline crossings.<br />

The Berri Causeway pipeline project in<br />

the Middle East was always seen as a big<br />

challenge. Both the length of the crossings<br />

and the dimensions of the pipeline,<br />

which would weigh more than 1,525<br />

tonnes, were testing the boundaries.<br />

While the first 24 inch oil pipeline had<br />

previously been successfully installed,<br />

unforeseen delays between the drilling<br />

process over a twelve week, non-working<br />

period had caused the drill string and<br />

the 42 inch hole-opener to become stuck<br />

on the second, 30 inch pipeline crossing<br />

and installation.<br />

They had little time to provide a solution<br />

to releasing the 3 km stuck drill string<br />

and 42 inch hole-opener.<br />

However, emergency discussions<br />

between TT-UK, the main contractor, and<br />

the local drilling contractor quickly led to<br />

a response. The company recommended<br />

using the Grundoram Taurus impacting<br />

hammer combined with steel pipe adaptations.<br />

The adaptations were designed<br />

and formulated to transfer dynamic<br />

impact performance energies through<br />

special steel fabrications adapted to the<br />

drill string via the Grundoram dynamic<br />

impacting hammer.<br />

Sharing the project information with<br />

other TT Group offices in the USA and<br />

For further information please contact TT UK LTD (+44) 1234 342566<br />

fax: (+44) 1234 352184 email: info@tt-uk.com website: www.tt-uk.com<br />

Germany, TT-UK drew up a strategic<br />

plan together with a technical proposal<br />

on how they believed the drill string could<br />

be freed up using dynamic impact vibration<br />

energy.<br />

While similar successful undertakings<br />

had previously been carried out<br />

worldwide, few have been attempted for<br />

releasing stuck drill rods over such an<br />

exceptionally long distance, with each<br />

drill rod weighing 480 kg. Dynamic<br />

impact vibration energies have normally<br />

been placed on the end of product pipes<br />

for assistance in completing HDD (ram<br />

assist), or using HDD techniques for<br />

product pipe retrieval where the product<br />

pipe has become stuck. Few undertakings<br />

had previously attempted with stuck<br />

drill rods due to the enormous impact<br />

power that has to be contained onto a<br />

relatively small size drill rod (6/58th) from<br />

a large impacting hammer in a usable<br />

and controllable process.<br />

The Project owner is Saudi Aramco.<br />

The main pipeline contractor is Al Robaya<br />

and the HDD subcontractors are DCL<br />

and TATCO. The combined efforts from<br />

all companies and the personal attendance<br />

on site of Roger Atherton of TT-UK<br />

proved invaluable to the success and<br />

final retrieval of this problematic drill<br />

bore taking TT’s Grundoram and pipe<br />

ramming technologies to a new level of<br />

HDD ram assist, pipe/drill stem rescue<br />

method. Following bore-hole salvage the<br />

3 km, 30 inch water injection pipe-line<br />

was finally and successfully installed on<br />

13 January 2009.<br />

This rescue prevented significant<br />

financial implications such as the total<br />

cost of a lost drilled bore, any contractual<br />

penalties and ongoing cost delays<br />

in commissioning the final pipelines.<br />

Associated costs involved in planning a<br />

new bore and the actual costs of duplicating<br />

all the undertakings of a new bore/<br />

installation.<br />

ISTT Membership/Directory<br />

Please complete the following form.<br />

Please note: Entry in the ISTT Directory is free to Corporate<br />

Members<br />

but only if the Industry Sector is completed.<br />

Alternatively, you can fill in this form online at www.istt.com.<br />

MEMBERSHIP TYPE<br />

Corporate Membership<br />

COMPANY DETAILS<br />

Company/Organisation Name:<br />

Name of Affiliate:<br />

Please write ISTT if there is not an ISTT Affiliate in your country.<br />

CONTACT DETAILS<br />

Title:<br />

First Name:<br />

Position:<br />

Department:<br />

Address:<br />

City:<br />

State/County:<br />

Zip/Postal Code:<br />

Country:<br />

Telephone:<br />

Email:<br />

Website:<br />

<strong>Trenchless</strong> technology is recognised as an Environmentally Sustainable<br />

Technology and is particularly suited to use in densely populated urban<br />

areas by reducing disruption to peoples daily lives, social costs (traffic congestion,<br />

damage to road surfaces and buildings, air quality), noise and dust.<br />

<strong>Trenchless</strong> technologies also have a considerably reduced carbon footprint<br />

compared to trenching in most situations.<br />

Ordinary Membership<br />

Last Name:<br />

Fax:<br />

INDUSTRY SECTOR<br />

Please select the industry sector that<br />

best describes your company, multiple<br />

selections can be made. Please check all<br />

relevant boxes.<br />

Agent<br />

Consultant<br />

Contractor<br />

Site Survey / Inspection /<br />

Leakage Detection<br />

Off Line Installation / Replacement<br />

Moling / Ramming<br />

Boring / Directional Drilling<br />

Pipe jacking / Microtunnelling<br />

On Line Replacement -<br />

Pipe Bursting / Splitting / Eating<br />

Repairs<br />

Internal Sleeves / Seals<br />

Resin Injection<br />

Robotic Repairs<br />

Renovation<br />

Cured in Place<br />

Sliplining (incl. spiral wound)<br />

Close Fit Lining<br />

Spray Lining<br />

Large diameter Systems<br />

(incl. segment lining, in situ lining<br />

and manholes)<br />

Equipment / Materials Supplier /<br />

Manufacturer<br />

Equipment Rental<br />

Public Sector / Utility<br />

Water / Sewerage<br />

Gas<br />

Electricity<br />

Telecoms<br />

Other<br />

Education / Research /<br />

Test Laboratory<br />

the international society for trenchless technology<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

68<br />

69


the international society for trenchless technology<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

Contacts and Addresses of Affiliated Societies<br />

AATT<br />

Osterreichische Vereinigung<br />

fur grabenloses Bauen und<br />

Instandhalten von Leitungen (OGL)<br />

Schubertring 14A-1015 Wien<br />

AUSTRIA<br />

Tel: +43 1 513 15 88/26<br />

Fax: +43 1 513 15 88/25<br />

Email: boccioli@oegl.at<br />

www.oegl.at<br />

Chairman: Robert Selinger<br />

Member Secretary: Ute Boccioli<br />

Int. Representative: Ute Boccioli<br />

(boccioli@oegl.at)<br />

ABRATT<br />

Al. Olga, 422 cj. 97<br />

Barra Funda – CEP 0155-040<br />

Sao Paulo - SP<br />

BRAZIL<br />

Tel: +55 (11) 3822 2084<br />

Fax: +55 (11) 3825-2414<br />

Email: secretaria@abratt.org.br<br />

www.abratt.org.br<br />

Chairman: Paulo Dequech<br />

Member Secretary: Fábio Tesarotto<br />

Int. Representative: Sergio Palazzo<br />

(Fax: +55 19 3881 3933)<br />

ASTT<br />

18 Frinton Place<br />

Greenwood<br />

WA 6024<br />

AUSTRALIA<br />

Tel: +61 (0)8 9420 2826<br />

Fax: +61 (0)8 9343 5420<br />

Email: jeffpace@astt.com.au<br />

www.astt.com.au<br />

Chairman: Menno Henneveld<br />

(menno.henneveld@mainroads.wa.gov.au)<br />

Member Secretary: Jeff Pace<br />

Int. Representative: Jeff Pace<br />

(jeffpace@astt.com.au)<br />

BATT<br />

Koprinka Lake Village<br />

Kazanlak<br />

6100<br />

BULGARIA<br />

Tel: +359 2 4901381<br />

Fax: +359 431 63776<br />

Email: info@batt-bg.org<br />

www.batt-bg.org<br />

Chairman: Mr. Stefan Zhelyazkov<br />

Member Secretary: Pavel Gruev<br />

CHKSTT<br />

10/F Hing Lung Commercial Building<br />

68-74 Bonham Strand East<br />

HONG KONG<br />

Fax: +852 81487764<br />

Email: info@chkstt.org<br />

www.chkstt.org<br />

Chairman: Ian Vickridge<br />

(vickridgeig@BV.com)<br />

Vice Chairman: Jon Boon<br />

(JBoon@insituform.com)<br />

Int. Representative: Derek Choi<br />

(derekchoi@balama.com)<br />

Treasurer: Ray Fung<br />

(ray.fung@towngas.com)<br />

CTSTT<br />

Rom 3150, 3F., No.3, Beiping W. Rd.,<br />

Zhongzheng District,<br />

Taipei<br />

TAIWAN<br />

Tel: :+886 2 2312 0709<br />

Fax: +886 2 2362 1268<br />

Email: anitawu@mail.water.gov.tw<br />

Chairman: Liao, Tsung-Shen<br />

General Secretary: Su, Jin-Long<br />

(steven@mail.water.gov.tw)<br />

Secretary: Anita Wu<br />

(anitawu@mail.water.gov.tw)<br />

Int. Representative: Prof. D.H Jlang<br />

CzSTT<br />

Bezova 1658/1<br />

147 14 Praha 4<br />

CZECH REPUBLIC<br />

Tel: +420 244 062 722<br />

Fax: +420 244 062 722<br />

Email: czstt@czn.cz<br />

www.czstt.cz<br />

Chairman: Stanislav Drabek<br />

(czstt@czn.cz)<br />

Member Secretary: Dr Jiri Kubalek<br />

(czstt@czn.cz)<br />

Int. Representative: Stanislav Drabek<br />

FiSTT<br />

Pl 493<br />

00101 Helsinki<br />

FINLAND<br />

Tel: +358 5 7495091<br />

Fax: +358 5 7495010<br />

Email: jani.vakeva@kymenvesi.fi<br />

www.fistt.net<br />

Chairman: Mikko Isakow<br />

(mikko.isakow@kouvola.fi)<br />

Int. Representative: Mikko Isakow<br />

Member Secretary: Jani Vakeva<br />

(Tel: +358 5 2344757)<br />

Secretary: Jani Vakeva<br />

(jani.vakeva@kymenvesi.fi)<br />

FSTT<br />

4 rue des Beaumonts<br />

F-94120 Fontenay Sous Bois<br />

FRANCE<br />

Tel: +33 1 53 99 90 20<br />

Fax: +33 1 53 99 90 29<br />

Email: fstt.paris@wanadoo.fr<br />

www.fstt.org<br />

Chairman: Patrice Dupont (President)<br />

Executive Director: Dominique Guillerm<br />

(dguillerm.fstt@aliceadsl.fr)<br />

Int. Representative: Jean-Marie Joussin<br />

(jeanmarie.joussin@hobas.com)<br />

General Secretary: Christian Legaz<br />

(christian.legaz-avr@wanadoo.fr)<br />

Treasurer: Jérôme Aubry<br />

(jaubry@chantiers-modernes.fr)<br />

GSTT<br />

Messedamm 22<br />

D-14055 Berlin<br />

GERMANY<br />

Tel: +49 30 3038 2143<br />

Fax: +49 30 3038 2079<br />

Email: beyer@gstt.de<br />

www.gstt.de<br />

Chairman: Prof. Dipl-Ing Jens<br />

Hoelterhoff<br />

Member Secretary: Dr Klaus Beyer<br />

Secretary: Dr Klaus Beyer<br />

Int. Representative: Dr Klaus Beyer<br />

IATT<br />

Via Ruggero Fiore, 41<br />

00136 Rome<br />

ITALY<br />

Tel: +39 06 39721997<br />

Fax:+39 06 91254325<br />

Email: iatt@iatt.it<br />

www.iatt.it<br />

Chairman: Paolo Trombetti<br />

(paolo.trombetti@telecomitalia.it)<br />

Member Secretary: Françoise Roccetti<br />

Hudebine<br />

(iatt@iatt.it)<br />

Int. Representative: Alessandro Olcese<br />

(2005emanuele@alice.it)<br />

Secretary: Feliciano Esposto<br />

(esposto.feliciano@virgilio.it)<br />

IbSTT<br />

C/ Josefa Valcarcel, 8 – 3a PTLA.<br />

28027 Madrid<br />

SPAIN<br />

Tel: +34 91 418 23 44<br />

Fax: +34 91 418 23 41<br />

Email: ibstt@ibstt.org<br />

www.ibstt.org<br />

Chairman: Alfredo Avello<br />

Member Secretary: Elena Zuniga Alcon<br />

Int. Representative: Alfredo Avello<br />

JSTT<br />

3rd Nishimura BLDG.<br />

2-11-18 Tomioka<br />

Koto-ku<br />

TOKYO, 135-0047<br />

JAPAN<br />

Tel: +81 3 5639 9970<br />

Fax: +81 3 5639 9975<br />

Email: office@jstt.jp<br />

www.jstt.jp<br />

Chairman: Mr Taigo Matsui<br />

(office@jstt.jp)<br />

Executive Secretary: Yoshihiko Nojiri<br />

(nojiri@jstt.jp)<br />

Member Secretary: Kyoko Kondo<br />

(kondo@jstt.jp)<br />

LIATT<br />

V.Gerulaicio str. 1<br />

LT-08200 Vilnius<br />

Lithuania<br />

Tel: +370 5 2622621<br />

Fax: +370 5 2617507<br />

Email: arturas.abromavicius@sweco.lt<br />

Chairman: Arturas Abromavicius<br />

(President)<br />

Member Secretary: Arturas<br />

Abromavicius<br />

Int. Representative: Arturas<br />

Abromavicius<br />

Algirdas Budreckas (Chairman of Council)<br />

NASTT<br />

1655 <strong>North</strong> Fort Myer Drive Ste 700<br />

Arlington<br />

Virginia 22209<br />

USA<br />

Tel: +1 703 351 5252 (US)<br />

+1 613 424 3036 (Canada)<br />

Fax: +1 613 424 3037<br />

(also Membership)<br />

Email: info@nastt.org<br />

www.nastt.org<br />

Chairman & <strong>International</strong><br />

Representative: Chris Brahler<br />

(cbrahler@tttechnologies.com)<br />

Vice Chairman: George Regula<br />

Treasurer: Kaleel Rahaim<br />

Secretary: Keith Hanks<br />

(keith.hanks@lacity.org)<br />

Executive Director: Mike Willmets<br />

(mwillmets@nastt.org)<br />

Assistant Executive Director:<br />

Angela Ghosh<br />

(aghosh@nastt.org)<br />

ESC Member: Dr Samuel Ariaratnam<br />

NSTT<br />

Postbus 483<br />

2700 AL Zoetermeer<br />

THE NETHERLANDS<br />

Tel: +31 (0)79 3252265<br />

Fax: +31 (0)79 3252294<br />

Email: info@nstt.nlwww.nstt.nl<br />

www.nstt.nl<br />

Chairman: Theo Everaers<br />

(mjceveraers@lievense.com)<br />

Secretary: Jelle de Boer<br />

(J.deBoer@bouwendnederland.nl)<br />

Int. Representative:Gerard (Gert) Arends<br />

(g.arends@citg.tudelft.nl)<br />

PFTT<br />

25-001 Kielce 1 skr. Poczt. 1453<br />

POLAND<br />

Tel: +48 41 3622145 (600328459)<br />

Email: parkaa@tu.kielce.pl<br />

www.pftt.pl<br />

Chairman: Andrzej Kuliczkowski<br />

Vice Chairman: Mr Wlodzimierz Pala<br />

Member Secretary: Anna Parka<br />

(parkaa@tu.kielce.pl.)<br />

Int. Representative: Andrzej Kuliczkowski<br />

Secretary: Marek Banasik<br />

RSTT<br />

Moscow area, Odintsovskii region,<br />

Marfino, 99, 143025,<br />

RUSSIAN FEDERATION<br />

Tel: +7 (495) 771 71 00<br />

Fax: +7 (495) 771 71 00<br />

Email: np-robt@mail.ru, robt@co.ru<br />

www.robt.ru<br />

Chairman: Stanislav Khramenkov<br />

Member Secretary: Elena Gusenkova<br />

Int. Representative: Andrey Sinitsyn<br />

SASTT<br />

PO Box 13048<br />

CLUBVIEW<br />

0014<br />

South Africa<br />

Tel: +27 (12) 567 4026<br />

Fax: +27 (12) 567 4026 (ask for Fax)<br />

Email: director@sastt.org.za<br />

www.sastt.org.za<br />

Chairman: Johann Wessels<br />

Honorary Director: Joop van Wamelen<br />

Member Secretary: Joop van Wamelen<br />

SSTT<br />

Box 7072<br />

S-174 07 Stockholm<br />

Sweden<br />

Tel: +46 8 522 122 90<br />

Fax: + 46 8 522 122 02<br />

Email: lennart.berglund@stockholmvatten.se<br />

www.sstt-skandinavien.com<br />

Chairman: Magnar Sekse<br />

(magnar.sekse@bergen.kommune.no)<br />

Vice Chairman: Gerda Hald<br />

(gh@ov.dk)<br />

Secretary (SSTT): Lennart Berglund<br />

(lennart.berglund@stockholmvatten.se)<br />

Member Secretary (Danish):<br />

Tina Juul Madsen (tjm@wtc.dk)<br />

Member Secretary (Norweigan):<br />

Odd Lieng (odd.lieng@rorsenter.no)<br />

Member Secretary (Swedish): Kjell Frödin<br />

(kjell@vretmaskin.se)<br />

UAMTT<br />

9A R.Karmen Str.<br />

Odessa 65044<br />

UKRAINE<br />

Tel: (380 482) 356305<br />

Fax: (380 482) 356305<br />

Email: no_dig@blacksea.od.ua<br />

www.no-dig.odessa.ua<br />

Chairman: Victor Prokopchuk<br />

ESC Member: Olga Martynyuk<br />

(Olga_marty@ukr.net)<br />

UKSTT<br />

38 Holly Walk<br />

Leamington Spa<br />

Warwickshire<br />

CV32 4LY<br />

UK<br />

Tel: +44 (0)1926 330 935<br />

Fax: +44 (0)1926 330 935<br />

Email: admin@ukstt.org.uk<br />

www.ukstt.org.uk<br />

Chairman: Steve Kent<br />

(steve.kent@pipe-equipment.co.uk)<br />

(Tel: 01642 769 789)<br />

Member Secretary: Val Chamberlain<br />

(admin@ukstt.org.uk)<br />

(Tel: 01926 330 935)<br />

the international society for trenchless technology<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

70<br />

71


ADVERTISERS INDEX<br />

SUBSCRIPTION FORM<br />

the international society for trenchless technology<br />

April 2009 - <strong>Trenchless</strong> <strong>International</strong><br />

<strong>American</strong> Augers 38<br />

Barbco 50<br />

BKP Berolina Polyester GmbH 31<br />

Brandenburger Liner GmbH 29<br />

Engineering 2009<br />

IBC<br />

Hanlyma 19<br />

HDD Broker and HDD Auction 22<br />

Hermes Technologie GmbH 35<br />

Herrenknecht AG<br />

IFC<br />

HOBAS Engineering GmbH 47<br />

IBAK Helmut Hunger GmbH 34<br />

IDS Ingegneria Dei Sistemi S.p.A 15<br />

KA-TE PMO AG 33<br />

Mears Group, Inc. 11<br />

Permaform 41<br />

Prime Drilling GmbH 54<br />

Prime Horizontal 9<br />

RWF Bron 45<br />

SEKISUI CPT GmbH<br />

OBC<br />

Sprayroq 55<br />

Tracto-Technik GmbH 13<br />

VueWorks 39<br />

Coming in future issues<br />

July 2009 October 2009 Directory/Yearbook 2010 January 2010<br />

Regional Focus Ukraine / Japan UK<br />

Industry Focus<br />

Inspection & Condition<br />

Assessment<br />

Risk Management<br />

Microtunnelling & Pipe<br />

Pipe Bursting<br />

HDD<br />

Major Features<br />

Jacking<br />

CIPP<br />

This indispensable reference Relining option<br />

Relining Tools<br />

guide will include:<br />

Utility Close-Up Water Electricity & Communications Wastewater<br />

Technology<br />

Products and<br />

Equipment<br />

Extra<br />

Circulation<br />

Manholes<br />

Resins<br />

Drilling Fluids / Pumps<br />

& Mud Systems<br />

SWE, Japan<br />

Modern <strong>Trenchless</strong><br />

Technologies, Ukraine<br />

Name:<br />

Job Title:<br />

Company:<br />

Address:<br />

Telephone:<br />

Fax:<br />

Email:<br />

I would like to subscribe to <strong>Trenchless</strong> <strong>International</strong>:<br />

Please invoice me<br />

I have enclosed a cheque/draft for<br />

payable to Great Southern Press Pty Ltd<br />

Annual subscription:<br />

A limited number of qualified free subscriptions are available.<br />

You can use this form to apply obligation free.<br />

Paid subscriptions are also available at the following rate<br />

$US60, €45, £35 (for one year/five issues including Directory)<br />

Please either detach this page or make a photocopy and send to:<br />

Great Southern Press Pty Ltd<br />

GPO Box 4967 Melbourne VIC 3001<br />

Phone: +61 3 9248 5100<br />

Fax: +61 3 9602 2708<br />

Email: query@trenchlessinternational.com<br />

Web: www.trenchlessinternational.com<br />

Utility Location<br />

Drilling Equipment<br />

<strong>Trenchless</strong> Australasia 2009,<br />

Melbourne, Australia<br />

Drain Trader Exhibition,<br />

Cheltenham, UK<br />

ICUEE 2009<br />

Louisville, Kentucky, USA<br />

Fully indexed listings of all<br />

companies in the industry<br />

Project information<br />

Techniques<br />

History and more.<br />

* Please note the updated deadlines.<br />

Middle East<br />

Environment & Sustainability<br />

CCTV<br />

Vacuum Equipment<br />

UCT, Tampa FL, USA<br />

DEADLINE 8 May 2009 31 July 2009 30 October 2009 27 November 2009<br />

72


conference, exhibition, technology shows<br />

Supported by:<br />

Ministerstwo<br />

Infrastruktury<br />

prof. dr hab. inż.<br />

Kazimierz Furtak Rektor<br />

Politechniki Krakowskiej<br />

Engineering<br />

2009<br />

1 6-18 J une<br />

TOMASZOWICE<br />

Near Krakow<br />

P O L AND<br />

prof. dr hab. inż.<br />

Antoni Tajduś<br />

Rektor AGH<br />

Polski Komitet<br />

Geotechniki<br />

Związek Mostowców<br />

Rzeczypospolitej<br />

Polskiej<br />

Room 1• networks inspection and monitoring<br />

• networks rehabilitation<br />

• pipes in trenchless technology<br />

• HDD<br />

• cables in city underground infrastructure<br />

• pipe jacking and microtunnelling<br />

Room 2• tunnelling<br />

• underground construction<br />

• geoengineering<br />

• bridges<br />

• hydro-technical construction<br />

General sponsor: Panel sponsors:<br />

Supporting sponsors:<br />

Polskie Stowarzyszenie<br />

Technologii<br />

Bezwykopowych<br />

Polska Fundacja<br />

Technologii<br />

Bezwykopowych<br />

Polskie Zrzeszenie<br />

Wykonawców<br />

Fundamentów Specjalnych<br />

Izba Gospodarcza<br />

Wodociągi Polskie<br />

Organisers:<br />

www.i-b.pl/conference/<br />

Inżynieria Bezwykopowa sp. z o.o.<br />

31-305 Kraków<br />

ul. Radzikowskiego 1<br />

tel. +48 12 351 10 90<br />

fax +48 12 393 18 93<br />

e-mail: biuro@i-b.pl

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!