COUNCIL MINUTES<br />

TUESDAY 28 AUGUST 2012<br />

• The unfavourable variance <strong>of</strong> $515k for employee costs is mainly <strong>of</strong>fset by the<br />

favourable variance in materials and contracts expenditure, resulting from a shift in<br />

the delivery <strong>of</strong> services from contracted services to in-house at the Wembley Golf<br />

Course and Quarry Amphitheatre.<br />

• The favourable variance <strong>of</strong> $63k for interest expense is due to lower variable interest<br />

rates on the $11 million commercial loan for the Wembley Golf Course.<br />

• The favourable variance <strong>of</strong> $309k on loss <strong>of</strong> disposal <strong>of</strong> assets is due to<br />

infrastructure assets replaced during the year not as yet having been written <strong>of</strong>f or<br />

disposed <strong>of</strong>.<br />

Capital Revenue<br />

Capital revenue from non operating grants and contributions is $773k more than budget,<br />

predominantly due to a capital grant <strong>of</strong> $1 million received from State Government towards<br />

Wembley Sports Park (Stage1) not budgeted for.<br />

Capital Expenditure<br />

Capital expenditure as at 30 June 2012, excluding land purchases, is $9 million against<br />

revised budget <strong>of</strong> $13.5 million giving a variance <strong>of</strong> $4.5 million. The majority <strong>of</strong> this variance<br />

relates to capital projects not commenced or which are in progress, such as the City Beach<br />

Pavilion renewal. These projects have been re-budgeted in FYE 2013.<br />

Reserve and Endowment Lands Account Transfers<br />

The net draw down on reserves and Endowment Lands Account is $194k.<br />

The transfer to reserves is $522k less than budget due to proceeds from Harding Lane<br />

subdivision delayed to 2012/2013.<br />

Transfer to Endowment Lands Account is below budget by $941k due to one Ocean Mia lot<br />

remaining unsold at year end. Draw downs on the Endowment Lands Account are below<br />

budget by $1.2 million due to a number <strong>of</strong> major ELA funded projects in progress and being<br />

carried forward into 2012/2013 such as the City Beach Pavilion upgrade ($450k unspent)<br />

and Quarry Amphitheatre Upgrade ($384k unspent).<br />

Closing (Municipal) Funds Carried Forward<br />

Municipal-funded carried forward projects <strong>of</strong> $2.95 million have been identified for the<br />

2012/2013 financial year. The notes to and forming part <strong>of</strong> the 2011/2012 summarised<br />

statement <strong>of</strong> financial activity detail the main programs, non capital and capital projects<br />

being carried forward. Add to this the unspent grants received in advance <strong>of</strong> $1.42 million<br />

and the total carried forward municipal funds become $4.37 million.<br />

Surplus/(Deficit)<br />

The final surplus for the 2011/2012 year is $180k, which is transferred to the Plant Reserve.<br />

H:\CEO\GOV\COUNCIL MINUTES\12 MINUTES\AUGUST 2012\C CR.DOCX 190