COUNCIL MINUTES<br />
TUESDAY 28 AUGUST 2012<br />
STRATEGIC DIRECTION:<br />
The eventual development <strong>of</strong> this land for sporting purposes is consistent with the <strong>Town</strong>'s<br />
strategic plan <strong>of</strong> creating communities <strong>of</strong> choice.<br />
COMMUNITY CONSULTATION:<br />
Award <strong>of</strong> these contracts has been assessed in terms <strong>of</strong> the <strong>Town</strong>'s Community<br />
Consultation Policy 1.2.11 as not requiring community consultation as the matter is purely<br />
administrative in nature with no external impacts envisaged.<br />
ATTACHMENTS:<br />
1. Executive Summary - Tender Recommendation Report (Confidential)<br />
COUNCIL DECISION:<br />
(COMMITTEE AND ADMINISTRATION RECOMMENDATION)<br />
Moved by Cr Langer, seconded by Cr Walker<br />
That:-<br />
(i)<br />
(ii)<br />
(iii)<br />
(iv)<br />
(v)<br />
(vi)<br />
Tender T01-12 be awarded to Robinson Build Tech at a contract cost <strong>of</strong><br />
$1,070,230 for the refurbishment and redevelopment <strong>of</strong> City Beach Oval<br />
Pavilion;<br />
approval be given to increasing the project budget $250,000 with funding as<br />
detailed in (iii) and (iv) below;<br />
an amount <strong>of</strong> $233,000 for the refurbishment and expansion <strong>of</strong> City Beach Oval<br />
Pavilion be authorised by an ABSOLUTE MAJORITY as unbudgeted<br />
expenditure in accordance with s6.8 <strong>of</strong> the Local Government Act 1995 (to be<br />
funded from the Endowment Lands Account);<br />
an additional $17,000 <strong>of</strong> funding from West Coast Sporting Association be<br />
sought as an increase from their existing commitment <strong>of</strong> $83,000 to bring their<br />
contribution to a total <strong>of</strong> $100,000;<br />
West Coast Sporting Association to provide an initial payment <strong>of</strong> $40,000 once<br />
site works commence, $43,000 once the project has reached practical<br />
completion; and $8,500 in each subsequent financial year; and<br />
any saving in the contingency funds be retained by the <strong>Town</strong>.<br />
Carried by an ABSOLUTE MAJORITY 9/0<br />