COUNCIL MINUTES<br />

TUESDAY 28 AUGUST 2012<br />

STRATEGIC DIRECTION:<br />

The eventual development <strong>of</strong> this land for sporting purposes is consistent with the <strong>Town</strong>'s<br />

strategic plan <strong>of</strong> creating communities <strong>of</strong> choice.<br />

COMMUNITY CONSULTATION:<br />

Award <strong>of</strong> these contracts has been assessed in terms <strong>of</strong> the <strong>Town</strong>'s Community<br />

Consultation Policy 1.2.11 as not requiring community consultation as the matter is purely<br />

administrative in nature with no external impacts envisaged.<br />

ATTACHMENTS:<br />

1. Executive Summary - Tender Recommendation Report (Confidential)<br />

COUNCIL DECISION:<br />

(COMMITTEE AND ADMINISTRATION RECOMMENDATION)<br />

Moved by Cr Langer, seconded by Cr Walker<br />

That:-<br />

(i)<br />

(ii)<br />

(iii)<br />

(iv)<br />

(v)<br />

(vi)<br />

Tender T01-12 be awarded to Robinson Build Tech at a contract cost <strong>of</strong><br />

$1,070,230 for the refurbishment and redevelopment <strong>of</strong> City Beach Oval<br />

Pavilion;<br />

approval be given to increasing the project budget $250,000 with funding as<br />

detailed in (iii) and (iv) below;<br />

an amount <strong>of</strong> $233,000 for the refurbishment and expansion <strong>of</strong> City Beach Oval<br />

Pavilion be authorised by an ABSOLUTE MAJORITY as unbudgeted<br />

expenditure in accordance with s6.8 <strong>of</strong> the Local Government Act 1995 (to be<br />

funded from the Endowment Lands Account);<br />

an additional $17,000 <strong>of</strong> funding from West Coast Sporting Association be<br />

sought as an increase from their existing commitment <strong>of</strong> $83,000 to bring their<br />

contribution to a total <strong>of</strong> $100,000;<br />

West Coast Sporting Association to provide an initial payment <strong>of</strong> $40,000 once<br />

site works commence, $43,000 once the project has reached practical<br />

completion; and $8,500 in each subsequent financial year; and<br />

any saving in the contingency funds be retained by the <strong>Town</strong>.<br />

Carried by an ABSOLUTE MAJORITY 9/0<br />