COUNCIL MINUTES<br />
TUESDAY 28 AUGUST 2012<br />
works. Analysis showed that the pre tender estimate was consistently below every tender<br />
price for preliminaries, electrical works and structural works. These are major components <strong>of</strong><br />
the project. In essence, insufficient allowance was made for these aspects <strong>of</strong> the project.<br />
The Administration has reviewed the project scope and tenders to determine what, if any,<br />
savings can be made. Approximately $20,000 <strong>of</strong> the tender price includes temporary<br />
facilities to be used (primarily as temporary toilets and change rooms) during the<br />
construction period for the cricket club needs. Approximately $ 20,000 has been tendered for<br />
external paving including car park. Any further savings would require significant reduction in<br />
scope by scaling back the size <strong>of</strong> the building extension. These costs have not been<br />
removed from the revised budget at this stage.<br />
The original project budget was $920,000 inclusive <strong>of</strong> construction, rise and fall, fees and<br />
contingencies. The revised project budget is now:<br />
Construction budget $1,070,230<br />
Fees $47,125<br />
Sub Total $1,117,355<br />
Contingency (approx 5% <strong>of</strong> construction) $52,645<br />
Total Budget $1,170,000<br />
West Coast Sporting Association agreed to contribute $83,000 towards the initial project<br />
budget <strong>of</strong> $920,000 (ie 9% <strong>of</strong> budget). During tender analysis, discussions were held with<br />
West Coast Sporting Association as to the matter <strong>of</strong> budget shortfall. They have considered<br />
this matter, and <strong>of</strong>fered to increase their total contribution to the project to $99,000 in<br />
recognition <strong>of</strong> increased building costs to maintain scope. This equates to 8.5% <strong>of</strong> budget. It<br />
is recommended that West Coast Sporting Association be required to fund 9% <strong>of</strong> the<br />
construction and fees budget which would be $ 100,000, with the <strong>Town</strong> retaining the<br />
Contingency budget.<br />
The Club has asked for consideration <strong>of</strong> a suitable payment schedule recognising the<br />
limitations <strong>of</strong> sporting clubs to raise large one <strong>of</strong>f payments. It is proposed that West Coast<br />
Sporting Association agree to fund $40,000 once site works commence; $43,000 prior to<br />
practical completion <strong>of</strong> the works and the remaining $17,000 as two equal annual payments<br />
in subsequent financial years.<br />
The project still holds a contingency. This will be used if necessary for issues arising during<br />
construction against the current scope. If West Coast Sporting Association request additional<br />
works to be undertaken during the construction these will need to be fully funded by West<br />
Coast Sporting Association. Once the project is complete, any remaining contingency will be<br />
retained by the <strong>Town</strong> as project savings as this amount is being fully funded by the <strong>Town</strong>.<br />
POLICY/STATUTORY IMPLICATIONS:<br />
In line with <strong>Council</strong> Policy, <strong>Council</strong> approval is necessary for the award <strong>of</strong> tenders greater<br />
than $100,000 unless the decision is delegated to the Chief Executive Officer.<br />
FINANCIAL IMPLICATIONS:<br />
The forecast cost for this project will require an increase in budget funding by $250,000. It is<br />
proposed that <strong>Council</strong> approve by an absolute majority, an increase <strong>of</strong> funding <strong>of</strong> $233,000<br />
to be sourced from the Endowment Lands Account and that $17,000 be sought from West<br />
Coast Sporting Association.<br />
H:\CEO\GOV\COUNCIL MINUTES\12 MINUTES\AUGUST 2012\C CR.DOCX 155