Appendix A<br />
Page 4/4<br />
Shatin Government Offices<br />
May 1998<br />
The BD issued PNAP No. 224 on “Superstructure Works — Measures for<br />
Public Safety”. PNAP No. 224, among other enhanced precautionary<br />
measures, required the construction of a double-deck hoarding with a<br />
projected, up-turn catch-platform.<br />
December 1998<br />
The FC approved the upgrading of the project “Shatin Government Offices<br />
Building” to Category A of the Public Works Programme.<br />
December 1998<br />
The ArchSD invited tenders for the STGO Contract and incorporated its<br />
hoarding requirements, which were based on the ArchSD’s standard<br />
drawings, into the tender documents as part of the Employer’s<br />
Requirements.<br />
July 1999<br />
The ArchSD awarded a design-and-build contract, the STGO Contract, to<br />
Contractor B for the construction of the STGO.<br />
September 1999<br />
The construction of a single-deck hoarding was completed in accordance<br />
with the Employer’s Requirements.<br />
July 2000<br />
The ArchSD discovered that there was a discrepancy between the<br />
ArchSD’s standard hoarding and the hoarding required by PNAP No. 224.<br />
December 2000<br />
For safety reasons, the ArchSD decided to upgrade the hoarding<br />
immediately to comply with the latest requirements of building works, i.e.<br />
PNAP No. 224.<br />
January 2001<br />
The ArchSD issued a variation order to Contractor B to modify the<br />
hoarding which had been constructed.