Appendix A<br />

Page 3/4<br />

March 1999<br />

The ArchSD, in accordance with the requirements of the Stores and<br />

Procurement Regulations, sought the FB’s approval of a single tender for<br />

the design and the construction of the footbridge by Contractor A.<br />

May 1999<br />

The fitting-out works for the MEB commenced.<br />

July 1999<br />

The CSB, the FB, the DH and the GSD had no in-principle objection to<br />

allowing government departments to engage private medical practitioners to<br />

conduct the medical examinations for recruitment to the civil service, and<br />

to implementing the outsourcing proposal by phases.<br />

August 1999<br />

The ArchSD informed the FB that the ArchSD withdrew its request for<br />

approval of the single tender for the construction of the footbridge.<br />

October 1999<br />

The fitting-out works for the MEB were completed.<br />

October 1999<br />

The works of the CSWGO Contract were substantially completed.<br />

November 1999<br />

The Director of Architectural Services endorsed the issue of a variation<br />

order for the design and the construction of the footbridge at an estimated<br />

cost of $2.9 million.<br />

December 1999<br />

The DH informed the GPA that the need to relocate the MEB from its<br />

existing accommodation at the Canton Road Government Offices had to be<br />

reconsidered.<br />

December 1999<br />

The CSB informed Heads of Department that the Government planned to<br />

outsource the medical examination services by July 2000.<br />

January 2000<br />

The DH informed the GPA and the CSB that, in view of the outsourcing of<br />

the medical examination services, the DH considered that it was not<br />

worthwhile to relocate the MEB to the CSWGO as originally planned. The<br />

ArchSD estimated that fitting-out works of $3.7 million completed for the<br />

MEB were rendered abortive.<br />

May 2000<br />

The ArchSD assessed that the prolongation cost arising from the allocation<br />

of CSWGO office space to another major user department would be<br />

$3.27 million.