Appendix A<br />
Page 3/4<br />
March 1999<br />
The ArchSD, in accordance with the requirements of the Stores and<br />
Procurement Regulations, sought the FB’s approval of a single tender for<br />
the design and the construction of the footbridge by Contractor A.<br />
May 1999<br />
The fitting-out works for the MEB commenced.<br />
July 1999<br />
The CSB, the FB, the DH and the GSD had no in-principle objection to<br />
allowing government departments to engage private medical practitioners to<br />
conduct the medical examinations for recruitment to the civil service, and<br />
to implementing the outsourcing proposal by phases.<br />
August 1999<br />
The ArchSD informed the FB that the ArchSD withdrew its request for<br />
approval of the single tender for the construction of the footbridge.<br />
October 1999<br />
The fitting-out works for the MEB were completed.<br />
October 1999<br />
The works of the CSWGO Contract were substantially completed.<br />
November 1999<br />
The Director of Architectural Services endorsed the issue of a variation<br />
order for the design and the construction of the footbridge at an estimated<br />
cost of $2.9 million.<br />
December 1999<br />
The DH informed the GPA that the need to relocate the MEB from its<br />
existing accommodation at the Canton Road Government Offices had to be<br />
reconsidered.<br />
December 1999<br />
The CSB informed Heads of Department that the Government planned to<br />
outsource the medical examination services by July 2000.<br />
January 2000<br />
The DH informed the GPA and the CSB that, in view of the outsourcing of<br />
the medical examination services, the DH considered that it was not<br />
worthwhile to relocate the MEB to the CSWGO as originally planned. The<br />
ArchSD estimated that fitting-out works of $3.7 million completed for the<br />
MEB were rendered abortive.<br />
May 2000<br />
The ArchSD assessed that the prolongation cost arising from the allocation<br />
of CSWGO office space to another major user department would be<br />
$3.27 million.