XXI. WATER SUPPLY & SANITATION - Planning

XXI. WATER SUPPLY & SANITATION - Planning

XXI. WATER SUPPLY & SANITATION - Planning

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

4. STORM <strong>WATER</strong> DRAINAGE & ANTI FLOOD WORKS : (Rs. 80.00 lakh)<br />

In the 9 th Five Year Plan the work of construction of major drains was with the<br />

Delhi Jal Board. But the works of storm water drains have been transferred to MCD<br />

(General Wing).<br />

A provision of Rs. 80 lacs has been made in the Annual Plan 2004-2005. To<br />

complete contunued work/balance work and SW drains of Model town and Adarsh<br />

Nagar are to be carried out by DJB.<br />

List of major schemes/ works is given bellow at ANNEXURE – IV<br />

AN OUITLAY OF RS. 80.00 LAKH IS APPROVED FOR ANNUAL PLAN 2004-05.<br />

5. RENOVATION OF EXISTING PLANTS AND PUMPING STATIONS<br />

(Rs. 325.00 lakh)<br />

A provision of Rs. 325 Lacs has been made in the Annual Plan 2004-2005.<br />

Sewage Treatment Plants at Keshopur (12, 20 & 40 mgd), Okhla Old (30 + 12 +<br />

45 + 37 MGD) , Kondli (10 MGD), Coronation Pillar (10 + 20 MGD), Rithala (40 MGD)<br />

are quiet old. Similarly, the Sewage Pumping Stations at Kilokri, Ring Road, Keshopur,<br />

Haiderpuri, Jagriti and Preet Vihar, etc. are quiet old and require renovation. The<br />

buildings of these Sewage Pumping Stations and Sewage Treatment Plants as well as<br />

their staff quarters are very old and require renovation and refurbishment.<br />

List of major schemes/ works is given bellow at ANNEXURE – V<br />

An outlay of Rs. 325 lakh is approved for Annual Plan 2004-05.<br />