XXI. WATER SUPPLY & SANITATION - Planning
XXI. WATER SUPPLY & SANITATION - Planning XXI. WATER SUPPLY & SANITATION - Planning
New STPs : M/s TCE Consulting Engineers Ltd. have been entrusted with the study of up gradation of sewerage system for Delhi. The consultant have draft final report, according to which a sewage treatment capacity of 803.4MGD would be required by the year 2011. Work for construction of 45 MGD STP at Kondli and 25 MGD STP at Yamuna vihar are likely to begin in the year 2004-05. Ancillary Works : With the setting up of the new sewage treatment plants of additional capacity of 293 MGD, additional Pumping Stations at various places will also be required to be set up as per the reports of the consultant. Some of the Pumping Stations proposed to be set up are at Chilla (80 MGD), effluent pumping station at Yamuna Vihar (90 MGD). There are 3 Nos. of Gravity Ducts leading to Okhla STP from Kilokri/Ring Road Pumping Station. One of the Gravity Ducts does not function in full capacity. It is planned to take improvement works and also fencing to avoid encroachment of land. List of major schemes/ works is given bellow at ANNEXURE – II. AN OUTLAY OF RS. 9000.00 LAKH IS APPROVED FOR ANNUAL PLAN 2004-05. 3. RESIDENTIAL ACCOMMODATION, STORES, LAB , GO DOWN ,ETC. (RS.350.00 LAKH) A provision of Rs. 672 Lacs has been made in the Annual Plan 2004-2005 under this head. Many staff quarters are quite old and require rehabilitation and renovation besides construction of new offices, go-downs, stores & laboratories at Okhla, Keshopur Kilokari, and Coronation Pillar. List of major schemes/ works is given bellow at ANNEXURE – III An outlay of Rs. 350.00 lakh is approved for Annual Plan 2004-05. 36
4. STORM WATER DRAINAGE & ANTI FLOOD WORKS : (Rs. 80.00 lakh) In the 9 th Five Year Plan the work of construction of major drains was with the Delhi Jal Board. But the works of storm water drains have been transferred to MCD (General Wing). A provision of Rs. 80 lacs has been made in the Annual Plan 2004-2005. To complete contunued work/balance work and SW drains of Model town and Adarsh Nagar are to be carried out by DJB. List of major schemes/ works is given bellow at ANNEXURE – IV AN OUITLAY OF RS. 80.00 LAKH IS APPROVED FOR ANNUAL PLAN 2004-05. 5. RENOVATION OF EXISTING PLANTS AND PUMPING STATIONS (Rs. 325.00 lakh) A provision of Rs. 325 Lacs has been made in the Annual Plan 2004-2005. Sewage Treatment Plants at Keshopur (12, 20 & 40 mgd), Okhla Old (30 + 12 + 45 + 37 MGD) , Kondli (10 MGD), Coronation Pillar (10 + 20 MGD), Rithala (40 MGD) are quiet old. Similarly, the Sewage Pumping Stations at Kilokri, Ring Road, Keshopur, Haiderpuri, Jagriti and Preet Vihar, etc. are quiet old and require renovation. The buildings of these Sewage Pumping Stations and Sewage Treatment Plants as well as their staff quarters are very old and require renovation and refurbishment. List of major schemes/ works is given bellow at ANNEXURE – V An outlay of Rs. 325 lakh is approved for Annual Plan 2004-05. 37
- Page 1 and 2: XXI. WATER SUPPLY & SANITATION Sche
- Page 3 and 4: augmented to 469 MGD and 472 MGD re
- Page 5 and 6: 9. P/L C.I water line in Kanwar Sin
- Page 7 and 8: Tughlakabad Extn. (Rs. 2.91 lacs),
- Page 9 and 10: 55. Repl. Of 700m dia PSC damaged p
- Page 11 and 12: 100. P/L/J 750-450 mm dia Periphera
- Page 13 and 14: 3.8 lacs), Tughlakabad Extn. Gali N
- Page 15 and 16: the plants important machines inclu
- Page 17 and 18: connected UGR-cum-BPS at Palla and
- Page 19 and 20: 8 -do- in Seelampur Constituency at
- Page 21 and 22: An outlays of Rs. 490.00 lakh is ap
- Page 23 and 24: 11 For 800 mm dia inlet main for Vi
- Page 25 and 26: 21 Large scale testing of water sam
- Page 27 and 28: Augmentation of Water Supply in Meh
- Page 29 and 30: Trans Yamuna Area Development board
- Page 31 and 32: ) Industrial, commercial and commun
- Page 33 and 34: 12. Out of 44 Resettlement Colonies
- Page 35: trunk sewers due to widening of car
- Page 39 and 40: 8. SEWERAGE FACILITIES IN URBAN VIL
- Page 41 and 42: 4 Rehabilitation of 1600 mm dia Har
- Page 43 and 44: ANNEXURE - II B. SEWAGE TREATMENT P
- Page 45 and 46: 64. Shifting of rising main of Adar
- Page 47 and 48: 5 Desilting of Model Town RCC Drain
- Page 49 and 50: 13 Diversion of sewer main DDA Flat
- Page 51 and 52: 65 -do- in balance portion of Chand
- Page 53 and 54: Therefore, a systematic programme t
- Page 55 and 56: CPWD Nursery, Water Boosting Statio
- Page 57 and 58: officer of DJB. The applications so
New STPs :<br />
M/s TCE Consulting Engineers Ltd. have been entrusted with the study of up gradation<br />
of sewerage system for Delhi. The consultant have draft final report, according to which<br />
a sewage treatment capacity of 803.4MGD would be required by the year 2011. Work<br />
for construction of 45 MGD STP at Kondli and 25 MGD STP at Yamuna vihar are likely<br />
to begin in the year 2004-05.<br />
Ancillary Works :<br />
With the setting up of the new sewage treatment plants of additional capacity of<br />
293 MGD, additional Pumping Stations at various places will also be required to be<br />
set up as per the reports of the consultant. Some of the Pumping Stations proposed<br />
to be set up are at Chilla (80 MGD), effluent pumping station at Yamuna Vihar (90<br />
MGD). There are 3 Nos. of Gravity Ducts leading to Okhla STP from Kilokri/Ring<br />
Road Pumping Station. One of the Gravity Ducts does not function in full capacity.<br />
It is planned to take improvement works and also fencing to avoid encroachment of<br />
land.<br />
List of major schemes/ works is given bellow at ANNEXURE – II.<br />
AN OUTLAY OF RS. 9000.00 LAKH IS APPROVED FOR ANNUAL PLAN 2004-05.<br />
3. RESIDENTIAL ACCOMMODATION, STORES, LAB , GO DOWN ,ETC.<br />
(RS.350.00 LAKH)<br />
A provision of Rs. 672 Lacs has been made in the Annual Plan 2004-2005 under this<br />
head.<br />
Many staff quarters are quite old and require rehabilitation and renovation<br />
besides construction of new offices, go-downs, stores & laboratories at Okhla, Keshopur<br />
Kilokari, and Coronation Pillar.<br />
List of major schemes/ works is given bellow at ANNEXURE – III<br />
An outlay of Rs. 350.00 lakh is approved for Annual Plan 2004-05.<br />
36