augmented to 469 MGD and 472 MGD respectively. By the end of the 8 th five<br />

year plan i.e. 1992 – 97, water production was augmented to 580 MGD.<br />

During the 9 th five-year plan period, the water treatment capacity was<br />

proposed to be augmented to 945 MGD, but due to raw water constraints<br />

achievement upto the end of 9 th Five Year Plan was only 650 MGD.<br />

(ii)<br />

For bringing raw water for Okhla Water Treatment plant from Western<br />

Yamuna Canal, it has been decided to lay 2000 mm dia water main in a<br />

length of 11 km from Wazirabad to Haiderpur .<br />

(iii)<br />

For the first time in the Board, 140 MGD water treatment plant at Sonia Vihar<br />

is being executed on Design, Build, Operate basis with state of the art<br />

technology. The work has been awarded. On commissioning, the operation &<br />

maintenance period will be 10 years. The work has three components:<br />

1. Const. of 3250 mm dia conduit from Murad Nagar to Sonia Vihar<br />

2. Const. of 140 MGD W.T.P. at Sonia Vihar.<br />

3. P/L/Jointing of Transmission mains from Water Treatment Plants to different<br />

areas of Delhi.<br />

Raw water is to be drawn from the storage of Tehri Dam where 300 cusecs water<br />

has been reserved for Delhi. The work has been completed.<br />

The scheme wise details for Annual Plan 2004-05 are given submit:-<br />

3