XXI. WATER SUPPLY & SANITATION - Planning
XXI. WATER SUPPLY & SANITATION - Planning XXI. WATER SUPPLY & SANITATION - Planning
8 Maintenance of 1500mm effluent main from Okhla to Tilak bridge. An outlay of Rs. 15000.00 lakh has been approved for Annual Plan 2004-05 8. Rural Water supply (General) Rural water supply (MNP), RWS Special componentplan. (RS. 490.00 lakh) Delhi Jal Board is providing potable drinking water to 219 rural villages. However these villages are extended vertically as well as horizontally thereby creating additional demand of water every year. Under the special component plan, 413 Harijan Basties have also been covered. Under this scheme water supply is also provided to land less laborers (House sites) allotted by Delhi Administration and the to extended abadies under M.N.P. Under 20 Point progress, out of 57 such colonies, 20 Nos. has been provided with water supply and the remaining are being provided. Water supply is also being extended in the extended Lal Dora of the village. Provision has been made for improving, stabilizing and strengthening the rural water supply distribution system besides providing more filtered water in Kanjhawala and Najafgarh Blocks where ground water is increasingly becoming saline. To overcome the problem of low voltage at tube wells, voltage stabilizer and transformers are propose to be provided, presently, tube wells provided in rural areas have been drilled to about 50—60 meters depth. It is seen that the yield of these tube wells is declining. There is need to explore the possibility of deeper tube wells. In case of success is obtained in establishing a dependable source of water at that depth, to meet substantially the needs of rural areas. Small Underground Reservoir and Booster Pumping Stations are being constructed to rationalize and improve water pressure. The DJB is providing portable drinking water to the 20 point programme,plotholders,Harizen Rural W/S under PMGY Basties and the Rural areas where piped W/S is not available. Provisions is also being made to supply water in the extended Lal Dora of the Villages by improving, stabilizing and strengthening of Rural W/S distribution Systems besides [providing more filtered water supply in Narela Block, Badli Block & Bawana Block. 20
An outlays of Rs. 490.00 lakh is approved for Annual Plan 2004-05. 11. Rural Water supply under Basic Minimum Services/ P.M.G.Y The State Level Committee held on 27.12.2001 has cleared 16 estimates amounting to Rs. 247.88 lacs. These estimates have been found eligible for according administrative approval under P.M.G.Y Rural Drinking Water. These estimates are under the administrative approval of the Competent Authority. The state level committee clear the schemes under this head. The Schemes amounting to Rs.115 lacs has already been cleared and are under administrative approval/award for execution. Proposals/schemes worth Rs.55 lacs has also been sent for Delhi Govt. for release of funds under these scheme. A provision of Rs.235 lac was made in RBE 2003-04 and more such scheme will be taken up during 2004-05. However, no Outlay has been provided in 2004-05 as unspent balances are available with DJB. 12. Distribution mains and reservoirs for IInd 100 MGD WTP Haiderpur. (RS.1575.00 lakh) The following works will be taken up during the year 2004-05 1 Const. of UGR/BPS at Kirti Nagar. 2 Const of UGR/BPS at Mayapuri. 3 Const. of UGR/BPS at Bijwasan 4 P/L/J DI/MS water mains for builtup area under command of CT-2 Dwarka. 5 Const. of 5.30 ML UGR/BPS at Ujwa Najafgarh. 6 P/F barbed wire fencing for UGR/BPS at Ujwa. 7 P/L/J 800-600mm feeder main from Najafgarh to Ujwa. 8 Const .of R.R.stone masonary boundary wall at Ujwa. 9 Const of 5.2ML UGR/BPS at Daulat pur. 10 P/L/J 600mm dia water main from Kharkhari to Daulappur UGR. 11 Const of 21.4ML UGR/BPS at Pitam pura. 12 P/L/J feeder main (1200mm dia) for Pitampura. 13 Const. of 20ML UGR/BPS at Avantika. 21
- Page 1 and 2: XXI. WATER SUPPLY & SANITATION Sche
- Page 3 and 4: augmented to 469 MGD and 472 MGD re
- Page 5 and 6: 9. P/L C.I water line in Kanwar Sin
- Page 7 and 8: Tughlakabad Extn. (Rs. 2.91 lacs),
- Page 9 and 10: 55. Repl. Of 700m dia PSC damaged p
- Page 11 and 12: 100. P/L/J 750-450 mm dia Periphera
- Page 13 and 14: 3.8 lacs), Tughlakabad Extn. Gali N
- Page 15 and 16: the plants important machines inclu
- Page 17 and 18: connected UGR-cum-BPS at Palla and
- Page 19: 8 -do- in Seelampur Constituency at
- Page 23 and 24: 11 For 800 mm dia inlet main for Vi
- Page 25 and 26: 21 Large scale testing of water sam
- Page 27 and 28: Augmentation of Water Supply in Meh
- Page 29 and 30: Trans Yamuna Area Development board
- Page 31 and 32: ) Industrial, commercial and commun
- Page 33 and 34: 12. Out of 44 Resettlement Colonies
- Page 35 and 36: trunk sewers due to widening of car
- Page 37 and 38: 4. STORM WATER DRAINAGE & ANTI FLOO
- Page 39 and 40: 8. SEWERAGE FACILITIES IN URBAN VIL
- Page 41 and 42: 4 Rehabilitation of 1600 mm dia Har
- Page 43 and 44: ANNEXURE - II B. SEWAGE TREATMENT P
- Page 45 and 46: 64. Shifting of rising main of Adar
- Page 47 and 48: 5 Desilting of Model Town RCC Drain
- Page 49 and 50: 13 Diversion of sewer main DDA Flat
- Page 51 and 52: 65 -do- in balance portion of Chand
- Page 53 and 54: Therefore, a systematic programme t
- Page 55 and 56: CPWD Nursery, Water Boosting Statio
- Page 57 and 58: officer of DJB. The applications so
An outlays of Rs. 490.00 lakh is approved for Annual Plan 2004-05.<br />
11. Rural Water supply under Basic Minimum Services/ P.M.G.Y<br />
The State Level Committee held on 27.12.2001 has cleared 16 estimates amounting<br />
to Rs. 247.88 lacs. These estimates have been found eligible for according<br />
administrative approval under P.M.G.Y Rural Drinking Water. These estimates are<br />
under the administrative approval of the Competent Authority.<br />
The state level committee clear the schemes under this head. The Schemes<br />
amounting to Rs.115 lacs has already been cleared and are under administrative<br />
approval/award for execution. Proposals/schemes worth Rs.55 lacs has also been<br />
sent for Delhi Govt. for release of funds under these scheme.<br />
A provision of Rs.235 lac was made in RBE 2003-04 and more such scheme will be<br />
taken up during 2004-05. However, no Outlay has been provided in 2004-05 as unspent<br />
balances are available with DJB.<br />
12. Distribution mains and reservoirs for IInd 100 MGD WTP Haiderpur.<br />
(RS.1575.00 lakh)<br />
The following works will be taken up during the year 2004-05<br />
1 Const. of UGR/BPS at Kirti Nagar.<br />
2 Const of UGR/BPS at Mayapuri.<br />
3 Const. of UGR/BPS at Bijwasan<br />
4 P/L/J DI/MS water mains for builtup area under command of CT-2 Dwarka.<br />
5 Const. of 5.30 ML UGR/BPS at Ujwa Najafgarh.<br />
6 P/F barbed wire fencing for UGR/BPS at Ujwa.<br />
7 P/L/J 800-600mm feeder main from Najafgarh to Ujwa.<br />
8 Const .of R.R.stone masonary boundary wall at Ujwa.<br />
9 Const of 5.2ML UGR/BPS at Daulat pur.<br />
10 P/L/J 600mm dia water main from Kharkhari to Daulappur UGR.<br />
11 Const of 21.4ML UGR/BPS at Pitam pura.<br />
12 P/L/J feeder main (1200mm dia) for Pitampura.<br />
13 Const. of 20ML UGR/BPS at Avantika.<br />
21