<strong>Sensys</strong> <strong>Stud</strong> <strong>Trial</strong><br />

5. The sensor will was placed flat in the centre of the hole with the arrow pointing in the<br />

direction of traffic.<br />

6. The holes were then filled with epoxy up to a level 20mm above the sensor.<br />

7. The filler material ‘EZ Street Cold Asphalt’ was then used to fill the remainder of the<br />

hole which was then compacted to road level.<br />

8. The closure was then removed. The whole operation for four studs in 2 lanes took<br />

less than 1 hour. Another semi-static closure was then installed in the 3 rd lane to<br />

install the remaining studs.<br />

Commercial in Confidence Page 15