ESA/REG/001, rev.2 Page 46 ARTICLE 30 - CLARIFICATIONS AND AMENDMENTS OF INVITATION TO TENDER 1. If justified by its complexity, briefing meetings where the requirements of the Invitation To Tender are described and explained can be called before or shortly after the Invitation To Tender is issued. The invitation to attend such briefing meetings and the subsequent questions submitted and answers given during these briefing meetings, shall be communicated simultaneously to all Potential Bidders concerned on the same date in a manner identical with that applicable in respect of the original or forthcoming Invitation To Tender’s publication. 2. Once the Invitation To Tender is issued and before the closing date for the submission of tenders, the Agency may clarify and/or amend the Invitation To Tender either following requests from economic operators or at its own initiative. 3. Only requests submitted in writing and concerning the understanding of the Invitation To Tender’s requirements will be answered. 4. The only authorised point of contact for the Agency before the closing date for the submission of tenders shall be the Contracts Officer designated in the Invitation To Tender, or in his absence any other Contracts Officer designated by the Procurement Department. 5. In all cases, such clarifications and/or amendments will: a) be subject to the approval of the Tender Evaluation Board’s Chairman prior to their publication; b) contain both the original question and answer when applicable without identifying the source of the request; c) be communicated within a reasonable time period prior to the closing date; and d) be communicated simultaneously to all Potential Bidders concerned on the same date and in a manner identical with that applicable in respect of the original Invitation To Tender ‘s publication.
ESA/REG/001, rev.2 Page 47 ARTICLE 31 - SUSPENSION OF THE PROCUREMENT PROCESS 1. The Director General may at any time suspend the procurement process related to an Invitation To Tender. 2. Upon resumption of the process, due account shall be taken of the period of suspension with respect to the time limits prescribed under Articles 29 and 37 of these Regulations and of any other elements entailed by such suspension the effect of which could impair the principles of transparency and fair and equitable treatment of economic operators. 3. Potential Bidders shall be informed simultaneously of any suspension and subsequent resumption in a manner identical with that applicable in respect of the original Invitation To Tender’s publication.
- Page 1 and 2: ESA UNCLASSIFIED - Releasable to th
- Page 3 and 4: ESA/REG/001, rev.2 Page 3 EUROPEAN
- Page 5 and 6: ESA/REG/001, rev.2 Page 5 PART III
- Page 7 and 8: ESA/REG/001, rev.2 Page 7 ANNEXES I
- Page 9 and 10: ESA/REG/001, rev.2 Page 9 PART I: G
- Page 11 and 12: ESA/REG/001, rev.2 Page 11 Tender E
- Page 13 and 14: ESA/REG/001, rev.2 Page 13 ARTICLE
- Page 15 and 16: ESA/REG/001, rev.2 Page 15 3. The A
- Page 17 and 18: ESA/REG/001, rev.2 Page 17 by the A
- Page 19 and 20: ESA/REG/001, rev.2 Page 19 ARTICLE
- Page 21 and 22: ESA/REG/001, rev.2 Page 21 ARTICLE
- Page 23 and 24: ESA/REG/001, rev.2 Page 23 ARTICLE
- Page 25 and 26: ESA/REG/001, rev.2 Page 25 PART II:
- Page 27 and 28: ESA/REG/001, rev.2 Page 27 ARTICLE
- Page 29 and 30: ESA/REG/001, rev.2 Page 29 If provi
- Page 31 and 32: ESA/REG/001, rev.2 Page 31 PART III
- Page 33 and 34: ESA/REG/001, rev.2 Page 33 ARTICLE
- Page 35 and 36: ESA/REG/001, rev.2 Page 35 ARTICLE
- Page 37 and 38: ESA/REG/001, rev.2 Page 37 ARTICLE
- Page 39 and 40: ESA/REG/001, rev.2 Page 39 PART IV
- Page 41 and 42: ESA/REG/001, rev.2 Page 41 ARTICLE
- Page 43 and 44: ESA/REG/001, rev.2 Page 43 2. For r
- Page 45: ESA/REG/001, rev.2 Page 45 ARTICLE
- Page 49 and 50: ESA/REG/001, rev.2 Page 49 ARTICLE
- Page 51 and 52: ESA/REG/001, rev.2 Page 51 10. When
- Page 53 and 54: ESA/REG/001, rev.2 Page 53 ARTICLE
- Page 55 and 56: ESA/REG/001, rev.2 Page 55 ARTICLE
- Page 57 and 58: ESA/REG/001, rev.2 Page 57 ARTICLE
- Page 59 and 60: ESA/REG/001, rev.2 Page 59 ARTICLE
- Page 61 and 62: ESA/REG/001, rev.2 Page 61 b) where
- Page 63 and 64: ESA/REG/001, rev.2 Page 63 ARTICLE
- Page 65 and 66: ESA/REG/001, rev.2 Page 65 PART VI:
- Page 67 and 68: ESA/REG/001, rev.2 Page 67 ARTICLE
- Page 69 and 70: ESA/REG/001, rev.2 Page 69 ARTICLE
- Page 71 and 72: ESA/REG/001, rev.2 Page 71 ARTICLE
- Page 73 and 74: ESA/REG/001, rev.2 Page 73 ARTICLE
- Page 75 and 76: ESA/REG/001, rev.2 Page 75 ARTICLE
- Page 77 and 78: ESA/REG/001, rev.2 Page 77 PART VII
- Page 79 and 80: ESA/REG/001, rev.2 ANNEXES ANNEXES
- Page 81 and 82: ESA/REG/001, rev.2 Annex I,rev.1 AN
- Page 83 and 84: ESA/REG/001, rev.2 Annex I,rev.1 Pa
- Page 85 and 86: ESA/REG/001, rev.2 Annex I,rev.1 Pa
- Page 87 and 88: ESA/REG/001, rev.2 Annex I,rev.1 Pa
- Page 89 and 90: ESA/REG/001, rev.2 Annex I,rev.1 Pa
- Page 91 and 92: ESA/REG/001, rev.2 Annex I,rev.1 Pa
- Page 93 and 94: ESA/REG/001, rev.2 Annex II, rev.1
- Page 95 and 96: ESA/REG/001, rev.2 Annex II,rev.1 P
<strong>ESA</strong>/REG/001, rev.2<br />
Page 47<br />
<strong>ARTICLE</strong> 31 -<br />
SUSPENSION OF THE PROCUREMENT PROCESS<br />
1. The Director General may at any time suspend the procurement process related to an<br />
Invitation To Tender.<br />
2. Upon resumption of the process, due account shall be taken of the period of suspension<br />
with respect to the time limits prescribed under Articles 29 and 37 of these Regulations<br />
and of any other elements entailed by such suspension the effect of which could impair<br />
the principles of transparency and fair and equitable treatment of economic operators.<br />
3. Potential Bidders shall be informed simultaneously of any suspension and subsequent<br />
resumption in a manner identical with that applicable in respect of the original<br />
Invitation To Tender’s publication.