<strong>ESA</strong>/REG/001, rev. 2<br />

Annex III,rev.1<br />

Page 83<br />

i. eliminate the proposal(s) having received one or more mark below 40;<br />

ii.<br />

proceed in applying the weighting factors only to the proposal or those<br />

proposals marked acceptable under all evaluation criteria;<br />

iii. make its overall assessment and recommendation pursuant to paragraph 6.7<br />

below; and,<br />

iv.<br />

finalise its final report and have it signed by all members.<br />

6.5.2 If as a result of the marking all of the proposals received are marked below 40<br />

under one or more criteria, the TEB shall not apply the weighting factors, close the<br />

evaluation and draw up its final report. In such a case:<br />

i. the Chairperson of the TEB shall submit the report to the Initiating Authority<br />

and to the Head of the local procurement division/service for decision on<br />

whether to re-issue the RFP;<br />

ii.<br />

The decision and the reasons therefore shall be recorded by the Contract officer<br />

in the contract file.<br />

6.6 Application of weighting factors<br />

6.6.1 Once the TEB has proceeded with its marking (paragraph 6.5.1 above) the TEB<br />

shall proceed in applying the weighting factors.<br />

6.6.2 The result of such application will be weighted marks which shall also be filled<br />

into the marking sheets together with their respective aggregate for each proposal.<br />

6.7 Overall assessment of proposals and finalisation of recommendation<br />

6.7.1 Following the application of the weighting factors the TEB shall proceed with an<br />

overall assessment of the proposals taking into consideration:<br />

i. the weighted marks 30 ,<br />

ii. when established in the RFP at the time of its issuing the industrial policy<br />

measures and/or the geographical return requirements ,<br />

iii. any other requirements provided they were clearly indicated as such in the<br />

RFP.<br />

6.7.2 The TEB Chairperson who is responsible for the correct proceedings of the board<br />

shall guide the discussion in such a way that any possible significant differences of<br />

opinion may be reduced, or if this is not possible, that they are clearly identified and<br />

recorded.<br />

30 Where it is established in the Framework Agreement or in the RFP that no Work Order will be<br />

attributed to framework contractors the proposals of which have not obtained a certain overall weighted<br />

mark ( e.g ≥ 60) such proposals shall be eliminated from further evaluation.