<strong>ESA</strong>/REG/001, rev. 2<br />

Annex III,rev.1<br />

Page 67<br />

The above notification shall comprise a summary of the findings of the TEB together<br />

with the associated marks.<br />

8.3 Debriefing to unsuccessful Tenderer<br />

8.3.1 Within 10 calendar days following the receipt of the notification foreseen under<br />

paragraph 8.2, the Tenderer may require from the Contract officer an oral debriefing<br />

explaining the reasons why his tender was not successful.<br />

8.3.2 Such a debriefing shall in principle take place at the Agency premises - unless<br />

otherwise decided by the Agency - and shall be given by the concerned Contract officer<br />

(or in case of unavailability, by another Contract officer designated by his hierarchy)<br />

and Technical officer at a date to be agreed with the Tenderer.<br />

As a matter of guidance, such debriefing should be given within 20 calendar days from<br />

the date of receipt by the Agency of the formal written request.<br />

8.3.3 For procurements which have been the subject of a submission to the IPC, the<br />

TEB Chairperson shall participate in the debriefing.<br />

8.3.4 Explanations shall be limited to the findings of the TEB.<br />

8.3.5 Minutes of the debriefing meeting shall be drafted by the Contract officer and<br />

shall be signed by him and the representative of the unsuccessful Tenderer. The original<br />

shall be placed in the contract file of the procurement.