7.7 Overall assessment of tender and finalisation of recommendation<br />

7.7.1 The TEB shall proceed with an overall assessment of the tender taking into<br />

consideration the price and when established in the RFQ at the time of its issuing the<br />

industrial policy measures and/or the geographical return requirements.<br />

7.7.2 The TEB Chairperson shall guide the discussion in such a way that any possible<br />

significant differences of opinion may be reduced, or if this is not possible, that they are<br />

clearly identified and recorded.<br />

7.7.3 As a result of the overall assessment of the tender, the TEB shall make a final<br />

recommendation for awarding the contract to the Tenderer.<br />

For RFQs superior or equal to 20 000 000 Euro a final recommendation for awarding<br />

the contract can only be made if the Tenderer has obtained a minimum overall<br />

weighted mark of at least sixty (60).<br />

7.7.4 The TEB shall also identify the main items that would require negotiation with<br />

the Tenderer prior to the placing of a contract and such findings shall be clearly<br />

identified in its report.<br />

7.7.5 The TEB may make in its final report any other remark it considers relevant to the<br />

evaluation.<br />

7.8 Submission of the final evaluation report for decision<br />

7.8.1 Pursuant to Article 42.4 of the Procurement Regulations, the Technical officer<br />

shall submit the final evaluation report to the Initiating Authority and to the Head of the<br />

local procurement division/ service for joint decision by attaching the scanned copy of<br />

the original final report signed by the TEB members to the appropriate electronic form.<br />

7.8.2 In order to help them in their decision the Initiating Authority and/or the Head of<br />

the local Procurement division/ service may require a copy of the tender.<br />

7.8.3 At this stage, the TEB Chairperson together with the Contract officer shall give an<br />

oral report to the Director General, the initiating Director, the Initiating Authority, the<br />

Appointing Authority and to the Head of the local Procurement division/ service, when<br />

required by them. This shall be recorded in the contract file.<br />

7.9 Referral of the final report back to the TEB<br />

Exceptionally, in case of doubt as to the correctness or completeness of the evaluation,<br />

the Initiating Authority and/or the Head of the local Procurement division/ service may<br />

refer the matter back to the TEB Chairperson and Contract officer in writing with their<br />

detailed comments for further evaluation by the TEB; they shall, however, not direct<br />

changes to evaluation criteria, or marks.