<strong>ESA</strong>/REG/001, rev.2<br />

Annex III,rev.1<br />

Page 64<br />

7.4.8 Where prior to the attribution of marks it was decided by the TEB to mark by<br />

consensus, any member who at the time of the marking cannot agree with the proposed<br />

consensus marking shall specifically state why he disagrees on which criterion, and this<br />

shall be recorded in the minutes by the Contract officer.<br />

In the latter case the marking shall be performed individually.<br />

7.4.9 When the Chairperson of the TEB is satisfied that further discussion will not lead<br />

to a reduction of any discrepancies, the marks shall be officially recorded on the<br />

marking sheets. Marks once thus recorded cannot be changed.<br />

7.5 Assessment of results following the marking<br />

7.5.1 If as a result of the marking the tender is marked acceptable (i.e. ≥ 40 under all<br />

evaluation criteria), the TEB shall:<br />

i. proceed in applying the weighting factors when applicable;<br />

ii. make its overall assessment and recommendation pursuant to paragraph 7.6<br />

below; and,<br />

iii.<br />

finalise its final report and have it signed by all members.<br />

7.5.2 If as a result of the marking the tender has received marks below 40 under one or<br />

more criteria, the TEB shall not apply the weighting factors when applicable, close the<br />

evaluation and draw up its final report. In such a case:<br />

i. the Chairperson of the TEB shall submit the report to the Initiating Authority<br />

and to the Head of the Procurement Department or the person to whom he has<br />

delegated his authority for their decision on whether to re-issue the RFQ; and,<br />

ii.<br />

The decision and the reasons therefore shall be recorded by the Contract officer<br />

in the contract file.<br />

7.6 Application of weighting factors for tender actions superior or equal to<br />

20 000 000 Euro<br />

Once the TEB has proceeded with its marking (paragraph 7.5.1 above ), it shall proceed<br />

with the application of the weighting factors.<br />

The result of such application will be weighted marks which shall also be filled into the<br />

marking sheets together with their respective aggregate.