<strong>ESA</strong>/REG/001, rev.2<br />

Annex III,rev.1<br />

Page 32<br />

1.4.4 Weighting factors<br />

i. The TEB shall attribute weighting factors against each of the evaluation criteria<br />

it establishes.<br />

ii.<br />

iii.<br />

iv.<br />

Weighting factors shall not create an unfair advantage to one economic operator<br />

over another.<br />

The total of the weighting factors spread over the evaluation criteria and subcriteria,<br />

if any, shall add up to 100%.<br />

The weighting factors to be applied for the evaluation shall be published at the<br />

time of the issuing of the ITT.<br />

1.4.5 Handling of approved evaluation criteria, sub criteria and weighting<br />

factors<br />

Approval of the evaluation criteria, sub-criteria, if any, and their corresponding weighting<br />

factors shall be the subject of a separate item in the records of the TEB.<br />

1.5 Establishment of the calendar<br />

Based on the proposal made by the Joint Secretaries, the TEB shall establish the<br />

calendar and schedule of its next meetings - and that of the tender evaluation panel(s)<br />

where appointed - up to the recommendation.<br />

1.5.1 General<br />

Considering that all initiating Directorates/Departments should produce a<br />

comprehensive Procurement Plan with the objective of an even flow of actual<br />

procurement actions, the TEB Chairperson when establishing the time-schedule for the<br />

tender action shall ensure that such schedule is compatible with the pertaining Internal<br />

Procurement Plan established by the Initiating Department in association with the<br />

Procurement Department.<br />

1.5.2 Proposal for time schedule<br />

The TEB Chairperson shall establish in consultation with the other members a calendar<br />

of meetings for the TEB further actions up to the recommendation, it being understood<br />

that the time-limits for the tendering period established in conformity with the<br />

provisions of Article 29.3 of the Procurement Regulations is not less than:<br />

i. 30 working days from the date of publication or dispatch of the ITT for<br />

procurement actions superior or equal to 300 000 Euro.<br />

ii.<br />

20 working days from the date of publication or dispatch of the ITT for all<br />

other procurement actions provided such period would not create an unfair<br />

advantage to the benefit of one or more economic operators.