March 09<br />
damaged prior to fitting a GASMIZER system by closing the bell exhaust valve with the<br />
dive control exhaust valve open.<br />
3. Suitable locations for the Reprocessing Unit, Electric Gas Booster, Volume Tank,<br />
Control Console <strong>and</strong> Bell Equipment should also be identified during this preliminary<br />
survey.<br />
8.2.2 Equipment Installation <strong>and</strong> Interconnection<br />
There are essentially five items of equipment to be accommodated.<br />
Reprocessing Unit Ideally should be sited in a compressor room or other machinery<br />
space.<br />
Electric Gas Booster Ideally should be sited close to the reprocessing unit for ease of<br />
installation <strong>and</strong> also to reduce pressure losses between the units.<br />
Volume Tank Siting is non-critical. It can be either beside the reprocessing unit or,<br />
alternatively in the ship’s gas storage area.<br />
Bell Equipment Should be mounted in the bell as close as possible to diver gas supply<br />
pressure gauge <strong>and</strong> shut-off valve. The bellman should have easy access to the water<br />
trap.<br />
Control Panel Should be mounted in a prominent position in dive control. During diving,<br />
the volume tank pressure <strong>and</strong> BPR pressure are probably the two most important<br />
gauges for the dive supervisor.<br />
The system may be installed with rigid stainless or tungum pipework (apart from O 2<br />
pipework which will be copper or tungum). Installations will be purged to remove all<br />
swarf, cuttings etc. <strong>and</strong> O 2 cleaned after installation.<br />
8.2.3 Commissioning<br />
The following steps should be carried out after installation:<br />
1. Pressurise system <strong>and</strong> check for leaks.<br />
2. Carry out hydraulic/pneumatic pressure testing as required by client. It is<br />
recommended that the system be tested to its full working pressure.<br />
Gas Supply System<br />
Gas Exhaust System<br />
O 2 System<br />
Full working pressure 100 bar (1500 psi)<br />
Full working pressure 68 bar (1000 psi)<br />
Full working pressure 50 bar (725 psi)<br />
3. Purge the system by pressurising with desired heliox mix to 10 bar using the<br />
make- up panel <strong>and</strong> vent to atmospheric pressure. Connect O 2 supply to Reprocessing<br />
Unit by opening isolating valve.<br />
4. Check that exhaust <strong>and</strong> supply umbilical as fitted comply with the table shown<br />
below for the proposed diving depth.<br />
OM002 Rev 5 Page 76 of 168 Chap 8