28.12.2014 Views

Gasmizer Manual - Submarine Manufacturing and Products Ltd

Gasmizer Manual - Submarine Manufacturing and Products Ltd

Gasmizer Manual - Submarine Manufacturing and Products Ltd

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

March 2009<br />

CHAPTER 8<br />

SYSTEM INSTALLATION AND OPERATION<br />

CONTENTS<br />

Page<br />

Introduction.................................................................................................................................. 75<br />

System Installation....................................................................................................................... 75<br />

System Start- Up <strong>and</strong> Operating Procedure ................................................................................ 77<br />

GASMIZER BELL CARD............................................................................................................. 79<br />

GASMIZER BELL CARD - ONE OR TWO DIVERS.................................................................... 81<br />

REGULATOR SETTING GUIDELINES – 1 DIVER ..................................................................... 89<br />

REGULATOR SETTING GUIDELINES – 2 DIVERS................................................................... 91<br />

System Operation at Extreme Depths ......................................................................................... 93<br />

Fault Finding................................................................................................................................ 94<br />

List of Figures<br />

1 GASMIZER BELL EQUIPMENT ONE DIVER ........................................................................................ 80<br />

2 GASMIZER BELL EQUIPMENT ONE OR TWO DIVERS ...................................................................... 82<br />

8.1 Introduction<br />

The purpose of this section of the manual is to describe in detail the procedures<br />

necessary to install a new GASMIZER system <strong>and</strong> to describe the detailed set-up <strong>and</strong><br />

operating procedure.<br />

8.2 System Installation<br />

8.2.1 Prior to Installation<br />

A preliminary survey should be carried out prior to despatch of a system to answer the<br />

following questions:<br />

1. Are the necessary services available<br />

Control Console, Power 220/240 Vac 50/60 Hz<br />

Reprocessing Unit, freshwater cooling, 3 gal/min (13 ltr/min) @ 45 o F (7 o C max.)<br />

Electric Gas Booster, power 440V, 3ph, 60 Hz, (30 Kw), seawater cooling 16 gal/min<br />

(70 ltr/min @ 80 o F (30 o C)<br />

2. Does the bell umbilical have a suitable exhaust hose – Refer to Table 8.2.4 for<br />

then exhaust hose diameter as a function of diving depth. Note that the exhaust hose<br />

must be suitable for at least 5 bar external pressure. Exhaust hoses are frequently<br />

Chap 8 Page 75 of 168 OM002 Rev 5