March 2009<br />

9.2 Booster Starter Control Box<br />

9.2.1 Motor Control The motor control circuit has a local <strong>and</strong> remote selector switch, with<br />

local <strong>and</strong> remote emergency stop-lock <strong>and</strong> start switches <strong>and</strong> mains indicator lights. The motor<br />

is wired in a star-delta configuration, starting in a star connection <strong>and</strong> changing to delta<br />

connection after approximately 8 seconds. Upon starting the booster running light illuminates<br />

<strong>and</strong> hours of running are recorded on an hour meter.<br />

9.2.2 Moisture Dump/Unloaders Upon starting the booster, a timer T1 sets the period that<br />

the booster runs unloaded <strong>and</strong> dumping moisture. T1 is pre-set, usually to 10 seconds<br />

(maximum 30 seconds). A second timer T2 sets the period between unloading during running .<br />

T1 additionally controls the initial period that the booster runs unloaded <strong>and</strong> dumping moisture.<br />

9.2.3 Main Fuse Switch <strong>and</strong> the Reset Button The main switch isolates the compete circuit<br />

from the power supply. After switching on, the reset button must be pressed <strong>and</strong> the fault lights<br />

extinguished before the motor can be started.<br />

9.2.4 Fault Lights The fault lights indicate low oil pressure, high gas temperature, <strong>and</strong> high<br />

gas pressure. In the event of low oil pressure, or high gas temperature/pressure in the 1 st or 2 nd<br />

stages the appropriate switch will open <strong>and</strong> stop the booster. The particular fault will be<br />

indicated locally on the control panel, but remotely only one fault light exists.<br />

9.3 Storage<br />

9.3.1 The booster is normally supplied uninhibited. If there is likely to be a long delay<br />

between installation <strong>and</strong> commissioning (in excess of six months) it can be inhibited prior to<br />

delivery. Consideration must also be given to this if the system is to be unused for a significant<br />

period (see chart overleaf)<br />

Inhibiting Oils (Always follow the oil suppliers instructions)<br />

Make<br />

9.3.2 Inhibiting Chart<br />

Inhibiting Oil<br />

Shell Ensis Oil 30<br />

BP Protective Engine Oil 30<br />

Esso Rustban 396<br />

Die-inhibiting Procedures – see chart overleaf.<br />

Period (months) Anticipated Conditions Procedure<br />

1-6 Normally Dry Seal off all openings to booster with<br />

suitable tape<br />