• How do I Apply for a Conditional Use Zoning Certificate<br />
An application for conditional use zoning certificate shall be accompanied by site plans, structural<br />
details and additional information as outlined in the attached checklist. The completed<br />
application packet and application fee shall be filed directly with the Board of Zoning Appeals.<br />
You may schedule an appointment with the Administrator of the Board if you have questions or<br />
wish to further discuss details of a case prior to submission. Requests for variance of a yard, bulk<br />
or parking standard must be clearly stated in the letter of application as submitted to the Board.<br />
Requests for modification of a streetscape or boundary buffer standard must be approved by<br />
the Rural Zoning Commission prior to action by the Board of Zoning Appeals. These<br />
applications and a more complete explanation of this process is contained in the User’s Guide<br />
titled “Buffer Yards and General Landscape Standards”. Please request the information if it is<br />
not already included with this document.<br />
• What are the Processing <strong>Procedures</strong> for a Conditional Use<br />
Minimum processing time for a Conditional Use Zoning Certificate is typically 62 days.<br />
a) Within 5 days after filing a complete application, the BZA Administrator sets a public<br />
hearing for between 30 and 62 days from that date.<br />
b) A copy of the application is transmitted to the Regional <strong>Planning</strong> Commission for staff<br />
review and recommendation.<br />
c) Within 20 days after filing a complete application, a staff report with a recommendation<br />
is sent to the BZA.<br />
d) The BZA Administrator sends notice of the public hearing at least 10 days prior to such<br />
hearing to the applicant, Township and property owners within 200 ft. A legal<br />
advertisement is published in a local county newspaper.<br />
e) BZA takes action within 21 days after public hearing.<br />
f) If the application is approved:<br />
1) Applicant must apply to the Rural Zoning Commission for a Zoning Certificate.<br />
Upon issuance, the Conditional Use Zoning Certificate is valid for a period no longer<br />
than one year unless a building permit has been issued or BZA has granted a time<br />
extension.<br />
2) Applicant applies to the Building Department for a Building Permit.<br />
g) When the development is complete:<br />
1) Applicant must file an affidavit of compliance with required conditions when<br />
development completed.<br />
2) A Final Zoning Inspection Certificate will be issued by the Zoning Field Inspector.<br />
For additional information contact the <strong>Hamilton</strong> <strong>County</strong> Rural Zoning Commission located in<br />
Room 804 of the <strong>County</strong> Administration Building, 138 E. Court Street, Cincinnati, <strong>Ohio</strong> 45202,<br />
513-946-4501 (FAX) 513-946-4475.