2004 Highlights<br />

Mine 48 million tonnes ex-pit (waste and ore)<br />

Mill 19.1 million tonnes of ore<br />

300,000 oz gold production<br />

75 million lbs copper production<br />

Cash Cost of $206/oz (US) or less ($180/oz using Gold Institute method)<br />

Complete Kemess <strong>North</strong> feasibility study early in 2 nd Quarter<br />

<strong>Exploration</strong> expenditures of $2 million in local area<br />

Speed up second SAG mill, install second Trommel magnet and complete phase II of Wemco cell<br />

retrofit<br />

Replace 23 yd Hitachi EX3500 with a 40 yd Hitachi EX5500<br />

Total Capital Expenditures of $16.9 million (incl. $6.1 million for tailings dam construction)