Appendix C - Cultural Heritage Impact Assessment - Peabody Energy

Appendix C - Cultural Heritage Impact Assessment - Peabody Energy Appendix C - Cultural Heritage Impact Assessment - Peabody Energy

peabodyenergy.com
from peabodyenergy.com More from this publisher
26.11.2014 Views

Cultural Heritage Impact Assessment North Wambo Underground Mine Modification While impacts to archaeological and cultural heritage within the MA are predicted to be negligible to low (MSEC 2012), it is recommended that, if required, Wambo Coal seek an AHIP under Section 90 of the NSW National Parks and Wildlife Act, 1974 (NPW Act) to allow for subsidence movements and the salvage of registered and unregistered sites (should they be uncovered) in consultation with the relevant Aboriginal parties. If salvage is required it is recommended that artefacts be transferred to the temporary keeping place under the existing Care and Control Permit (#3130) in consultation with the relevant Aboriginal parties. Subsidence estimates for the project area (including specific predictions for Aboriginal sites) have been provided by MSEC (2012). Much of the surrounding area has also been previously undermined (Wollemi and Homestead workings in the Whybrow Seam), or approved to be undermined, including NWUM in the Wambo Seam, the Arrowfield and the Bowfield Seams. The NWUMM longwall area will be subject to a Subsidence Management Plan or Extraction Plan which will be implemented prior to the proposed works being undertaken. MSEC (2012:58-60) calculated the maximum predicted total conventional subsidence parameters for the archaeological sites in the MA for approved mining of the Wambo, Arrowfield and Bowfield Seams (Approved Layout) and compared them to the predicted values for the proposed NWUMM (Modified Layout). The predicted maximum incremental changes in subsidence resulting from the proposed modification at any Aboriginal site ranged from 0mm to 2400mm; in tilt ranged from 0mm/m to 35 mm/m; in hogging curvature ranged from 0 km -1 to 1.50 km -1 ; and in sagging curvature ranged from 0 km -1 to 1.90 km -1 (MSEC [2012:58- 60, Table D01]). Further MSEC (2012: Table D01) predicted that although the maximum subsidence effects in the vicinity of known Aboriginal sites resulting from subsidence relating to the Modified Layout could vary between 350 mm and 6400 mm (35 cm and 640 cm) the actual incremental change between the Modified Layout and the previously Approved Layout varied between 0 mm and 2400 mm (0 cm and 240 cm). This increment would be an even smaller proportion of approved subsidence impacts if the historic workings (Whybrow Seam) were also included in the subsidence model. As such, MSEC (2012) predicted that the subsidence effects in the vicinity of known Aboriginal sites would not exceed 2400 mm and was significantly lower for the majority of Aboriginal sites ranging from 0 mm to 2400 mm (0 cm to 240 cm). MSEC (2012:59) considered that the artefact sites in the MA could potentially be affected by cracking of the surface soils. It is unlikely that the Aboriginal objects at these sites would be destroyed by the surface cracking but could be impacted on or harmed by downward movement due to vertical subsidence (whereby the land surface moves downwards as a whole). However, compared to the existing and approved mining in this area, the NWUMM would not increase the risk of impacts to these sites. The Wollemi National Park escarpment cliff lines and steep talus slopes are more than one kilometre from the NWUMM area and are outside of the predicted subsidence impact area (MSEC 2012). As such, the proposed modification will not impact on the Wollemi National Park or the associated escarpment. Wollombi Brook lies approximately 500 m to the east of the project area and 1 km from any Aboriginal sites within the NWUMM area. Wollombi Brook will not be impacted by the proposed NWUMM (MSEC 2012). The existing Consent #2222 (Consent to Destroy with Salvage) covers the vast majority of the MA. It is therefore recommended that either the existing Consent be slightly expended or a new AHIP be applied for to cover the southern extent of the MA. 108453-2; October 2012 Page 53

Cultural Heritage Impact Assessment North Wambo Underground Mine Modification Table 18 Summary of potential impacts, risks to heritage and mitigation options Impact Risk to Heritage Mitigation Option 1 Mine Subsidence Vehicle Movement/ Subsidence Mitigation Works Surface Infrastructure Vandalism Based on the subsidence predictions for surface movement and potential soil cracking in MSEC (2012) (and provided in Table 17), risk of substantial impacts to Aboriginal heritage is considered negligible to low. Direct disturbance/ damage to cultural heritage sites. Direct disturbance/ damage to cultural heritage sites. Direct disturbance/ damage to cultural heritage sites. Subsidence monitoring to ensure subsidence movements are as predicted (details to be included in a Subsidence Management Plan) Avoid; ensure relevant Wambo Coal Environmental Officer and personnel are given site locations. Avoid; locate subsidence mitigation works to prevent impacts on Aboriginal cultural heritage. Locate required surface infrastructure within limit of existing approved disturbance areas. Avoid impact to known heritage sites; ensure Wambo Coal Environmental Officer and relevant personnel. Avoid; ensure Wambo Coal Environmental Officer and relevant personnel are given site locations. 8.2 Principles of Ecologically Sustainable Development Mitigation Option 2 Move artefacts under an AHIP to location outside impact area if subsidence monitoring identifies cracking or erosion proximal to a site. Cordon off site area or prevent vehicular access to site. Cordon off site area to prevent accidental damage. Cordon off site area and block access route to restrict vehicular access to sites. Mitigation Option 3 NA Move artefacts under an AHIP to location outside impact area. Move artefacts under an AHIP to location outside impact area. Site awareness and sensitivity education programme. The principles of ecologically sustainable development need to be considered under Section 2A of the NPW Act. Inter-generational equity is part of these principles, which allows future generations to access the cultural and environmental diversity of the present generation. Inter-generational equity has been considered as part of the assessment of significance. State significant Aboriginal sites should be considered for blanket protection for future generations, as these sites have been assessed as having highest significance within NSW. No Aboriginal sites of state significance were identified in this assessment. 108453-2; October 2012 Page 54

<strong>Cultural</strong> <strong>Heritage</strong> <strong>Impact</strong> <strong>Assessment</strong><br />

North Wambo Underground Mine Modification<br />

While impacts to archaeological and cultural heritage within the MA are predicted to be negligible to low<br />

(MSEC 2012), it is recommended that, if required, Wambo Coal seek an AHIP under Section 90 of the NSW<br />

National Parks and Wildlife Act, 1974 (NPW Act) to allow for subsidence movements and the salvage of<br />

registered and unregistered sites (should they be uncovered) in consultation with the relevant Aboriginal<br />

parties. If salvage is required it is recommended that artefacts be transferred to the temporary keeping place<br />

under the existing Care and Control Permit (#3130) in consultation with the relevant Aboriginal parties.<br />

Subsidence estimates for the project area (including specific predictions for Aboriginal sites) have been<br />

provided by MSEC (2012). Much of the surrounding area has also been previously undermined (Wollemi<br />

and Homestead workings in the Whybrow Seam), or approved to be undermined, including NWUM in the<br />

Wambo Seam, the Arrowfield and the Bowfield Seams.<br />

The NWUMM longwall area will be subject to a Subsidence Management Plan or Extraction Plan which will<br />

be implemented prior to the proposed works being undertaken.<br />

MSEC (2012:58-60) calculated the maximum predicted total conventional subsidence parameters for the<br />

archaeological sites in the MA for approved mining of the Wambo, Arrowfield and Bowfield Seams (Approved<br />

Layout) and compared them to the predicted values for the proposed NWUMM (Modified Layout). The<br />

predicted maximum incremental changes in subsidence resulting from the proposed modification at any<br />

Aboriginal site ranged from 0mm to 2400mm; in tilt ranged from 0mm/m to 35 mm/m; in hogging curvature<br />

ranged from 0 km -1 to 1.50 km -1 ; and in sagging curvature ranged from 0 km -1 to 1.90 km -1 (MSEC [2012:58-<br />

60, Table D01]). Further MSEC (2012: Table D01) predicted that although the maximum subsidence effects<br />

in the vicinity of known Aboriginal sites resulting from subsidence relating to the Modified Layout could vary<br />

between 350 mm and 6400 mm (35 cm and 640 cm) the actual incremental change between the Modified<br />

Layout and the previously Approved Layout varied between 0 mm and 2400 mm (0 cm and 240 cm). This<br />

increment would be an even smaller proportion of approved subsidence impacts if the historic workings<br />

(Whybrow Seam) were also included in the subsidence model.<br />

As such, MSEC (2012) predicted that the subsidence effects in the vicinity of known Aboriginal sites would<br />

not exceed 2400 mm and was significantly lower for the majority of Aboriginal sites ranging from 0 mm to<br />

2400 mm (0 cm to 240 cm). MSEC (2012:59) considered that the artefact sites in the MA could potentially<br />

be affected by cracking of the surface soils. It is unlikely that the Aboriginal objects at these sites would be<br />

destroyed by the surface cracking but could be impacted on or harmed by downward movement due to<br />

vertical subsidence (whereby the land surface moves downwards as a whole). However, compared to the<br />

existing and approved mining in this area, the NWUMM would not increase the risk of impacts to these sites.<br />

The Wollemi National Park escarpment cliff lines and steep talus slopes are more than one kilometre from<br />

the NWUMM area and are outside of the predicted subsidence impact area (MSEC 2012). As such, the<br />

proposed modification will not impact on the Wollemi National Park or the associated escarpment. Wollombi<br />

Brook lies approximately 500 m to the east of the project area and 1 km from any Aboriginal sites within the<br />

NWUMM area. Wollombi Brook will not be impacted by the proposed NWUMM (MSEC 2012).<br />

The existing Consent #2222 (Consent to Destroy with Salvage) covers the vast majority of the MA. It is<br />

therefore recommended that either the existing Consent be slightly expended or a new AHIP be applied for<br />

to cover the southern extent of the MA.<br />

108453-2; October 2012 Page 53

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!