Appendix C - Cultural Heritage Impact Assessment - Peabody Energy
Appendix C - Cultural Heritage Impact Assessment - Peabody Energy
Appendix C - Cultural Heritage Impact Assessment - Peabody Energy
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>Cultural</strong> <strong>Heritage</strong> <strong>Impact</strong> <strong>Assessment</strong><br />
North Wambo Underground Mine Modification<br />
Site ID<br />
Code<br />
Site Name<br />
Predicted total<br />
subsidence based<br />
on the approved<br />
layout (mm)<br />
Incremental<br />
change in<br />
subsidence due to<br />
the proposed<br />
modification<br />
(millimetres [mm])<br />
Incremental<br />
change in tilt due<br />
to the proposed<br />
modification<br />
(mm/m)<br />
AS G Wambo Site 338 3000 2100 15<br />
AS E Wambo Site 348 5100 0 -5<br />
AS A Wambo Site 351 3100 0 0<br />
AS B Wambo Site 352 4400 1800 -5<br />
AS C Wambo Site 353 3000 100 0<br />
AS F Wambo Site 354 350 0 0<br />
AS P Wambo Site 356 3600 900 25<br />
AS Z Wambo Site 357 2300 800 20<br />
IFY Wambo Site 358 4000 2400 10<br />
ST3 Wambo Site 360 3000 300 10<br />
IF AA Wambo Site 361 1700 1800 35<br />
AS AB Wambo Site 362 5300 700 10<br />
AS AC Wambo Site 363 500 0 0<br />
The identified risks to heritage, as well as, proposed conservation and mitigation strategies have been<br />
summarised in Table 18.<br />
There were a number of formal tools identified at Wambo Site 57 and Wambo Site 360 was a culturally<br />
scarred tree. Wambo Site 360 (ST3) and Wambo Site 57 were in close proximity to the crest of the hill and<br />
each other and may well be connected. For this reason they were ranked as moderately significant at a local<br />
level. The remainder of the Aboriginal cultural heritage sites in the project area were ranked as having low<br />
archaeological significance. A number of trees of a similar size and type were inspected in areas that had<br />
been previously undermined and it was determined by the Aboriginal stakeholders present, that if the<br />
predicted subsidence is similar to that experienced in other underground mining area then the tree should be<br />
left in situ and that regular monitoring of the site should be undertaken to monitor health of the tree.<br />
The registered Aboriginal parties inspected a number of trees with a similar girth and of similar type in an<br />
adjacent area which had been previously undermined by longwall mining with similar predictive subsidence<br />
modelling and found that the previously undermined trees had not been adversely affected.<br />
An inspection was also made of areas that had previously been mined by longwall mining in order to view the<br />
impact of potential subsidence on artefact sites in the current project area. On the basis of subsidence<br />
effects viewed in the area, it was determined by the registered Aboriginal parties present, that if subsidence<br />
impacts were minimal then it was unlikely that artefact sites would suffer impact. However, where<br />
subsidence predictions were moderate to high then the artefact sites could be impacted on by downward<br />
movement due to vertical subsidence (whereby the land surface moves downwards as a whole). As such an<br />
Aboriginal <strong>Heritage</strong> <strong>Impact</strong> Permit (AHIP) would be required for Aboriginal sites that were likely to suffer<br />
impact. The registered Aboriginal parties recommended that artefact scatters and isolated finds not be<br />
moved unless required. They considered that if impact to specific sites was likely, then those sites should be<br />
salvaged under an appropriate permit. It was also recommended that periodic monitoring of the sites be<br />
maintained by Wambo Coal to mitigate against potential site damage from subsidence impacts. If any<br />
impact to the Aboriginal objects is considered likely then immediate remediation measures should be<br />
instigated.<br />
108453-2; October 2012 Page 52