26.11.2014 Views

Appendix C - Cultural Heritage Impact Assessment - Peabody Energy

Appendix C - Cultural Heritage Impact Assessment - Peabody Energy

Appendix C - Cultural Heritage Impact Assessment - Peabody Energy

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Cultural</strong> <strong>Heritage</strong> <strong>Impact</strong> <strong>Assessment</strong><br />

North Wambo Underground Mine Modification<br />

Incorporated, Yinaar <strong>Cultural</strong> Services, Widescope Indigenous Group, Buudang and Cacatua Culture<br />

Consultants. Troy Favell, Environment & Community Manager and David Rankin, Environment &<br />

Community Coordinator both from Wambo Coal Mine also attended the survey.<br />

Two polygon searches of the AHIMS database were undertaken, identifying a total of 54 sites in the area.<br />

However, due to overlap in the search results, the actual number of sites previously recorded in the project<br />

area and its environs was found to be 41 sites (see Section 4.3.2). This included 28 artefact scatters, ten<br />

isolated finds, one potential archaeological deposit (PAD) and one possible scar tree. One of the artefact<br />

scatter sites had been previously salvaged under Permit #2222 (Wambo Site 62). There were 11 artefact<br />

scatters and seven isolated finds that had been previously recorded on the AHIMS database that lay within<br />

the actual boundaries of the NWUMM project area, comprising the MA and buffer. The subsequent<br />

Aboriginal cultural heritage survey identified 16 new sites. A total of 24 artefact scatters, nine isolated finds<br />

and one possible scar tree were therefore identified within the NWUMM project area (refer Table 14).<br />

The desktop study revealed that a number of major archaeological field surveys had previously been<br />

undertaken in the area, including but not limited to an Aboriginal <strong>Heritage</strong> <strong>Assessment</strong> in 2003 (White 2003)<br />

and an Archaeological Survey for the Proposed Open Cut and Underground Mine area (Rich 1991a). These<br />

studies identified a number of sites in both the local and regional area (refer Figure 4-1).<br />

During the course of the 2011 and 2012 Aboriginal cultural heritage field survey, sites previously identified by<br />

White (2003) and those recorded on the AHIMS database were ground truthed. In addition, any newly<br />

identified sites were recorded and a site card generated for inclusion on the AHIMS database. The majority<br />

of sites within the project area were located along crests, upper and mid slope areas of the rolling hills and<br />

on the lower slope areas above the flood plain.<br />

Several new artefact scatters and isolated finds were identified during the field survey. These sites were<br />

recorded and site cards were generated for registration on the AHIMS database. One possible scar tree<br />

Wambo Site 360 was also identified during the course of the field survey. The tree was a narrow leaved red<br />

ironbark in fair condition which showed evidence of both probable cultural scarring (on the west side of the<br />

trunk) and wounding resulting from mechanical damage in the recent past on the east side of the trunk. A<br />

site card has been submitted for registration with the Office of Environment and <strong>Heritage</strong> (OEH).<br />

The registered Aboriginal parties present inspected a number of trees with a similar girth and of similar type<br />

in an adjacent area which had been previously undermined by longwall mining with similar predictive<br />

subsidence modelling and found that the previously undermined trees had not been adversely affected.<br />

They therefore determined that regular monitoring by Wambo Coal be maintained to determine that the tree<br />

experienced no adverse effects from the proposed mining works. If any impact to the possible scar tree is<br />

considered likely then immediate remediation measures should be instigated.<br />

An inspection was also made of areas that had previously been mined by longwall mining in order to view the<br />

impact of potential subsidence artefact sites in the current project area. On the basis of subsidence effects<br />

viewed in the area, it was determined by the registered Aboriginal parties present, that if subsidence impacts<br />

were minimal then it was unlikely that artefact sites would suffer impact. However, where subsidence<br />

predictions were moderate to high then the artefact sites could be impacted on by downward movement due<br />

to vertical subsidence (whereby the land surface moves downwards as a whole). As such, an Aboriginal<br />

<strong>Heritage</strong> <strong>Impact</strong> Permit (AHIP) would be required for Aboriginal sites that were likely to suffer impact. The<br />

registered Aboriginal Parties recommended that artefact scatters and isolated finds not be moved unless<br />

required. They considered that if impact to specific sites was likely, then those sites should be salvaged<br />

under an appropriate permit. It was also recommended that periodic monitoring of the sites be maintained<br />

by Wambo Coal to mitigate against potential site damage from subsidence impacts. If any impact to the<br />

Aboriginal objects is considered likely then immediate remediation measures should be instigated.<br />

108453-2; October 2012 ES- 2

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!