planning permission and a confirmed compulsory purchase order in place. The LPA is<br />
committed to funding the preparation costs of the road itself. Sales of <strong>Council</strong>-owned<br />
land do have the potential to generate substantial sums which could be used for this<br />
purpose. The extent of this is, however, a matter of speculation. The <strong>Council</strong>’s capital<br />
programme could also make a substantial contribution but would, inevitably, be the<br />
subject of competing demands arising across the whole range of local government<br />
services. I conclude that there is no realistic prospect that the <strong>A5225</strong> road will be funded<br />
so as to enable a start of construction within the plan period.<br />
The likelihood that the scheme will commence within the plan period<br />
10.121 The LPA, at the inquiry, expressed its intention to submit a planning<br />
application for the construction of the road, as a whole, in December 2004. It would make<br />
a decision on this and refer the application to the ODPM in July 2005. A subsequent<br />
inquiry would, it believes, probably be concluded in June 2006 and the decision arising<br />
from this would be issued in April 2007. A further LTP submission would be made in<br />
July of that year. If approved in December 2007, funding would be available at April<br />
2008. Compulsory Purchase Orders and Side Road Orders would be made in December<br />
2007. The Compulsory Purchase Order inquiry would be held in May 2008 leading to a<br />
decision in December 2008. Tenders would be issued in October 2008 and accepted in<br />
February 2009. This would allow construction to commence in April 2009 and be<br />
completed in October 2011. The LPA estimates that this timetable could be reduced by<br />
about two years if there are no outstanding objections to be resolved by the various<br />
inquiries. This is, however, an unlikely scenario.<br />
10.122 The LPA assumes that it will make a decision on the planning application<br />
in July 2005. This is based on the assumption that a planning application would be<br />
submitted during December 2004. However, at mid-January 2005, the LPA confirmed<br />
that such an application had not yet been submitted and that it could not indicate when<br />
that might occur. The decision of GONW on the LTP bid (2/12/04) referred to the need<br />
for additional traffic modelling work to be done. This would have to be completed before<br />
a Transport Assessment could be finalised and used to support a planning application. At<br />
January 2005 the LPA confirmed that its traffic modelling work was continuing but gave<br />
no indication when it might be concluded.<br />
10.123 In any case the starting point for a decision on the planning application<br />
will be the development plan. Given the advanced stage reached in the preparation of the<br />
replacement UDP, the content of this report will be an important material consideration<br />
which might well delay such a decision. Indeed, given the advice of the companion<br />
document to PPS1 (The Planning System: General Principles, paragraph 17), it is likely<br />
to be the case that the proposed road scheme would be considered to be so substantial,<br />
and its effect on other land uses so significant, that to grant planning permission for it in<br />
advance of this report would prejudice the outcome of the plan process by predetermining<br />
decisions about the scale, location or phasing of new development that ought<br />
properly to be taken in the development plan context.<br />
419