21.11.2014 Views

australia's identified mineral resources 2005 - Geoscience Australia

australia's identified mineral resources 2005 - Geoscience Australia

australia's identified mineral resources 2005 - Geoscience Australia

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

AUSTRALIA’S IDENTIFIED MINERAL RESOURCES <strong>2005</strong><br />

World Ranking<br />

<strong>Australia</strong> has 5% of the world’s recoverable black coal EDR and ranks sixth behind USA (28%), Russia<br />

(20%), China (13%), India (12%) and South Africa (7%). It produced about 7% of the world’s saleable<br />

black coal in 2004 and ranked fourth after China (37%), USA (22%) and India (8%).<br />

INDUSTRY DEVELOPMENTS – QUEENSLAND<br />

Pacific Coal: At Hail Creek a $300 million expansion from 5.5 to 8 Mtpa is scheduled to be<br />

completed by mid-2006 with the introduction of a second dragline. Underground longwall mining<br />

commenced in the Ti Tree zone at the Kestrel mine. The $400 million Clermont open-cut thermal<br />

coal project is being investigated as a replacement for the 12 Mtpa Blair Athol mine when operations<br />

cease in about 2009. A decision on whether to proceed is expected in <strong>2005</strong>.<br />

BHP Billiton Mitsubishi Alliance (BMA): At Blackwater, construction commenced in early 2004<br />

on a US$180 million 14 Mtpa coal handling and preparation plant. The plant will process the entire<br />

production from Blackwater and replace existing high cost plants. Commissioning is scheduled for<br />

late <strong>2005</strong>. In April 2004, development driveage commenced at the Broadmeadow punch longwall<br />

project following completion of highwall preparation. The 3.5 Mtpa mine is expected to commence<br />

in mid-<strong>2005</strong>.<br />

In March 2004, BMA announced plans to increase coking coal production from 52 to 57 Mtpa by<br />

mid-<strong>2005</strong> at a cost of US$94 million. The plan includes purchasing additional equipment for Saraji,<br />

Peak Downs and Goonyella mines, upgrades to processing plants at Saraji and Peak Downs and<br />

awarding of overburden stripping contracts. The next stage is estimated to cost $US75 million and<br />

increase production to 59 Mtpa by mid-2006 and includes acquisition of additional stripping and<br />

mining equipment and awarding an overburden stripping contract at Saraji.<br />

Xstrata Coal: The $290 million Rolleston open-cut thermal coal project commenced construction in<br />

early 2004 and initial production of 1 Mtpa is expected in <strong>2005</strong>. Full production of 6 Mtpa of export<br />

and 2 Mtpa of domestic product is scheduled for 2008. The operation is expected to have a mine life<br />

in excess of 20 years and has further expansion potential to 12 Mtpa with minor additional capital.<br />

At Newlands, development continued on the Northern underground punch longwall mine with full<br />

production expected in late <strong>2005</strong> to replace production from the existing Southern underground<br />

mine, which is due to close in late <strong>2005</strong>. Production commenced at the Suttor Creek and Eastern<br />

Creek open-cut thermal coal mines near the Newlands operation.<br />

20<br />

Anglo Coal: Construction at the $250 million Grasstrees underground longwall mine commenced<br />

in 2001 and is due to be commissioned in 2006 at a capacity of 5 Mtpa. The mine is designed to<br />

replace production from the Southern Colliery at the German Creek project. Open-cut production<br />

commenced in early 2004 at the Oak Park open-cut mine near the German Creek project. The Lake<br />

Lindsay open-cut coking and thermal coal project is currently undergoing feasibility studies to<br />

possibly commence mining in 2006. Feasibility studies are continuing on the $500 million 5 Mtpa<br />

Grosvenor underground longwall coking coal project adjacent to the Moranbah North mine. At<br />

Moura, Anglo announced a US$600 million plan to increase production from 7 to 12.7 Mtpa by 2007.<br />

Anglo intends to establish two additional operations near the Moura mine with the new and<br />

expanded operations to be known as the Dawson Complex.<br />

Macarthur Coal: At Coppabella the first coal was mined from the South Pit in early 2004. The new<br />

Moorvale mine was expanded from 1.6 to 2 Mtpa from early 2004. The Olive Downs, Moorvale<br />

West and Codrilla deposits are all being considered as satellite operations to the Moorvale mine.<br />

Development is dependent on the expansion of the Dalrymple Bay Coal Terminal. Macarthur is<br />

undertaking a feasibility study into the West Rolleston open-cut thermal coal project as production<br />

could be shipped through the expanding Port of Gladstone. Construction is proposed to commence<br />

in mid-2006 with first production in 2008. In late 2004, Macarthur announced a feasibility study into<br />

establishing a new generation coke making facility near the Stanwell Power Station in Central<br />

Queensland. The facility will produce 300 MW of electricity and could begin producing coke by<br />

the end of 2007.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!