australia's identified mineral resources 2005 - Geoscience Australia
australia's identified mineral resources 2005 - Geoscience Australia
australia's identified mineral resources 2005 - Geoscience Australia
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
AUSTRALIA’S IDENTIFIED MINERAL RESOURCES <strong>2005</strong><br />
World Ranking<br />
<strong>Australia</strong> has 5% of the world’s recoverable black coal EDR and ranks sixth behind USA (28%), Russia<br />
(20%), China (13%), India (12%) and South Africa (7%). It produced about 7% of the world’s saleable<br />
black coal in 2004 and ranked fourth after China (37%), USA (22%) and India (8%).<br />
INDUSTRY DEVELOPMENTS – QUEENSLAND<br />
Pacific Coal: At Hail Creek a $300 million expansion from 5.5 to 8 Mtpa is scheduled to be<br />
completed by mid-2006 with the introduction of a second dragline. Underground longwall mining<br />
commenced in the Ti Tree zone at the Kestrel mine. The $400 million Clermont open-cut thermal<br />
coal project is being investigated as a replacement for the 12 Mtpa Blair Athol mine when operations<br />
cease in about 2009. A decision on whether to proceed is expected in <strong>2005</strong>.<br />
BHP Billiton Mitsubishi Alliance (BMA): At Blackwater, construction commenced in early 2004<br />
on a US$180 million 14 Mtpa coal handling and preparation plant. The plant will process the entire<br />
production from Blackwater and replace existing high cost plants. Commissioning is scheduled for<br />
late <strong>2005</strong>. In April 2004, development driveage commenced at the Broadmeadow punch longwall<br />
project following completion of highwall preparation. The 3.5 Mtpa mine is expected to commence<br />
in mid-<strong>2005</strong>.<br />
In March 2004, BMA announced plans to increase coking coal production from 52 to 57 Mtpa by<br />
mid-<strong>2005</strong> at a cost of US$94 million. The plan includes purchasing additional equipment for Saraji,<br />
Peak Downs and Goonyella mines, upgrades to processing plants at Saraji and Peak Downs and<br />
awarding of overburden stripping contracts. The next stage is estimated to cost $US75 million and<br />
increase production to 59 Mtpa by mid-2006 and includes acquisition of additional stripping and<br />
mining equipment and awarding an overburden stripping contract at Saraji.<br />
Xstrata Coal: The $290 million Rolleston open-cut thermal coal project commenced construction in<br />
early 2004 and initial production of 1 Mtpa is expected in <strong>2005</strong>. Full production of 6 Mtpa of export<br />
and 2 Mtpa of domestic product is scheduled for 2008. The operation is expected to have a mine life<br />
in excess of 20 years and has further expansion potential to 12 Mtpa with minor additional capital.<br />
At Newlands, development continued on the Northern underground punch longwall mine with full<br />
production expected in late <strong>2005</strong> to replace production from the existing Southern underground<br />
mine, which is due to close in late <strong>2005</strong>. Production commenced at the Suttor Creek and Eastern<br />
Creek open-cut thermal coal mines near the Newlands operation.<br />
20<br />
Anglo Coal: Construction at the $250 million Grasstrees underground longwall mine commenced<br />
in 2001 and is due to be commissioned in 2006 at a capacity of 5 Mtpa. The mine is designed to<br />
replace production from the Southern Colliery at the German Creek project. Open-cut production<br />
commenced in early 2004 at the Oak Park open-cut mine near the German Creek project. The Lake<br />
Lindsay open-cut coking and thermal coal project is currently undergoing feasibility studies to<br />
possibly commence mining in 2006. Feasibility studies are continuing on the $500 million 5 Mtpa<br />
Grosvenor underground longwall coking coal project adjacent to the Moranbah North mine. At<br />
Moura, Anglo announced a US$600 million plan to increase production from 7 to 12.7 Mtpa by 2007.<br />
Anglo intends to establish two additional operations near the Moura mine with the new and<br />
expanded operations to be known as the Dawson Complex.<br />
Macarthur Coal: At Coppabella the first coal was mined from the South Pit in early 2004. The new<br />
Moorvale mine was expanded from 1.6 to 2 Mtpa from early 2004. The Olive Downs, Moorvale<br />
West and Codrilla deposits are all being considered as satellite operations to the Moorvale mine.<br />
Development is dependent on the expansion of the Dalrymple Bay Coal Terminal. Macarthur is<br />
undertaking a feasibility study into the West Rolleston open-cut thermal coal project as production<br />
could be shipped through the expanding Port of Gladstone. Construction is proposed to commence<br />
in mid-2006 with first production in 2008. In late 2004, Macarthur announced a feasibility study into<br />
establishing a new generation coke making facility near the Stanwell Power Station in Central<br />
Queensland. The facility will produce 300 MW of electricity and could begin producing coke by<br />
the end of 2007.