21.11.2014 Views

tunnel's - Trenchless International

tunnel's - Trenchless International

tunnel's - Trenchless International

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Weighing in<br />

on the best cure<br />

Speed of installation was the<br />

focus of a project rehabilitating mixed<br />

water channels in the Rethmar district of<br />

Sehnde, Lower Saxony. The damaged<br />

pipelines lay under the town’s main artery,<br />

the busy B65 motorway. Rehabilitation of<br />

the pipe via open construction methods<br />

would have resulted in considerable traffic<br />

re-routing. Proponent Sehnde Municipal<br />

Utilities issued an invitation to tender<br />

that specified rehabilitation via trenchless<br />

relining.<br />

The job required renewal of 911 m of<br />

mixed water channel in the dimensions of<br />

DN250 to DN1,200. Rohrsanierung Jensen<br />

from Bordesholm was awarded the tender<br />

due to the company’s extensive experience<br />

in pipe rehabilitation. In May 2012, the<br />

channel was rehabilitated in ten sections<br />

under the direction of Andreas Josef.<br />

Challenges coming thick and fast<br />

The biggest challenge of the project was<br />

rehabilitating a section of DN1,200 circular<br />

profile pipe, measuring 205 m. This long<br />

section ran directly under the motorway,<br />

which meant multiple installation pits were<br />

out of the question and the entire section<br />

would have to be relined from a single<br />

installation point.<br />

Based on the existing pipeline damage,<br />

structural engineers calculated the composite<br />

wall thickness required as 12.1 mm. In order<br />

to install a pipe liner with this wall thickness<br />

in a reasonable time, it was initially decided<br />

the only viable curing method could be<br />

‘combination curing’, which works by using<br />

a combination of UV light curing and thermal<br />

curing. However, the disadvantage of this<br />

technology is the time-consuming process;<br />

in order to prevent premature curing of the<br />

SEE US AT<br />

Reline Europe details a project that took place in Sehnde, Germany, in which Rohrsanierung Jensen<br />

installed a 205 m, 20 tonne Alphaliner1500 with UV curing, completing one of the heaviest cured pipe<br />

installations to-date in record time.<br />

79<br />

BOOTH NO.<br />

resin, the liner material must be transported<br />

and stored in cool containers. Additionally,<br />

on the construction site a considerable<br />

amount of additional work is required<br />

compared with pure UV light curing.<br />

Rohrsanierung Jensen Managing Director<br />

Stefan Jensen decided on a different strategy,<br />

deciding to use an Alphaliner1500, a newly<br />

developed GFRP liner from manufacturer<br />

RELINEEUROPE. This pipe liner is characterised<br />

by a highly developed, high<br />

level transparency glass resin complex.<br />

In combination with UV curing technology,<br />

Alphaliner1500 with wall thicknesses<br />

exceeding 10 mm can be quickly cured<br />

using pure light.<br />

The liner arrives on-site<br />

On 2 May, the 205 m liner was delivered<br />

to the construction site at 10 am.<br />

The transport case, which measured 6<br />

m long and 2.5 m in height and width,<br />

weighed almost 20 tonnes. A heavy-duty<br />

crane unloaded the liner from the lorry to<br />

the manhole. Four hours later, the pipe<br />

liner was inserted into the channel on a<br />

sliding foil with the help of a conveyor belt,<br />

and the packers were positioned on both<br />

ends of the liner.<br />

Mr Jensen said “For the curing process, we<br />

used the light source that RELINEEUROPE<br />

developed especially for rehabilitating large<br />

profiles, which has a curing performance of<br />

12 x 1,000 watts.”<br />

Mr Jensen invested in this highperformance<br />

curing technology back in<br />

2011. He explains that the technology has<br />

already proven itself on many construction<br />

sites when it comes to quickly curing liners<br />

with large wall thicknesses.<br />

Speedy completion<br />

The liner had been positioned and<br />

calibrated using compressed air within one<br />

hour, allowing a team specialised in the<br />

installation of large liners to start the curing<br />

process at 3 pm.<br />

A curing speed of around 50 cm per<br />

minute was achieved with the powerful<br />

UV light source. The curing process was<br />

completed at 10 pm after around seven<br />

hours of work. At 3 am, the specialists<br />

had completed the milling out of the<br />

supply lines and the rehabilitation of the<br />

connections. In the morning, commuters<br />

driving to work were able to go through<br />

Sehnde without experiencing any traffic<br />

congestion. Sehnde Municipal Utilities’<br />

Claudia Pechtheiden–Meier, who<br />

monitored the project as the contracting<br />

body’s construction manager, was<br />

also satisfied. Rohrsanierung Jensen<br />

completed the project at a record speed<br />

and well within the allocated time frame.<br />

REL Anz_185x84_en.fh11 11.09.2012 15:40 Uhr Seite 1<br />

The pipe rehabilitation team uses a conveyor belt for feeding into the manhole.<br />

“This globally unique curing performance<br />

enables a considerably faster and more<br />

reliable installation of pipe liners, even<br />

when rehabilitating large cross-sections<br />

with high static loads," says Mr Jensen.<br />

C M Y CM MY CY CMY K<br />

Mr Jensen said the benefits of light curing<br />

with the Alphaliner1500, are “therefore<br />

transferrable on a one-to-one basis for the<br />

rehabilitation of large profiles.”<br />

CIPP<br />

CIPP<br />

October 2012 - <strong>Trenchless</strong> <strong>International</strong><br />

The Alphaliner1500, which weighs 20 tonnes, during the loading process at RELINEEUROPE's premises.<br />

Perfect System:<br />

Light-transparent liner material<br />

and high performance UV-technology<br />

• Diameter DN150 – DN1300 (circular, egg-shaped, special sections) with uniquely<br />

defined wearing layer for optimum endurance<br />

• Curing with innovative new UV-curing technology – with controlled stable UV<br />

radiation power<br />

• Alphaliner 1500 with UV-light transparent liner material – for quick and reliable<br />

curing of high wall thicknesses over 10 mm<br />

With its Alphaliner users RELINEEUROPE uses the unique RE-TQM Total Quality<br />

Management System as an integrated QM system with defined quality guidelines<br />

from the raw material to the completed liner installation, in order to guarantee<br />

the highest level of quality in all cases.<br />

More about us : : www.relineeurope.com<br />

RELINEEUROPE AG : : Große Ahlmühle 31 : : D-76865 Rohrbach : : Fon +49 63 49 93 934-0 : : info@relineeurope.com<br />

October 2012 - <strong>Trenchless</strong> <strong>International</strong><br />

34<br />

Probedruck<br />

35

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!