tunnel's - Trenchless International
tunnel's - Trenchless International
tunnel's - Trenchless International
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Weighing in<br />
on the best cure<br />
Speed of installation was the<br />
focus of a project rehabilitating mixed<br />
water channels in the Rethmar district of<br />
Sehnde, Lower Saxony. The damaged<br />
pipelines lay under the town’s main artery,<br />
the busy B65 motorway. Rehabilitation of<br />
the pipe via open construction methods<br />
would have resulted in considerable traffic<br />
re-routing. Proponent Sehnde Municipal<br />
Utilities issued an invitation to tender<br />
that specified rehabilitation via trenchless<br />
relining.<br />
The job required renewal of 911 m of<br />
mixed water channel in the dimensions of<br />
DN250 to DN1,200. Rohrsanierung Jensen<br />
from Bordesholm was awarded the tender<br />
due to the company’s extensive experience<br />
in pipe rehabilitation. In May 2012, the<br />
channel was rehabilitated in ten sections<br />
under the direction of Andreas Josef.<br />
Challenges coming thick and fast<br />
The biggest challenge of the project was<br />
rehabilitating a section of DN1,200 circular<br />
profile pipe, measuring 205 m. This long<br />
section ran directly under the motorway,<br />
which meant multiple installation pits were<br />
out of the question and the entire section<br />
would have to be relined from a single<br />
installation point.<br />
Based on the existing pipeline damage,<br />
structural engineers calculated the composite<br />
wall thickness required as 12.1 mm. In order<br />
to install a pipe liner with this wall thickness<br />
in a reasonable time, it was initially decided<br />
the only viable curing method could be<br />
‘combination curing’, which works by using<br />
a combination of UV light curing and thermal<br />
curing. However, the disadvantage of this<br />
technology is the time-consuming process;<br />
in order to prevent premature curing of the<br />
SEE US AT<br />
Reline Europe details a project that took place in Sehnde, Germany, in which Rohrsanierung Jensen<br />
installed a 205 m, 20 tonne Alphaliner1500 with UV curing, completing one of the heaviest cured pipe<br />
installations to-date in record time.<br />
79<br />
BOOTH NO.<br />
resin, the liner material must be transported<br />
and stored in cool containers. Additionally,<br />
on the construction site a considerable<br />
amount of additional work is required<br />
compared with pure UV light curing.<br />
Rohrsanierung Jensen Managing Director<br />
Stefan Jensen decided on a different strategy,<br />
deciding to use an Alphaliner1500, a newly<br />
developed GFRP liner from manufacturer<br />
RELINEEUROPE. This pipe liner is characterised<br />
by a highly developed, high<br />
level transparency glass resin complex.<br />
In combination with UV curing technology,<br />
Alphaliner1500 with wall thicknesses<br />
exceeding 10 mm can be quickly cured<br />
using pure light.<br />
The liner arrives on-site<br />
On 2 May, the 205 m liner was delivered<br />
to the construction site at 10 am.<br />
The transport case, which measured 6<br />
m long and 2.5 m in height and width,<br />
weighed almost 20 tonnes. A heavy-duty<br />
crane unloaded the liner from the lorry to<br />
the manhole. Four hours later, the pipe<br />
liner was inserted into the channel on a<br />
sliding foil with the help of a conveyor belt,<br />
and the packers were positioned on both<br />
ends of the liner.<br />
Mr Jensen said “For the curing process, we<br />
used the light source that RELINEEUROPE<br />
developed especially for rehabilitating large<br />
profiles, which has a curing performance of<br />
12 x 1,000 watts.”<br />
Mr Jensen invested in this highperformance<br />
curing technology back in<br />
2011. He explains that the technology has<br />
already proven itself on many construction<br />
sites when it comes to quickly curing liners<br />
with large wall thicknesses.<br />
Speedy completion<br />
The liner had been positioned and<br />
calibrated using compressed air within one<br />
hour, allowing a team specialised in the<br />
installation of large liners to start the curing<br />
process at 3 pm.<br />
A curing speed of around 50 cm per<br />
minute was achieved with the powerful<br />
UV light source. The curing process was<br />
completed at 10 pm after around seven<br />
hours of work. At 3 am, the specialists<br />
had completed the milling out of the<br />
supply lines and the rehabilitation of the<br />
connections. In the morning, commuters<br />
driving to work were able to go through<br />
Sehnde without experiencing any traffic<br />
congestion. Sehnde Municipal Utilities’<br />
Claudia Pechtheiden–Meier, who<br />
monitored the project as the contracting<br />
body’s construction manager, was<br />
also satisfied. Rohrsanierung Jensen<br />
completed the project at a record speed<br />
and well within the allocated time frame.<br />
REL Anz_185x84_en.fh11 11.09.2012 15:40 Uhr Seite 1<br />
The pipe rehabilitation team uses a conveyor belt for feeding into the manhole.<br />
“This globally unique curing performance<br />
enables a considerably faster and more<br />
reliable installation of pipe liners, even<br />
when rehabilitating large cross-sections<br />
with high static loads," says Mr Jensen.<br />
C M Y CM MY CY CMY K<br />
Mr Jensen said the benefits of light curing<br />
with the Alphaliner1500, are “therefore<br />
transferrable on a one-to-one basis for the<br />
rehabilitation of large profiles.”<br />
CIPP<br />
CIPP<br />
October 2012 - <strong>Trenchless</strong> <strong>International</strong><br />
The Alphaliner1500, which weighs 20 tonnes, during the loading process at RELINEEUROPE's premises.<br />
Perfect System:<br />
Light-transparent liner material<br />
and high performance UV-technology<br />
• Diameter DN150 – DN1300 (circular, egg-shaped, special sections) with uniquely<br />
defined wearing layer for optimum endurance<br />
• Curing with innovative new UV-curing technology – with controlled stable UV<br />
radiation power<br />
• Alphaliner 1500 with UV-light transparent liner material – for quick and reliable<br />
curing of high wall thicknesses over 10 mm<br />
With its Alphaliner users RELINEEUROPE uses the unique RE-TQM Total Quality<br />
Management System as an integrated QM system with defined quality guidelines<br />
from the raw material to the completed liner installation, in order to guarantee<br />
the highest level of quality in all cases.<br />
More about us : : www.relineeurope.com<br />
RELINEEUROPE AG : : Große Ahlmühle 31 : : D-76865 Rohrbach : : Fon +49 63 49 93 934-0 : : info@relineeurope.com<br />
October 2012 - <strong>Trenchless</strong> <strong>International</strong><br />
34<br />
Probedruck<br />
35