tunnel's - Trenchless International
tunnel's - Trenchless International
tunnel's - Trenchless International
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
projects<br />
HDD under<br />
the Havel River<br />
By Lutz Rau<br />
SEE US AT<br />
70<br />
BOOTH NO.<br />
When crews in Germany installed a pipe 17 m below ground in a limited-size area with strict angle<br />
requirements, pipe-by-pipe assembly using Duktus DN700 ductile iron pipe allowed for high installation<br />
rates, despite project constraints.<br />
Berlin’s Havel River, measuring over<br />
a kilometre in width, supports a series of<br />
water wells on its banks. Berlin’s water<br />
supply company, Berliner Wasserbetriebe,<br />
pumps raw water from the Schildhorn Wells<br />
and treats it in the Tiefwerder Waterworks,<br />
producing drinkable water.<br />
For the past three years the wells have<br />
been under renovation. Open trench<br />
excavation was utilised to replace a 2 km<br />
section of raw water pipeline with ductile<br />
iron pipes.<br />
Fighting the slope<br />
In a sloping region of Charlottenburg,<br />
486 m of the pipeline runs approximately<br />
17 m below the high river bank.<br />
Because of this severe project constraint,<br />
open-trench installation was immediately<br />
dismissed, and the project proponent had<br />
to consider alternative means of renovating<br />
the ageing pipe.<br />
The existing pipes lay in relatively short<br />
lengths of 6 m, and had restrained joints<br />
with angular deflections. Horizontal direction<br />
drilling (HDD) was chosen as the preferred<br />
technique as it provided an elegant way of<br />
meeting these difficult requirements.<br />
Instruction by the pipe supplier’s applications engineering department.<br />
The installation crew quickly<br />
gained momentum with<br />
the drilling and installation<br />
process, and the 486 m long<br />
pipeline was assembled and<br />
pulled in in just 34 hours.<br />
Working with ductile iron<br />
An order was placed for 504 m of Duktus<br />
ductile iron pipes to EN 545 with TYTON<br />
push-in sockets with BLS/VRS-T restraint<br />
systems and associated fittings. This type<br />
of pipe is lined with cement mortar and has<br />
an outside zinc coating with a rugged outer<br />
cement mortar coating of EN 15 542. This<br />
coating can withstand very high mechanical<br />
and chemical stresses.<br />
The installation<br />
The existing bore was enlarged to<br />
850 mm, and then bored out to 1,100 mm.<br />
TAKING CARE OF THE ENVIRONMENT!<br />
Ductile iron pipe systems for trenchless laying.<br />
Visit us at the No-Dig 2012 in São Paulo, pavilion F, stand 70<br />
and at www.duktus.com<br />
The steel assembly ramp – a shrink-on sleeve and protective cone being fitted.<br />
The installation crew quickly gained<br />
momentum with the drilling and installation<br />
process, and the 486 m long pipeline was<br />
assembled and pulled in in just 34 hours. In<br />
this time frame the crews also managed to<br />
finish installing joint protection, which had<br />
been planned to take up to 60 hours.<br />
projects<br />
October 2012 - <strong>Trenchless</strong> <strong>International</strong><br />
Because of this severe<br />
project constraint, opentrench<br />
installation was<br />
immediately dismissed, and<br />
the project proponent had to<br />
consider alternative means of<br />
renovating the ageing pipe.<br />
Fitting the traction head.<br />
October 2012 - <strong>Trenchless</strong> <strong>International</strong><br />
24<br />
Anzeige grabenlos 185x125.indd 1 05.09.2012 09:22:34<br />
25