LOCATION STATEMENT OF PROPOSED CROSS DRAINAGE KM FROM 69.900 TO KM 72.075 ON ROAD SEVOKE GANGTOK(NH-31A) IN STATE SIKKIM.<br />
Altitude :-Below 2100 Mtrs<br />
SL NO. LOC (Km) Extension <strong>of</strong> exist<strong>in</strong>g Culvert to 12m length Remarks<br />
1.5m span 2m span 3m span 6m span<br />
1 70.200 3.60 mtr extn<br />
2 70.450 3.60 mtr extn<br />
3 70.783 2.40 mtr extn<br />
4 71.038 4.80 mtr extn<br />
5 71.125 New culvert to be<br />
constructed<br />
6 71.150 2.40 mtr extn<br />
7 71.309 2.40 mtr extn<br />
8 71.425 4.80 mtr extn<br />
9 71.537 3.60 mtr extn<br />
10 71.719 3.60 mtr extn<br />
11 71.925 6.00 mtr extn