Santa Clara River Trail Final Master Plan - Development Services ...

Santa Clara River Trail Final Master Plan - Development Services ... Santa Clara River Trail Final Master Plan - Development Services ...

developmentservices.cityofoxnard.org
from developmentservices.cityofoxnard.org More from this publisher
18.11.2014 Views

Chapter 7: Project Implementation Plan Table 14: Concept Estimate, Segment 2 Concept Estimate Santa Clara River Trail Segment 2 From Easterly End of Segment 1 Junction with Ventura Road Easterly to Approximately 750 Feet East of Highway 101 Concrete Pavement Over Aggregate Base Bid Item Description Estimated Quantity Unit Unit Cost Extended Cost 1 Mobilization and Site Requirements 1 LS $26,000.00 $ 26,000.00 2 Implement SWPP/WQMP 1 LS $5,200.00 $ 5,200.00 3 Dust Control 1 LS $2,600.00 $ 2,600.00 4 Erosion Control - MS4 permit 1 LS $5,000.00 $ 5,000.00 5 Clearing and Grubbing 1.5 Acre $500.00 $ 750.00 6 Tree Removal 0 LS $ - 7 Tree Trimming 1 LS $15,000.00 $ 15,000.00 8 Protect Gas Monitoring Wells/Adjust Risers and Valves to Finish Grade 0 LS $0.00 $ - 9 Rough Grading - Include Surveying 46800 SF $0.65 $ 30,420.00 10 Subgrade Preparation 46800 SF $0.30 $ 14,040.00 11 Construct Portland Cement Concrete Pavement Over Aggregate Base 46800 SF $8.25 $ 386,100.00 12 Decorative Concrete Pavers 0 LS $0.00 $ - 13 Fine Grade Shoulder 12800 SF $0.50 $ 6,400.00 14 Construct 2' Wide Concrete Traffic Barrier 0 LS $0.00 $ - 15 Construct Curb and Gutter 2700 LF $25.00 $ 67,500.00 16 Provide and Install Mile Marker/Trail Medallions 3 EA $300.00 $ 900.00 17 Pavement Markings and Striping 1 LS $6,000.00 $ 6,000.00 18 Provide and Install Bollards 4 EA $1,500.00 $ 6,000.00 19 Construct Bench Slab 0 EA $500.00 $ - 20 Construct 4-foot Split-Rail Fence 0 LF $15.00 $ - 21 Construct 6-foot High Chain Link Fence 0 LF $35.00 $ - 22 Construct 4-foot High Ornamental Metal Fence 550 LF $65.00 $ 35,750.00 23 Construct Double Drive Gate 0 EA $6,200.00 $ - 24 Tree Replacement/Planting 0 LS $5,000.00 $ - 100 | Alta Planning + Design

Santa Clara River Trail Plan 25 Miscellaneous Minor Drainage Structures (field inlets, culvert Headwall, etc) 1 LS $10,000.00 $ 10,000.00 26 Slough Walls/Low Retaining walls 0 LF $75.00 $ - 27 Channel Crossing - Pedestrian/Bicycle Bridge 0 LS $0.00 $ - 28 Provide and Install Benches 0 EA $2,500.00 $ - 29 Landscape and Irrigation Improvements 1 LS $20,000.00 $ 20,000.00 30 Provide and Install Directional, Etiquette, Regulatory and Warning Signs 8 EA $250.00 $ 2,000.00 31 Provide and Install Wayfinding Signs 3 EA $750.00 $ 2,250.00 32 Provide and Install Interpretive Signs 0 EA $5,000.00 $ - 33 Construct Entry Monument Structure 0 EA $0.00 $ - 34 Provide and Install Trash Receptacles 2 EA $1,800.00 $ 3,600.00 35 Provide and Install Lighting 0 EA $5,000.00 $ - 36 Provide and Install Bike Racks 0 EA $1,500.00 $ - 37 Provide and Install Drinking Fountain 0 EA $5,000.00 $ - 38 Provide and Install Conduit for Surveillance Cameras 39 Provide and Install Camera and Video Surveillance System 0 LF $25.00 0 EA $2,500.00 $ - $ - 40 Provide and Install Police Call Box 0 EA $6,000.00 $ - Sub-Total = $ 645,510.00 20% Design, Engineering, Environmental and Permitting = $ 129,102.00 20% Contingency = $ 129,102.00 $ 903,714.00 City of Oxnard | 101

<strong>Santa</strong> <strong>Clara</strong> <strong>River</strong> <strong>Trail</strong> <strong>Plan</strong><br />

25<br />

Miscellaneous Minor Drainage Structures<br />

(field inlets, culvert Headwall, etc)<br />

1 LS $10,000.00 $ 10,000.00<br />

26 Slough Walls/Low Retaining walls 0 LF $75.00 $ -<br />

27<br />

Channel Crossing - Pedestrian/Bicycle<br />

Bridge<br />

0 LS $0.00<br />

$ -<br />

28 Provide and Install Benches 0 EA $2,500.00 $ -<br />

29 Landscape and Irrigation Improvements 1 LS $20,000.00 $ 20,000.00<br />

30 Provide and Install Directional, Etiquette,<br />

Regulatory and Warning Signs 8 EA $250.00 $ 2,000.00<br />

31 Provide and Install Wayfinding Signs 3 EA $750.00 $ 2,250.00<br />

32 Provide and Install Interpretive Signs 0 EA $5,000.00 $ -<br />

33 Construct Entry Monument Structure 0 EA $0.00 $ -<br />

34 Provide and Install Trash Receptacles 2 EA $1,800.00 $ 3,600.00<br />

35 Provide and Install Lighting 0 EA $5,000.00 $ -<br />

36 Provide and Install Bike Racks 0 EA $1,500.00 $ -<br />

37 Provide and Install Drinking Fountain 0 EA $5,000.00 $ -<br />

38 Provide and Install Conduit for<br />

Surveillance Cameras<br />

39 Provide and Install Camera and Video<br />

Surveillance System<br />

0 LF $25.00<br />

0 EA $2,500.00<br />

$ -<br />

$ -<br />

40 Provide and Install Police Call Box 0 EA $6,000.00 $ -<br />

Sub-Total = $ 645,510.00<br />

20% Design, Engineering, Environmental and Permitting = $ 129,102.00<br />

20% Contingency = $ 129,102.00<br />

$ 903,714.00<br />

City of Oxnard | 101

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!