Chapter 7: Project Implementation <strong>Plan</strong><br />

Table 13: Concept Estimate, Segment 1<br />

Concept Estimate <strong>Santa</strong> <strong>Clara</strong> <strong>River</strong> <strong>Trail</strong> Segment 1<br />

From Approximately 1/4 mile Westerly of Victoria Avenue Easterly to Junction with North Ventura<br />

Road<br />

Concrete Pavement Over Aggregate Base<br />

Bid<br />

Item<br />

Description<br />

Estimated<br />

Quantity Unit Unit Cost Extended Cost<br />

1 Mobilization and Site Requirements 1 LS $ 70,000.00<br />

2 Implement SWPP/WQMP 1 LS $ 14,000.00<br />

3 Dust Control 1 LS $ 7,000.00<br />

4 Erosion Control - MS4 permit 1 LS $ 14,000.00<br />

5 Clearing and Grubbing 3.9 Acre $500.00 $ 1,950.00<br />

6 Tree Removal 0 LS $ -<br />

7 Tree Trimming 0 LS $ -<br />

8 Protect Gas Monitoring Wells/Adjust<br />

Risers and Valves to Finish Grade<br />

1 LS $5,000.00 $ 5,000.00<br />

9 Rough Grading - Include Surveying 126000 SF $0.65 $ 81,900.00<br />

10 Subgrade Preparation 126000 SF $0.30 $ 37,800.00<br />

11<br />

12<br />

Construct Portland Cement Concrete<br />

Pavement Over Aggregate Base<br />

Decorative Concrete Pavers (N. Ventura<br />

Road Gateway)<br />

126000 SF $8.25 $ 1,039,500.00<br />

1 LS $35,000.00<br />

$ 35,000.00<br />

13 Fine Grade Shoulder 42000 SF $0.50 $ 21,000.00<br />

14 Construct 2' Wide Concrete Traffic Barrier 1 LS $17,000.00 $ 17,000.00<br />

15 Construct Curb and Gutter 450 LF $25.00 $ 11,250.00<br />

16<br />

Provide and Install Mile Marker/<strong>Trail</strong><br />

Medallions<br />

6<br />

EA $300.00 $ 1,800.00<br />

17 Pavement Markings and Striping 1 LS $15,400.00 $ 15,400.00<br />

18 Provide and Install Bollards 4 EA $1,500.00 $ 6,000.00<br />

19 Construct Bench Slab 4 EA $500.00 $ 2,000.00<br />

20 Construct 4-foot Split-Rail Fence 0 LF $15.00 $ -<br />

21 Construct 6-foot High Chain Link Fence 9500 LF $35.00 $ 332,500.00<br />

22<br />

Construct 4-foot High Ornamental Metal<br />

Fence<br />

0<br />

LF $65.00 $ -<br />

23 Construct Double Drive Gate 8 EA $6,200.00 $ 49,600.00<br />

24 Tree Replacement/<strong>Plan</strong>ting 0 LS $5,000.00 $ -<br />

98 | Alta <strong>Plan</strong>ning + Design