COUNCIL MINUTES<br />
TUESDAY 20 DECEMBER 2011<br />
<br />
<br />
<br />
<br />
Halesworth Road - this is scheduled in Year 2 pending the outcome <strong>of</strong> the Wembley<br />
Sports Park plans.<br />
Herdsman Parade - this is scheduled in Year 1 to coincide with resurfacing <strong>of</strong> this<br />
section <strong>of</strong> Herdsman Parade with grant funding. The recent developments on the<br />
north side <strong>of</strong> Herdsman Parade, between Selby Street and Marlow Street has<br />
significantly increased pedestrian traffic.<br />
Teslin Road - this is scheduled in Year 2 since it is a short road with low traffic.<br />
Tilton Terrace - this is scheduled in Year 2 pending community consultation. The<br />
scheduled replacement <strong>of</strong> a short section <strong>of</strong> slab path on Tilton Terrace will depend<br />
on which side the new path is constructed.<br />
2. Replacement <strong>of</strong> Slab Paths - The proposed program for upgrading slab footpaths to<br />
concrete footpaths was developed in consideration <strong>of</strong>:-<br />
There are approximately 23 kilometres <strong>of</strong> slab footpath remaining after June 2012.<br />
At the current funding, all remaining slab footpaths can be upgraded over a 5 year<br />
program at a rate <strong>of</strong> 4.6 kilometres each year.<br />
Condition <strong>of</strong> the existing slab path – the poorest condition rated paths are listed in<br />
the first years <strong>of</strong> the program.<br />
High pedestrian use or high traffic volume on adjacent road.<br />
Paths adjacent to hospitals, schools, commercial centres, recreational centres and<br />
bus stops.<br />
Community requests - Daglish Street, Dodd Street, Station Street, Linden Gardens,<br />
Salvado Road.<br />
Complete the footpaths on whole roads rather than isolated sections.<br />
The remaining sections <strong>of</strong> slab path on Salvado Road are currently deferred to Year 5<br />
until the plans for a shared path on Salvado Road, between Jersey and Haydn Bunton<br />
Drive are known.<br />
POLICY/STATUTORY IMPLICATIONS:<br />
The recommendation is in accordance with <strong>Council</strong> Policy No. 5.2.5 “Footpaths – Upgrading<br />
Of”.<br />
FINANCIAL IMPLICATIONS:<br />
There are no Financial Implications related to this report other than consideration <strong>of</strong> setting<br />
appropriate levels <strong>of</strong> funding for the Draft 2012/13 Budget.<br />
The current 2011/12 Budget provides a total <strong>of</strong>:-<br />
<br />
<br />
<br />
$554,400 for upgrading 5.0 kilometres <strong>of</strong> slab footpaths;<br />
$93,000 for construction <strong>of</strong> 0.75 kilometres <strong>of</strong> new paths; and<br />
$500,000 for the new shared path program.<br />
Total funding is $1,147,000 for the current budget year.<br />